7012 N INDEPENDENCE AVE 91303
Certificate Information: 7012 N INDEPENDENCE AVE 91303
- Application / Permit
- 22014-20000-01145
- Plan Check / Job No.
- B22VN03775
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 20' X 20' IRR.-SHAPE MASTER BEDROOM/BATHROOM/CLOSET ADDITION TO REAR OF (E) SFD. ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 7/22/2022
- Issuing Office
- Current Status
- CofO Issued on 9/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2022 | GURUNATH NESARAJAH |
| Corrections Issued | 3/19/2022 | GURUNATH NESARAJAH |
| Plan Check Approved | 4/30/2022 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 5/2/2022 | APPLICANT |
| Issued | 7/22/2022 | APPLICANT |
| CofO in Progress | 8/31/2023 | ALEXANDER HANDY |
| Permit Finaled | 9/6/2023 | JOHN JANSON |
| CofO Issued | 9/6/2023 | JOHN JANSON |
| Permit Finaled | 9/6/2023 | JOHN JANSON |
Permit Application Clearance Information
| ZI | Cleared | 4/15/2022 | PABLO ESTRADA |
| Roof/Waste drainage to street | Cleared | 4/19/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 4/19/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/20/2022 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/28/2022 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 7/28/2022 | Not Ready for Inspection | STEVEN BACK |
| BUILDING-Rough-Frame | 8/17/2022 | Partial Approval | STEVEN BACK |
| Deputy Drilled-In Anchors | 8/17/2022 | Corrections Issued | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 8/17/2022 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 8/17/2022 | Approved | STEVEN BACK |
| Insulation | 8/17/2022 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 8/17/2022 | Partial Approval | STEVEN BACK |
| Sewer | 8/17/2022 | Not Ready for Inspection | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2022 | Partial Approval | STEVEN BACK |
| ELECTRICAL-Rough | 10/19/2022 | Corrections Issued | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2022 | Approved | STEVEN BACK |
| HVAC-Rough | 10/19/2022 | Not Ready for Inspection | STEVEN BACK |
| PLUMBING-Rough | 10/19/2022 | Corrections Issued | STEVEN BACK |
| BUILDING-Rough-Frame | 10/28/2022 | Not Ready for Inspection | STEVEN BACK |
| ELECTRICAL-Rough | 10/28/2022 | Approved | STEVEN BACK |
| Green Building Rough | 10/28/2022 | Not Ready for Inspection | STEVEN BACK |
| HVAC-Rough | 10/28/2022 | Not Ready for Inspection | STEVEN BACK |
| Interior/Exterior Lathing | 10/28/2022 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 10/28/2022 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 11/8/2022 | Partial Approval | STEVEN BACK |
| Green Building Rough | 11/8/2022 | Approved | STEVEN BACK |
| HVAC-Rough | 11/8/2022 | Corrections Issued | STEVEN BACK |
| Interior/Exterior Lathing | 11/8/2022 | Partial Approval | STEVEN BACK |
| BUILDING-Rough-Frame | 11/18/2022 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 11/18/2022 | Approved | STEVEN BACK |
| Shower Pan | 11/18/2022 | Approved | STEVEN BACK |
| Insulation | 12/29/2022 | Partial Approval | ALEXANDER HANDY |
| Insulation | 1/13/2023 | Approved | JESUS PINEDA |
| Drywall Nailing | 1/27/2023 | Partial Approval | ALEXANDER HANDY |
| HVAC-Rough | 1/27/2023 | Corrections Issued | ALEXANDER HANDY |
| Drywall Nailing | 2/13/2023 | Approved | ALEXANDER HANDY |
| HVAC-Rough | 2/13/2023 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 4/17/2023 | SGSOV Not Ready | ALEXANDER HANDY |
| Final | 6/7/2023 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 6/7/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 6/7/2023 | SGSOV Approved | ALEXANDER HANDY |
| Smoke Detectors | 6/7/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| ELECTRICAL-Final | 8/30/2023 | Approved | ALEXANDER HANDY |
| Final | 8/30/2023 | OK to Issue CofO | ALEXANDER HANDY |
| Green Building Final | 8/30/2023 | Approved | ALEXANDER HANDY |
| HVAC-Final | 8/30/2023 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 8/30/2023 | Approved | ALEXANDER HANDY |
| Smoke Detectors | 8/30/2023 | Approved | ALEXANDER HANDY |