14015 W SYLVAN ST 91401
Certificate Information: 14015 W SYLVAN ST 91401
- Application / Permit
- 22014-20000-01200
- Plan Check / Job No.
- B22VN03933
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 46'-2" X 29'-5" ADDITION OF AN ACCESSORY DWELLING UNIT TO EXISTING DETACHED GARAGE PER LAMC 12.22 A.33(c) AND (d) - ALL WORK PER WFPP
- Permit Issued
- Issued on 4/19/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2022 | DANIEL ABRAMYAN |
| Corrections Issued | 3/26/2022 | DANIEL ABRAMYAN |
| Plan Check Approved | 5/26/2022 | DANIEL ABRAMYAN |
| Building Plans Picked Up | 5/31/2022 | APPLICANT |
| Issued | 4/19/2024 | APPLICANT |
| CofO in Progress | 1/24/2025 | RYAN SALAZAR |
| Permit Finaled | 2/4/2025 | RUBEN SALAS |
| CofO Issued | 2/4/2025 | RUBEN SALAS |
| Permit Finaled | 2/4/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/2/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/5/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 4/5/2022 | JOSE DUARTE-DIAZ |
| Low Impact Development | Cleared | 5/12/2022 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 5/17/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/19/2024 | Approved | RYAN SALAZAR |
| Deputy Drilled-In Anchors | 8/22/2024 | Conditional Approval | ROBERT GOLD |
| PLUMBING-Rough | 8/23/2024 | Partial Approval | RYAN SALAZAR |
| Excavation/Setback/Form/Re-Bar | 8/27/2024 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 9/12/2024 | Partial Approval | RYAN SALAZAR |
| ELECTRICAL-Rough | 9/12/2024 | Approved | RYAN SALAZAR |
| Green Building Rough | 9/12/2024 | Approved | RYAN SALAZAR |
| HVAC-Rough | 9/12/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 9/12/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Gas Test | 9/16/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 9/16/2024 | Approved | RYAN SALAZAR |
| Insulation | 9/24/2024 | Conditional Approval | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 9/24/2024 | Partial Approval | SALVADOR MARTINEZ |
| Drywall Nailing | 9/27/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 10/17/2024 | Approved | RYAN SALAZAR |
| Shower Pan | 10/17/2024 | Approved | RYAN SALAZAR |
| Underground Mechanical | 12/2/2024 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 1/23/2025 | Approved | RYAN SALAZAR |
| Final | 1/23/2025 | OK to Issue CofO | RYAN SALAZAR |
| Footing/Foundation/Slab | 1/23/2025 | Approved | RYAN SALAZAR |
| Green Building Final | 1/23/2025 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 1/23/2025 | SGSOV Approved | RYAN SALAZAR |
| Service/Power Release | 1/23/2025 | Approved | RYAN SALAZAR |
| Smoke Detectors | 1/23/2025 | Approved | RYAN SALAZAR |