7846 N VANTAGE AVE 91605
Certificate Information: 7846 N VANTAGE AVE 91605
- Application / Permit
- 22014-20000-01198
- Plan Check / Job No.
- B22VN03930
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED 17'-3" x 18'-3" ADDITION TO AND CONVERT (E) 20'-3" X 17'-6" DETACHED GARAGE INTO A NEW ACCESSORY DWELLING UNIT (669.44 SQ. FT. TOTAL) PER LAMC 12.22 A.33 (c) and (d). AND (N) 3' X 10'-9" ATTACHED PATIO COVER PER P/BC 2020-006. - ALL WORK PER WFPP
- Permit Issued
- Issued on 5/16/2023
- Issuing Office
- Current Status
- CofO Issued on 1/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2022 | ALEC MOUSAKHANIAN |
| Corrections Issued | 8/20/2022 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 10/5/2022 | SARKIS HARABEDIAN |
| Applicant returned to address corrections | 1/19/2023 | DANIEL ABRAMYAN |
| Plan Check Approved | 1/22/2023 | DANIEL ABRAMYAN |
| Issued | 5/16/2023 | APPLICANT |
| CofO in Progress | 12/15/2023 | MATTHEW NELSON |
| Permit Finaled | 1/3/2024 | RUBEN SALAS |
| CofO Issued | 1/3/2024 | RUBEN SALAS |
| Permit Finaled | 1/3/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/26/2022 | ROMAN GUTIERREZ |
| Roof/Waste drainage to street | Cleared | 8/26/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/7/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 9/7/2022 | ROMAN GUTIERREZ |
| Construction near power lines | Cleared | 1/12/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Next Generation Builders; Lic. No.: 1069728-B | , |
| Contractor | Polymath Development Group Inc; Lic. No.: 1069728-B | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/15/2023 | Partial Approval | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 6/23/2023 | Approved | MATTHEW NELSON |
| Footing/Foundation/Slab | 6/23/2023 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 8/10/2023 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2023 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 8/10/2023 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 8/21/2023 | Approved | WILLIAM WREN |
| Green Building Rough | 8/21/2023 | Approved | WILLIAM WREN |
| HVAC-Rough | 8/21/2023 | Corrections Issued | WILLIAM WREN |
| Deputy Wood Construction | 8/24/2023 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 8/28/2023 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 8/28/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 8/28/2023 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 8/28/2023 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 8/31/2023 | Conditional Approval | WILLIAM WREN |
| Drywall Nailing | 9/7/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 9/11/2023 | Approved | WILLIAM WREN |
| Shower Pan | 9/11/2023 | Approved | WILLIAM WREN |
| Final | 12/8/2023 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 12/8/2023 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 12/8/2023 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 12/8/2023 | Approved | MATTHEW NELSON |
| Final | 12/14/2023 | OK to Issue CofO | MATTHEW NELSON |