5035 N ZELZAH AVE 91316

Certificate Information: 5035 N ZELZAH AVE 91316

Application / Permit
22014-20000-01209
Plan Check / Job No.
B22VN03960
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
726.7 SQ. FT. ADDITION OF BEDROOMS, BATHROOMS, PANTRY, LAUNDRY AND KITCHEN. ALL WORK PER ENGINEER. NFPA-13D FIRE SPRINKLER THRU-OUT.
Permit Issued
Issued on 9/12/2022
Issuing Office
Valley
Current Status
Issued on 9/12/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/18/2022 APPLICANT
Assigned to Plan Check Engineer 3/25/2022 PINANK PATEL
Corrections Issued 3/27/2022 PINANK PATEL
Applicant returned to address corrections 6/24/2022 PINANK PATEL
Applicant returned to address corrections 7/8/2022 PINANK PATEL
Building Plans Picked Up 7/11/2022 APPLICANT
Plan Check Approved 7/29/2022 YAQUB MIRZA
Issued 9/12/2022 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/19/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 4/19/2022 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 5/6/2022 DWAYNE LAURENT
Low Impact Development Cleared 6/16/2022 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 6/16/2022 JOHN LIN
Grading Pre-Inspection Cleared 6/26/2022 PINANK PATEL
GPI Written Notices Cleared 7/29/2022 PINANK PATEL

Contact Information

Contractor G S Tingling; Lic. No.: 952884-B 15425 SHERMAN WY #226      VAN NUYS, CA 91406
Engineer Gonzalez,, Fernando Francisco; Lic. No.: C53256 11607 AMESTOY AVE      GRANADA HILLS, CA 91344

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/23/2022 Approved DAVID SANDOVAL
Footing/Foundation/Slab 10/14/2022 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Rough 10/14/2022 Corrections Issued DAVID SANDOVAL
Footing/Foundation/Slab 10/21/2022 Corrections Issued SEAN WIRCH
PLUMBING-Rough 10/21/2022 Partial Approval SEAN WIRCH
Special/Order Compliance 10/21/2022 Corrections Issued SEAN WIRCH
Deputy Drilled-In Anchors 11/1/2022 Approved SEAN WIRCH
Footing/Foundation/Slab 11/4/2022 No Access for Inspection VINCENT HANLEY
Footing/Foundation/Slab 11/9/2022 Conditional Approval DAVID SANDOVAL
Deputy Drilled-In Anchors 1/26/2023 No Access for Inspection DAVID SANDOVAL
Footing/Foundation/Slab 5/3/2023 Not Ready for Inspection SEAN HAUPT
PLUMBING-Rough 5/3/2023 Not Ready for Inspection SEAN HAUPT
BUILDING-Rough-Frame 5/9/2023 Corrections Issued SEAN HAUPT
ELECTRICAL-Rough 5/9/2023 Not Ready for Inspection SEAN HAUPT
Green Building Rough 5/9/2023 Not Ready for Inspection SEAN HAUPT
HVAC-Rough 5/9/2023 Not Ready for Inspection SEAN HAUPT
PLUMBING-Rough 5/9/2023 Not Ready for Inspection SEAN HAUPT
BUILDING-Rough-Frame 5/19/2023 Corrections Issued SEAN HAUPT
ELECTRICAL-Rough 5/19/2023 Corrections Issued SEAN HAUPT
Green Building Rough 5/19/2023 Not Ready for Inspection SEAN HAUPT
PLUMBING-Rough 5/19/2023 Corrections Issued SEAN HAUPT
BUILDING-Rough-Frame 7/18/2023 Corrections Issued SEAN HAUPT
ELECTRICAL-Rough 7/18/2023 Partial Approval SEAN HAUPT
Green Building Rough 7/18/2023 Not Ready for Inspection SEAN HAUPT
PLUMBING-Rough 7/18/2023 Approved SEAN HAUPT
BUILDING-Rough-Frame 8/9/2023 Not Ready for Inspection SEAN HAUPT
ELECTRICAL-Rough 8/9/2023 Not Ready for Inspection SEAN HAUPT
Green Building Rough 8/9/2023 Not Ready for Inspection SEAN HAUPT
PLUMBING-Rough 8/9/2023 Approved SEAN HAUPT
Pre-Inspection 8/11/2023 Corrections Issued SEAN WIRCH
BUILDING-Rough-Frame 8/23/2023 Not Ready for Inspection SEAN HAUPT
ELECTRICAL-Rough 8/23/2023 Not Ready for Inspection SEAN HAUPT
Green Building Rough 8/23/2023 Approved SEAN HAUPT
Interior/Exterior Lathing 8/23/2023 Approved SEAN HAUPT
PLUMBING-Rough 8/23/2023 Approved SEAN HAUPT
BUILDING-Rough-Frame 8/25/2023 Approved MORRIS JACKSON
ELECTRICAL-Rough 8/25/2023 Approved MORRIS JACKSON
Insulation 8/30/2023 Approved SEAN HAUPT
Drywall Nailing 9/6/2023 Approved SEAN HAUPT