11478 W SATICOY ST 91605

Certificate Information: 11478 W SATICOY ST 91605

Application / Permit
22014-20000-01189
Plan Check / Job No.
B22VN03916
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2-STORY ADU PER LAMC 12.22 A.33 WITH ATTACHED PATIO COVERED.
Permit Issued
Issued on 12/14/2022
Issuing Office
Valley
Current Status
CofO Issued on 4/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/15/2022 APPLICANT
Assigned to Plan Check Engineer 4/14/2022 MAHNAZ NOURHASHEMI
Corrections Issued 4/21/2022 MAHNAZ NOURHASHEMI
Quality Review Completed 4/27/2022 SAI KHUM
Building Plans Picked Up 5/2/2022 APPLICANT
Applicant returned to address corrections 6/16/2022 MAHNAZ NOURHASHEMI
Plan Check Approved 12/5/2022 MAHNAZ NOURHASHEMI
Issued 12/14/2022 APPLICANT
CofO in Progress 3/14/2024 JOHN HAYES
Permit Finaled 4/3/2024 RUBEN SALAS
CofO Issued 4/3/2024 RUBEN SALAS
Permit Finaled 4/3/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/22/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 8/2/2022 ROSE MARIE SMITH
Low Impact Development Cleared 8/2/2022 MITESH PATEL
Sewer availability Cleared 8/2/2022 ROSE MARIE SMITH
Roof/Waste drainage to street Cleared 8/16/2022 COLIN LOREDO
Hydrant and Access approval Cleared 9/1/2022 GILBERT URREA
Construction near power lines Cleared 12/2/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Dominguez,, Refugio; Lic. No.: C50820 254 COTTONWOOD ST      ONTARIO, CA 91761

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/13/2023 Partial Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 2/16/2023 Corrections Issued MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 2/22/2023 Corrections Issued JOHN HAYES
Excavation/Setback/Form/Re-Bar 2/28/2023 Approved JOHN HAYES
ELECTRICAL-Rough 3/28/2023 Not Ready for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 3/28/2023 Not Ready for Inspection JOHN HAYES
HVAC-Rough 3/28/2023 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 3/28/2023 Not Ready for Inspection JOHN HAYES
Rough-Elec/Plmb/HVAC 3/28/2023 Not Ready for Inspection JOHN HAYES
Wood Frame 3/28/2023 Corrections Issued JOHN HAYES
BUILDING-Rough-Frame 5/3/2023 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 5/3/2023 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 5/3/2023 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 5/10/2023 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Rough 5/10/2023 Approved JOHN HAYES
Green Building Rough 5/10/2023 Not Ready for Inspection JOHN HAYES
HVAC-Rough 5/10/2023 Approved JOHN HAYES
PLUMBING-Rough 5/10/2023 Approved JOHN HAYES
Verify Sprinkler Sign Off 5/10/2023 Approved JOHN HAYES
BUILDING-Rough-Frame 5/18/2023 Approved JENNIFER RABUCHIN
Green Building Rough 5/18/2023 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 5/18/2023 Partial Approval JENNIFER RABUCHIN
Shower Pan 5/18/2023 Corrections Issued JENNIFER RABUCHIN
Underground Mechanical 5/18/2023 Partial Approval JENNIFER RABUCHIN
Gas Test 5/24/2023 Partial Approval JENNIFER RABUCHIN
Insulation 5/24/2023 Corrections Issued JENNIFER RABUCHIN
Shower Pan 5/24/2023 Approved JENNIFER RABUCHIN
Insulation 6/2/2023 Approved JENNIFER RABUCHIN
Shower Pan 6/2/2023 Approved JENNIFER RABUCHIN
Drywall Nailing 6/12/2023 Approved DAVID ANDERSON
Interior/Exterior Lathing 6/12/2023 Approved DAVID ANDERSON
Final 7/21/2023 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 7/21/2023 Approved JOHN HAYES
Green Building Final 7/21/2023 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 7/21/2023 SGSOV Not Ready JOHN HAYES
Service/Power Release 7/21/2023 Not Ready for Inspection JOHN HAYES
Smoke Detectors 7/21/2023 Approved JOHN HAYES
ELECTRICAL-Final 2/28/2024 Not Ready for Inspection JOHN HAYES
Final 2/28/2024 Corrections Issued JOHN HAYES
HVAC-Final 2/28/2024 Not Ready for Inspection JOHN HAYES
PLUMBING-Final 2/28/2024 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 2/28/2024 SGSOV Approved JOHN HAYES
Service/Power Release 2/28/2024 Not Ready for Inspection JOHN HAYES
Final 3/4/2024 OK to Issue CofO JOHN HAYES
Service/Power Release 3/4/2024 Approved JOHN HAYES