11480 W SATICOY ST 91605
Certificate Information: 11480 W SATICOY ST 91605
- Application / Permit
- 22014-20000-01188
- Plan Check / Job No.
- B22VN03916
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- GROUND FLOOR ADDITION TO (E) 1-STORY SFD
- Permit Issued
- Issued on 12/14/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/14/2022 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 4/21/2022 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 4/27/2022 | SAI KHUM |
| Building Plans Picked Up | 5/2/2022 | APPLICANT |
| Applicant returned to address corrections | 6/16/2022 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 12/5/2022 | MAHNAZ NOURHASHEMI |
| Issued | 12/14/2022 | APPLICANT |
| CofO in Progress | 3/14/2024 | JOHN HAYES |
| Permit Finaled | 4/3/2024 | DANIEL ORRANTE |
| CofO Issued | 4/3/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/3/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2022 | ROSE MARIE SMITH |
| Low Impact Development | Cleared | 8/2/2022 | MITESH PATEL |
| Low Impact Development | Cleared | 8/2/2022 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 8/15/2022 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Dominguez,, Refugio; Lic. No.: C50820 | 254 COTTONWOOD ST ONTARIO, CA 91761 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/7/2023 | Corrections Issued | JOHN HAYES |
| Pre-Inspection | 8/7/2023 | Not Ready for Inspection | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 8/23/2023 | Corrections Issued | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 9/12/2023 | Approved | JOHN HAYES |
| Deck | 9/25/2023 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 9/25/2023 | Approved | JOHN HAYES |
| Insulation | 9/25/2023 | Corrections Issued | JOHN HAYES |
| BUILDING-Rough-Frame | 9/29/2023 | Partial Approval | JOHN HAYES |
| Underground Mechanical | 9/29/2023 | Approved | JOHN HAYES |
| Insulation | 10/4/2023 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2023 | Partial Approval | JENNIFER RABUCHIN |
| Special/Order Compliance | 10/18/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 11/16/2023 | Not Ready for Inspection | JOSE AVILA |
| PLUMBING-Rough | 11/16/2023 | Not Ready for Inspection | JOSE AVILA |
| Special/Order Compliance | 11/16/2023 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 12/11/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| HVAC-Rough | 12/11/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 12/11/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 12/11/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Special/Order Compliance | 12/11/2023 | Partial Approval | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 12/14/2023 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 12/14/2023 | Approved | JOHN HAYES |
| Green Building Rough | 12/14/2023 | Approved | JOHN HAYES |
| HVAC-Rough | 12/14/2023 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 12/14/2023 | Partial Approval | JOHN HAYES |
| PLUMBING-Rough | 12/14/2023 | Approved | JOHN HAYES |
| Insulation | 12/19/2023 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 12/27/2023 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 12/27/2023 | Approved | JOHN HAYES |
| Shower Pan | 12/27/2023 | Approved | JOHN HAYES |
| Special/Order Compliance | 12/27/2023 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Final | 2/28/2024 | Not Ready for Inspection | JOHN HAYES |
| Final | 2/28/2024 | Corrections Issued | JOHN HAYES |
| Green Building Final | 2/28/2024 | Approved | JOHN HAYES |
| HVAC-Final | 2/28/2024 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Final | 2/28/2024 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 2/28/2024 | SGSOV Approved | JOHN HAYES |
| Service/Power Release | 2/28/2024 | Not Ready for Inspection | JOHN HAYES |
| Smoke Detectors | 2/28/2024 | Approved | JOHN HAYES |
| Final | 3/4/2024 | OK to Issue CofO | JOHN HAYES |