23263 W GONZALES DR 91367

Certificate Information: 23263 W GONZALES DR 91367

Application / Permit
22014-20000-01159
Plan Check / Job No.
B22VN03797
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 17'-0" X 49'-9" IRREGULAR SHAPE FOR (2) NEW BEDROOMS, (N) MASTER BEDROOM WITH CLOSET AND BATH AND REMODEL TO (E) ONE STORY SINGLE FAMILY DWELLING. WORK PER ENGINEER.
Permit Issued
Issued on 9/12/2022
Issuing Office
Valley
Current Status
CofO Issued on 2/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/14/2022 APPLICANT
Assigned to Plan Check Engineer 4/7/2022 TROY DEGUZMAN
Corrections Issued 4/8/2022 TROY DEGUZMAN
Quality Review Completed 4/18/2022 OMID HEDAYAT
Building Plans Picked Up 4/20/2022 APPLICANT
Applicant returned to address corrections 7/14/2022 TROY DEGUZMAN
Plan Check Approved 9/9/2022 RAPHAEL ROSAS
Issued 9/12/2022 APPLICANT
CofO in Progress 2/13/2024 TROY SANDERS
Permit Finaled 2/22/2024 JOHN JANSON
CofO Issued 2/22/2024 JOHN JANSON
Permit Finaled 2/22/2024 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/31/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 6/2/2022 JOSE DUARTE-DIAZ
Green Code Cleared 7/14/2022 TROY DEGUZMAN
Low Impact Development Cleared 8/18/2022 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 8/19/2022 ROMAN GUTIERREZ
Hydrant and Access approval Cleared 9/6/2022 GILBERT URREA
GPI Written Notices Cleared 9/9/2022 TROY DEGUZMAN
Grading Pre-Inspection Cleared 9/9/2022 TROY DEGUZMAN

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 21757 DEVONSHIRE ST.   SUITE 3    CANOGA PARK, CA 91311

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/20/2023 Approved TROY SANDERS
BUILDING-Rough-Frame 8/17/2023 Approved TROY SANDERS
ELECTRICAL-Rough 8/17/2023 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 8/17/2023 Partial Approval TROY SANDERS
Green Building Rough 8/17/2023 Not Ready for Inspection TROY SANDERS
HVAC-Rough 8/17/2023 Approved TROY SANDERS
PLUMBING-Rough 8/17/2023 Approved TROY SANDERS
Insulation 8/25/2023 Approved TROY SANDERS
Interior/Exterior Lathing 8/25/2023 Partial Approval TROY SANDERS
Drywall Nailing 8/31/2023 Approved TROY SANDERS
Green Building Rough 8/31/2023 Approved TROY SANDERS
Shower Pan 8/31/2023 Approved TROY SANDERS
Interior/Exterior Lathing 9/18/2023 Partial Approval TROY SANDERS
ELECTRICAL-Final 12/28/2023 Approved TROY SANDERS
Final 12/28/2023 Not Ready for Inspection TROY SANDERS
Green Building Final 12/28/2023 Approved TROY SANDERS
HVAC-Final 12/28/2023 Approved TROY SANDERS
PLUMBING-Final 12/28/2023 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 12/28/2023 SGSOV Approved TROY SANDERS
Smoke Detectors 12/28/2023 Approved TROY SANDERS
Final 2/13/2024 OK to Issue CofO TROY SANDERS