8270 N REDBUSH LANE 91402

Certificate Information: 8270 N REDBUSH LANE 91402

Application / Permit
22014-20000-01191
Plan Check / Job No.
B22VN03917
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan. Second story addition to an (E) 1-story SFD and conversion of the new addition into an ADU. Attached ADU per ordinance 186,481.
Permit Issued
Issued on 1/26/2023
Issuing Office
Current Status
CofO Issued on 7/21/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/5/2022 APPLICANT
Assigned to Plan Check Engineer 5/5/2022 KELVIN CHUONG
Corrections Issued 5/18/2022 HELEN NGUYEN
Quality Review Completed 6/8/2022 MICHAEL PEREZ
Plan Check Approved 10/5/2022 KELVIN CHUONG
Issued 1/26/2023 APPLICANT
CofO in Progress 6/3/2026 OGANES TARAKHCHYAN
Permit Finaled 7/21/2026 DANIEL ORRANTE
CofO Issued 7/21/2026 DANIEL ORRANTE
Permit Finaled 7/21/2026 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 5/26/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 5/26/2022 MEGAN GODINEZ
Sewer availability Cleared 5/26/2022 MEGAN GODINEZ
Low Impact Development Cleared 8/18/2022 MITESH PATEL
Roof/Waste drainage to street Cleared 8/24/2022 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 8/24/2022 MEGAN GODINEZ
Public Works-Open Permits Cleared 8/24/2022 MEGAN GODINEZ
Public Works-Sewers Cleared 8/24/2022 MEGAN GODINEZ

Contact Information

Contractor Markarian Setrag; Lic. No.: 832632-B       ,
Contractor Pampa Investment Inc; Lic. No.: 832632-B       ,
Engineer Moser,, Bradley Charles; Lic. No.: C68803 116 OAKSIDE LN      BUELLTON, CA 93427

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/13/2023 Approved GREGG CUMMINGS
Footing/Foundation/Slab 3/8/2023 Partial Approval MATTHEW NELSON
Footing/Foundation/Slab 3/14/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Excavation/Setback/Form/Re-Bar 3/16/2023 No Access for Inspection CHRISTOPHER DELLEFIELD
Excavation/Setback/Form/Re-Bar 3/17/2023 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 6/27/2023 Partial Approval GREGG CUMMINGS
Green Building Rough 6/27/2023 Not Ready for Inspection GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 6/27/2023 SGSOV Not Ready GREGG CUMMINGS
Wood Frame 6/27/2023 Partial Approval GREGG CUMMINGS
BUILDING-Rough-Frame 8/1/2023 Not Ready for Inspection GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 8/1/2023 Partial Approval GREGG CUMMINGS
Green Building Rough 8/1/2023 Not Ready for Inspection GREGG CUMMINGS
Wood Frame 8/28/2023 No Access for Inspection GREGG CUMMINGS
ELECTRICAL-Rough 9/1/2023 Not Ready for Inspection GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 9/1/2023 Partial Approval GREGG CUMMINGS
Green Building Rough 9/1/2023 Not Ready for Inspection GREGG CUMMINGS
HVAC-Rough 9/1/2023 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 9/1/2023 Not Ready for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 9/20/2023 Not Ready for Inspection GREGG CUMMINGS
Green Building Rough 9/20/2023 No Access for Inspection GREGG CUMMINGS
Rough-Elec/Plmb/HVAC 9/20/2023 No Access for Inspection GREGG CUMMINGS
Wood Frame 9/20/2023 No Access for Inspection GREGG CUMMINGS
Insulation 9/22/2023 Not Ready for Inspection THOMAS FINNILA
Shower Pan 9/22/2023 Not Ready for Inspection THOMAS FINNILA
Wood Frame 9/22/2023 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 9/26/2023 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Rough 9/26/2023 Approved GREGG CUMMINGS
PLUMBING-Rough 9/26/2023 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 9/29/2023 Partial Approval GREGG CUMMINGS
Green Building Rough 9/29/2023 Approved GREGG CUMMINGS
HVAC-Rough 9/29/2023 Corrections Issued GREGG CUMMINGS
Interior/Exterior Lathing 9/29/2023 Not Ready for Inspection GREGG CUMMINGS
Insulation 10/3/2023 Corrections Issued GREGG CUMMINGS
Shower Pan 10/3/2023 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 10/5/2023 Approved GREGG CUMMINGS
HVAC-Final 10/5/2023 Corrections Issued GREGG CUMMINGS
Insulation 10/5/2023 Approved GREGG CUMMINGS
Drywall Nailing 10/11/2023 Approved DAVID MATSON
Interior/Exterior Lathing 10/11/2023 Partial Approval DAVID MATSON
ELECTRICAL-Final 1/3/2024 Corrections Issued CHRISTOPHER ROJAS
Final 1/3/2024 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 1/3/2024 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Final 1/3/2024 Corrections Issued CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 1/3/2024 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 1/3/2024 Approved CHRISTOPHER ROJAS
Final 3/6/2026 Corrections Issued OGANES TARAKHCHYAN
Final 5/6/2026 Corrections Issued DAVID MATSON
Footing/Foundation/Slab 5/6/2026 Not Ready for Inspection DAVID MATSON
Green Building Final 5/6/2026 Not Ready for Inspection DAVID MATSON
Final 6/1/2026 OK to Issue CofO OGANES TARAKHCHYAN
Footing/Foundation/Slab 6/1/2026 Approved OGANES TARAKHCHYAN
Green Building Final 6/1/2026 Approved OGANES TARAKHCHYAN