6102 E ROY ST 90042
Certificate Information: 6102 E ROY ST 90042
- Application / Permit
- 22014-20000-01197
- Plan Check / Job No.
- B22VN03929
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT/ RE-FRAME (E) DETACHED GARAGE WITH ADDITION ( 13'-5" X 6'-7" ) INTO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (d). REMOVE 7'-6" X 5'-6" PORTION OF BLDG. WORK PER ENGINEER.
- Permit Issued
- Issued on 6/15/2022
- Issuing Office
- Current Status
- CofO Issued on 3/22/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2022 | ROSENDO MEDINA |
| Corrections Issued | 3/26/2022 | ROSENDO MEDINA |
| Applicant returned to address corrections | 6/1/2022 | ROSENDO MEDINA |
| Plan Check Approved | 6/14/2022 | ROSENDO MEDINA |
| Issued | 6/15/2022 | APPLICANT |
| Building Plans Picked Up | 6/16/2022 | APPLICANT |
| CofO in Progress | 3/14/2023 | CRAIG VAUGHAN |
| CofO Issued | 3/22/2023 | DEROLD HAUFF |
| Permit Finaled | 3/22/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/20/2022 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 4/20/2022 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 4/22/2022 | WALLIE JONG |
| Sewer availability | Cleared | 4/22/2022 | WALLIE JONG |
| Grading Pre-Inspection | Cleared | 5/17/2022 | KIRK LINKLATER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nazarians,, Harmick Edward; Lic. No.: C91232 | 9825 OSO AVE CHATSWORTH, CA 91311 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/26/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Gas Test | 8/26/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 8/26/2022 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 9/15/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 10/11/2022 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2022 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2022 | Approved | RUBEN SALAS |
| Interior/Exterior Lathing | 11/18/2022 | Not Ready for Inspection | RUBEN SALAS |
| BUILDING-Rough-Frame | 11/30/2022 | Partial Approval | CRAIG VAUGHAN |
| Deputy Drilled-In Anchors | 11/30/2022 | Conditional Approval | CRAIG VAUGHAN |
| Green Building Rough | 11/30/2022 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 11/30/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Rough-Elec/Plmb/HVAC | 11/30/2022 | Approved | CRAIG VAUGHAN |
| Shower Pan | 11/30/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Insulation | 12/8/2022 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 12/8/2022 | Partial Approval | CRAIG VAUGHAN |
| Shower Pan | 12/8/2022 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 12/15/2022 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 12/15/2022 | Approved | CRAIG VAUGHAN |
| Final | 1/26/2023 | Corrections Issued | CRAIG VAUGHAN |
| Gas Test | 1/26/2023 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 2/2/2023 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 2/2/2023 | Approved | CRAIG VAUGHAN |
| Final | 2/2/2023 | Partial Inspection | CRAIG VAUGHAN |
| Green Building Final | 2/2/2023 | Approved | CRAIG VAUGHAN |
| HVAC-Final | 2/2/2023 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 2/2/2023 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 2/2/2023 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 2/2/2023 | Approved | CRAIG VAUGHAN |
| Final | 2/3/2023 | Corrections Issued | CRAIG VAUGHAN |
| Final | 3/13/2023 | OK to Issue CofO | CRAIG VAUGHAN |