7846 N VANTAGE AVE 91605

Certificate Information: 7846 N VANTAGE AVE 91605

Application / Permit
22014-20000-01198
Plan Check / Job No.
B22VN03930
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 17'-3" x 18'-3" ADDITION TO AND CONVERT (E) 20'-3" X 17'-6" DETACHED GARAGE INTO A NEW ACCESSORY DWELLING UNIT (669.44 SQ. FT. TOTAL) PER LAMC 12.22 A.33 (c) and (d). AND (N) 3' X 10'-9" ATTACHED PATIO COVER PER P/BC 2020-006. - ALL WORK PER WFPP
Permit Issued
Issued on 5/16/2023
Issuing Office
Current Status
CofO Issued on 1/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/16/2022 APPLICANT
Assigned to Plan Check Engineer 8/19/2022 ALEC MOUSAKHANIAN
Corrections Issued 8/20/2022 ALEC MOUSAKHANIAN
Applicant returned to address corrections 10/5/2022 SARKIS HARABEDIAN
Applicant returned to address corrections 1/19/2023 DANIEL ABRAMYAN
Plan Check Approved 1/22/2023 DANIEL ABRAMYAN
Issued 5/16/2023 APPLICANT
CofO in Progress 12/15/2023 MATTHEW NELSON
Permit Finaled 1/3/2024 RUBEN SALAS
CofO Issued 1/3/2024 RUBEN SALAS
Permit Finaled 1/3/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/26/2022 ROMAN GUTIERREZ
Roof/Waste drainage to street Cleared 8/26/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 9/7/2022 ROMAN GUTIERREZ
Sewer availability Cleared 9/7/2022 ROMAN GUTIERREZ
Construction near power lines Cleared 1/12/2023 RIDWAN HARDY

Contact Information

Contractor Next Generation Builders; Lic. No.: 1069728-B       ,
Contractor Polymath Development Group Inc; Lic. No.: 1069728-B       ,

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/15/2023 Partial Approval MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 6/23/2023 Approved MATTHEW NELSON
Footing/Foundation/Slab 6/23/2023 Approved MATTHEW NELSON
ELECTRICAL-Rough 8/10/2023 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 8/10/2023 Approved MATTHEW NELSON
PLUMBING-Rough 8/10/2023 Approved MATTHEW NELSON
BUILDING-Rough-Frame 8/21/2023 Approved WILLIAM WREN
Green Building Rough 8/21/2023 Approved WILLIAM WREN
HVAC-Rough 8/21/2023 Corrections Issued WILLIAM WREN
Deputy Wood Construction 8/24/2023 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 8/28/2023 Approved JENNIFER RABUCHIN
Green Building Rough 8/28/2023 Approved JENNIFER RABUCHIN
HVAC-Rough 8/28/2023 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 8/28/2023 Partial Approval JENNIFER RABUCHIN
Insulation 8/31/2023 Conditional Approval WILLIAM WREN
Drywall Nailing 9/7/2023 Approved DAVID ANDERSON
Interior/Exterior Lathing 9/11/2023 Approved WILLIAM WREN
Shower Pan 9/11/2023 Approved WILLIAM WREN
Final 12/8/2023 Corrections Issued MATTHEW NELSON
Green Building Final 12/8/2023 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 12/8/2023 SGSOV Approved MATTHEW NELSON
Smoke Detectors 12/8/2023 Approved MATTHEW NELSON
Final 12/14/2023 OK to Issue CofO MATTHEW NELSON