6212 E HILLANDALE DR 90042

Certificate Information: 6212 E HILLANDALE DR 90042

Application / Permit
22014-20000-01169
Plan Check / Job No.
B22VN03836
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
16'-1 1/2" X 19'-2 IRREGULAR SHAPED ADDITION TO THE REAR OF THE (E) SFD AND 8'-4 1/2" X 6'9" ATTACHED DECK. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 7/13/2022
Issuing Office
Current Status
CofO Issued on 11/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/14/2022 APPLICANT
Assigned to Plan Check Engineer 3/15/2022 OMAR GARNICA
Corrections Issued 3/15/2022 OMAR GARNICA
Applicant returned to address corrections 5/11/2022 OMAR GARNICA
Plan Check Approved 6/29/2022 OMAR GARNICA
Building Plans Picked Up 6/30/2022 APPLICANT
Issued 7/13/2022 APPLICANT
CofO in Progress 10/30/2024 LILIANA PORTILLO
Permit Finaled 11/4/2024 DEROLD HAUFF
CofO Issued 11/4/2024 DEROLD HAUFF
Permit Finaled 11/4/2024 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/21/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 5/18/2022 AMAAN MALIK
Grading Pre-Inspection Cleared 6/15/2022 MANUEL TEJADA

Contact Information

Contractor Vision Home Remodeling Inc; Lic. No.: 1059278-B 20500 ARCHWOOD ST      CANOGA PARK, CA 91306

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/8/2022 Conditional Approval AMY COLIN
Footing/Foundation/Slab 8/11/2022 Corrections Issued AMY COLIN
Excavation/Setback/Form/Re-Bar 8/16/2022 Conditional Approval AMY COLIN
Deputy Wood Construction 9/27/2022 Conditional Approval AMY COLIN
ELECTRICAL-Rough 10/4/2022 Approved AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 10/4/2022 Corrections Issued AMY COLIN
PLUMBING-Rough 10/4/2022 Approved AMY COLIN
BUILDING-Rough-Frame 10/6/2022 Corrections Issued AMY COLIN
Green Building Rough 10/6/2022 Not Ready for Inspection AMY COLIN
BUILDING-Rough-Frame 10/7/2022 Partial Approval AMY COLIN
Insulation 10/14/2022 Partial Approval AMY COLIN
Drywall Nailing 10/17/2022 Partial Approval AMY COLIN
BUILDING-Rough-Frame 10/28/2022 Partial Approval AMY COLIN
Green Building Rough 10/28/2022 Not Ready for Inspection AMY COLIN
BUILDING-Rough-Frame 11/3/2022 Approved AMY COLIN
Deputy Wood Construction 11/3/2022 Approved AMY COLIN
Green Building Rough 11/3/2022 Approved AMY COLIN
Interior/Exterior Lathing 11/3/2022 Approved AMY COLIN
Drywall Nailing 11/4/2022 Approved AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 11/4/2022 Approved AMY COLIN
Final 12/28/2022 Corrections Issued AMY COLIN
Footing/Foundation/Slab 12/28/2022 Approved AMY COLIN
Green Building Final 12/28/2022 Approved AMY COLIN
SGSOV-Seismic Gas S/O Valve 12/28/2022 SGSOV Approved AMY COLIN
Smoke Detectors 12/28/2022 Approved AMY COLIN
ELECTRICAL-Final 12/30/2022 Approved AMY COLIN
Final 12/30/2022 Partial Inspection AMY COLIN
Final 1/11/2023 Corrections Issued AMY COLIN
Final 10/29/2024 OK to Issue CofO LILIANA PORTILLO