8040-8042 N RANCHITO AVE 91402
Certificate Information: 8040-8042 N RANCHITO AVE 91402
- Application / Permit
- 22014-20000-01220
- Plan Check / Job No.
- B22VN03994
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT 20'-3" X 18'-0" PORTION OF (E) SFD TO JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) AND 65852.22. ADDITION 37'-0" X 25'-5" (IRREGULAR SHAPED) AT 1ST FL AND 29'-6" X 25'-5" AT 2ND FL TO (E) SFD. <NFPA 13-D FIRE SPRINKLER THRU-OUT>
- Permit Issued
- Issued on 12/6/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/2/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2022 | LUISANGEL VALENZUELA |
| Corrections Issued | 4/9/2022 | LUISANGEL VALENZUELA |
| Building Plans Picked Up | 4/14/2022 | APPLICANT |
| Plan Check Approved | 12/6/2023 | ROSENDO MEDINA |
| Issued | 12/6/2023 | APPLICANT |
| CofO in Progress | 12/17/2025 | VINCENT HANLEY |
| Permit Finaled | 1/2/2026 | RUBEN SALAS |
| CofO Issued | 1/2/2026 | RUBEN SALAS |
| Permit Finaled | 1/2/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/22/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 3/13/2023 | CARLOS AGUILERA |
| Miscellaneous | Cleared | 7/13/2023 | NELSON RODRIGUEZ |
| Sewer availability | Cleared | 7/13/2023 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 7/14/2023 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 7/14/2023 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adams,, Robert Charles; Lic. No.: C21234 | 22129 BRYANT STREET CANOGA PARK, CA 91304 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/7/2023 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 12/11/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Footing/Foundation/Slab | 12/11/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 12/11/2023 | Corrections Issued | GREGG CUMMINGS |
| Underground Mechanical | 12/11/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 12/13/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 12/13/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Underground Mechanical | 12/13/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 12/14/2023 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 12/26/2023 | Partial Approval | GREGG CUMMINGS |
| Sewer | 12/26/2023 | Approved | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 12/27/2023 | Approved | MATTHEW NELSON |
| Footing/Foundation/Slab | 12/27/2023 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2024 | Partial Approval | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 4/26/2024 | Corrections Issued | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/26/2024 | Corrections Issued | DAVID MATSON |
| PLUMBING-Rough | 4/29/2024 | Approved | KIRK SANDERS |
| ELECTRICAL-Rough | 6/18/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2024 | Partial Approval | GREGG CUMMINGS |
| HVAC-Rough | 6/18/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Interior/Exterior Lathing | 6/18/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Deputy Wood Construction | 6/20/2024 | Conditional Approval | DAVID MATSON |
| ELECTRICAL-Rough | 7/12/2024 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 7/12/2024 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Rough | 7/12/2024 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 7/31/2024 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2024 | Partial Approval | GREGG CUMMINGS |
| Green Building Rough | 7/31/2024 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 7/31/2024 | Approved | GREGG CUMMINGS |
| Insulation | 8/7/2024 | Corrections Issued | GREGG CUMMINGS |
| Interior/Exterior Lathing | 8/7/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Insulation | 8/9/2024 | Corrections Issued | GREGG CUMMINGS |
| Insulation | 8/14/2024 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 8/22/2024 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 8/22/2024 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 4/10/2025 | Approved | DAVID ANDERSON |
| PLUMBING-Final | 4/10/2025 | Approved | DAVID ANDERSON |
| Service/Power Release | 9/25/2025 | Approved | VINCENT HANLEY |
| Final | 12/16/2025 | OK to Issue CofO | VINCENT HANLEY |
| Green Building Final | 12/16/2025 | Approved | VINCENT HANLEY |
| HVAC-Final | 12/16/2025 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 12/16/2025 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 12/16/2025 | Approved | VINCENT HANLEY |
| Smoke Detectors | 12/16/2025 | Approved | VINCENT HANLEY |