11662 W MARGATE ST 91601

Certificate Information: 11662 W MARGATE ST 91601

Application / Permit
22014-20000-01218
Plan Check / Job No.
B22VN03978
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
IRREGULAR SHAPED ADDITION OF 342 SF, ADDITION OF AN ATT PATIO COVER OF 11' X 14' (155 SF), AND ENCLOSE A 8'-2" X 9'-8" PORTION (79 SF) OF (E) FRONT PORCH, AND INTERIOR REMODEL TO THE (E) SFD. ALL WORK PER ENGINEERING
Permit Issued
Issued on 5/13/2022
Issuing Office
Current Status
CofO Issued on 5/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/23/2022 APPLICANT
Assigned to Plan Check Engineer 3/25/2022 LUISANGEL VALENZUELA
Corrections Issued 3/26/2022 LUISANGEL VALENZUELA
Applicant returned to address corrections 4/4/2022 LUISANGEL VALENZUELA
Plan Check Approved 5/5/2022 LUISANGEL VALENZUELA
Building Plans Picked Up 5/6/2022 APPLICANT
Issued 5/13/2022 APPLICANT
CofO in Progress 5/23/2023 JACK KARGODORIAN
Permit Finaled 5/14/2024 RUBEN SALAS
CofO Issued 5/14/2024 RUBEN SALAS
Permit Finaled 5/14/2024 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/4/2022 CARLOS AGUILERA
Sewer availability Cleared 4/4/2022 CARLOS AGUILERA
ZA Case Cleared 4/7/2022 LOUIS ORTEGA
ZA Case Cleared 4/7/2022 LOUIS ORTEGA
ZI Cleared 4/11/2022 ERIN NASH
ZI Cleared 4/11/2022 ERIN NASH
Roof/Waste drainage to street Cleared 4/27/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/22/2022 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 6/24/2022 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 7/1/2022 Corrections Issued THOMAS FINNILA
Green Building Rough 7/1/2022 Not Ready for Inspection THOMAS FINNILA
MERV13>=Rough 7/1/2022 Not Ready for Inspection THOMAS FINNILA
Wood Frame 8/1/2022 Corrections Issued THOMAS FINNILA
ELECTRICAL-Rough 8/15/2022 Not Ready for Inspection THOMAS FINNILA
HVAC-Rough 8/15/2022 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 8/15/2022 Not Ready for Inspection THOMAS FINNILA
Wood Frame 8/15/2022 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 8/17/2022 Approved THOMAS FINNILA
BUILDING-Rough-Frame 8/22/2022 Corrections Issued JACK KARGODORIAN
ELECTRICAL-Rough 8/22/2022 Not Ready for Inspection JACK KARGODORIAN
Green Building Rough 8/22/2022 Not Ready for Inspection JACK KARGODORIAN
HVAC-Rough 8/22/2022 Not Ready for Inspection JACK KARGODORIAN
MERV13>=Rough 8/22/2022 Not Ready for Inspection JACK KARGODORIAN
ELECTRICAL-Rough 8/24/2022 Not Ready for Inspection CALEB MEISTER
HVAC-Rough 8/24/2022 Not Ready for Inspection CALEB MEISTER
ELECTRICAL-Rough 8/26/2022 Corrections Issued THOMAS FINNILA
HVAC-Rough 8/26/2022 Corrections Issued THOMAS FINNILA
Wood Frame 8/26/2022 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 8/31/2022 Approved THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/11/2022 Corrections Issued CHRISTOPHER DELLEFIELD
HVAC-Rough 10/11/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Insulation 10/19/2022 Not Ready for Inspection JACK KARGODORIAN
Interior/Exterior Lathing 10/19/2022 Partial Approval JACK KARGODORIAN
Shower Pan 10/19/2022 Approved JACK KARGODORIAN
Wood Frame 10/19/2022 Corrections Issued JACK KARGODORIAN
Interior/Exterior Lathing 10/31/2022 Approved JACK KARGODORIAN
Wood Frame 10/31/2022 Approved JACK KARGODORIAN
Insulation 11/7/2022 Approved JACK KARGODORIAN
Drywall Nailing 11/21/2022 Approved CHRISTOPHE COCHRAN
Green Building Rough 11/21/2022 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 3/31/2023 Corrections Issued JACK KARGODORIAN
HVAC-Final 3/31/2023 Corrections Issued JACK KARGODORIAN
Service/Power Release 3/31/2023 Not Ready for Inspection JACK KARGODORIAN
BUILDING-Rough-Frame 4/14/2023 Approved JACK KARGODORIAN
ELECTRICAL-Final 4/14/2023 Approved JACK KARGODORIAN
Final 4/14/2023 Conditional Approval JACK KARGODORIAN
Green Building Final 4/14/2023 Approved JACK KARGODORIAN
HVAC-Final 4/14/2023 Approved JACK KARGODORIAN
MERV13>=Final 4/14/2023 Approved JACK KARGODORIAN
MERV13>=Rough 4/14/2023 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 4/14/2023 SGSOV Approved JACK KARGODORIAN
Service/Power Release 4/14/2023 Approved JACK KARGODORIAN
Smoke Detectors 4/14/2023 Approved JACK KARGODORIAN
Final 4/20/2023 Corrections Issued JACK KARGODORIAN
Final 5/16/2023 Not Ready for Inspection JACK KARGODORIAN
Final 5/22/2023 OK to Issue CofO JACK KARGODORIAN