8270 N REDBUSH LANE 91402
Certificate Information: 8270 N REDBUSH LANE 91402
- Application / Permit
- 22014-20000-01191
- Plan Check / Job No.
- B22VN03917
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan. Second story addition to an (E) 1-story SFD and conversion of the new addition into an ADU. Attached ADU per ordinance 186,481.
- Permit Issued
- Issued on 1/26/2023
- Issuing Office
- Current Status
- CofO Issued on 7/21/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/5/2022 | KELVIN CHUONG |
| Corrections Issued | 5/18/2022 | HELEN NGUYEN |
| Quality Review Completed | 6/8/2022 | MICHAEL PEREZ |
| Plan Check Approved | 10/5/2022 | KELVIN CHUONG |
| Issued | 1/26/2023 | APPLICANT |
| CofO in Progress | 6/3/2026 | OGANES TARAKHCHYAN |
| Permit Finaled | 7/21/2026 | DANIEL ORRANTE |
| CofO Issued | 7/21/2026 | DANIEL ORRANTE |
| Permit Finaled | 7/21/2026 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 5/26/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/26/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 5/26/2022 | MEGAN GODINEZ |
| Low Impact Development | Cleared | 8/18/2022 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 8/24/2022 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 8/24/2022 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 8/24/2022 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 8/24/2022 | MEGAN GODINEZ |
Contact Information
| Contractor | Markarian Setrag; Lic. No.: 832632-B | , |
| Contractor | Pampa Investment Inc; Lic. No.: 832632-B | , |
| Engineer | Moser,, Bradley Charles; Lic. No.: C68803 | 116 OAKSIDE LN BUELLTON, CA 93427 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/13/2023 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 3/8/2023 | Partial Approval | MATTHEW NELSON |
| Footing/Foundation/Slab | 3/14/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Excavation/Setback/Form/Re-Bar | 3/16/2023 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| Excavation/Setback/Form/Re-Bar | 3/17/2023 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2023 | Partial Approval | GREGG CUMMINGS |
| Green Building Rough | 6/27/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 6/27/2023 | SGSOV Not Ready | GREGG CUMMINGS |
| Wood Frame | 6/27/2023 | Partial Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 8/1/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2023 | Partial Approval | GREGG CUMMINGS |
| Green Building Rough | 8/1/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Wood Frame | 8/28/2023 | No Access for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 9/1/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 9/1/2023 | Partial Approval | GREGG CUMMINGS |
| Green Building Rough | 9/1/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 9/1/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 9/1/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 9/20/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 9/20/2023 | No Access for Inspection | GREGG CUMMINGS |
| Rough-Elec/Plmb/HVAC | 9/20/2023 | No Access for Inspection | GREGG CUMMINGS |
| Wood Frame | 9/20/2023 | No Access for Inspection | GREGG CUMMINGS |
| Insulation | 9/22/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Shower Pan | 9/22/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Wood Frame | 9/22/2023 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 9/26/2023 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 9/26/2023 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 9/26/2023 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 9/29/2023 | Partial Approval | GREGG CUMMINGS |
| Green Building Rough | 9/29/2023 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 9/29/2023 | Corrections Issued | GREGG CUMMINGS |
| Interior/Exterior Lathing | 9/29/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Insulation | 10/3/2023 | Corrections Issued | GREGG CUMMINGS |
| Shower Pan | 10/3/2023 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 10/5/2023 | Approved | GREGG CUMMINGS |
| HVAC-Final | 10/5/2023 | Corrections Issued | GREGG CUMMINGS |
| Insulation | 10/5/2023 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 10/11/2023 | Approved | DAVID MATSON |
| Interior/Exterior Lathing | 10/11/2023 | Partial Approval | DAVID MATSON |
| ELECTRICAL-Final | 1/3/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 1/3/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 1/3/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Final | 1/3/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 1/3/2024 | SGSOV Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 1/3/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 3/6/2026 | Corrections Issued | OGANES TARAKHCHYAN |
| Final | 5/6/2026 | Corrections Issued | DAVID MATSON |
| Footing/Foundation/Slab | 5/6/2026 | Not Ready for Inspection | DAVID MATSON |
| Green Building Final | 5/6/2026 | Not Ready for Inspection | DAVID MATSON |
| Final | 6/1/2026 | OK to Issue CofO | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 6/1/2026 | Approved | OGANES TARAKHCHYAN |
| Green Building Final | 6/1/2026 | Approved | OGANES TARAKHCHYAN |