7647 N RUDNICK AVE 91304
Certificate Information: 7647 N RUDNICK AVE 91304
- Application / Permit
- 22014-20000-01144
- Plan Check / Job No.
- B22VN03772
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- ADD (14'-7"x 5'-8") AT 1ST & (20'-10"x 5'-10") 2ND FLOOR M. BED TO (E) 2- STORY SINGLE FAMILY DWELLING WITH (36'-1"x 12'-10") ATT PATIO COVER @ REAR. WORK PER ENGINEER.
- Permit Issued
- Issued on 8/10/2022
- Issuing Office
- Valley
- Current Status
- Issued on 8/10/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2022 | TROY DEGUZMAN |
| Corrections Issued | 4/14/2022 | TROY DEGUZMAN |
| Quality Review Completed | 4/15/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 4/18/2022 | APPLICANT |
| Applicant returned to address corrections | 7/14/2022 | TROY DEGUZMAN |
| Plan Check Approved | 8/10/2022 | TROY DEGUZMAN |
| Issued | 8/10/2022 | APPLICANT |
Permit Application Clearance Information
| Low Impact Development | Cleared | 5/19/2022 | LONDY ALVARADO |
| Miscellaneous | Cleared | 5/25/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 5/25/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 5/25/2022 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 6/3/2022 | ROBERT DUFF |
| Green Code | Cleared | 7/14/2022 | TROY DEGUZMAN |
| Eng Process Fee Ord 176,300 | Cleared | 7/20/2022 | DAGOVERTO GUERRERO |
| Miscellaneous | Cleared | 7/20/2022 | DANG NGUYEN |
Contact Information
| Contractor | Builders Hub Renovation Inc; Lic. No.: 1063741-B | 14622 VENTURA BLVD STE 102 SHERMAN OAKS, CA 91403 |
| Engineer | Boules,, George Helmy; Lic. No.: C64144 | 29082 MADRID PL CASTAIC, CA 91384 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/22/2022 | Conditional Approval | CHRIS CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 9/27/2022 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2022 | Approved | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 1/23/2023 | Partial Inspection | KRISTEN CAUSEY |
| ELECTRICAL-Rough | 1/23/2023 | Approved | KRISTEN CAUSEY |
| Green Building Rough | 1/23/2023 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 1/23/2023 | Partial Approval | KRISTEN CAUSEY |
| PLUMBING-Rough | 1/23/2023 | Partial Inspection | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 1/24/2023 | No Access for Inspection | KRISTEN CAUSEY |
| Green Building Rough | 1/24/2023 | No Access for Inspection | KRISTEN CAUSEY |
| PLUMBING-Rough | 1/26/2023 | Approved | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2023 | Partial Inspection | KRISTEN CAUSEY |
| HVAC-Final | 2/16/2023 | Partial Inspection | KRISTEN CAUSEY |
| HVAC-Rough | 2/16/2023 | Approved | KRISTEN CAUSEY |
| Insulation | 2/16/2023 | Approved | KRISTEN CAUSEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2023 | Partial Inspection | JESUS PINEDA |
| BUILDING-Rough-Frame | 2/23/2023 | Approved | KRISTEN CAUSEY |
| Drywall Nailing | 2/23/2023 | Approved | KRISTEN CAUSEY |
| Shower Pan | 3/29/2023 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 4/5/2023 | Not Ready for Inspection | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 5/4/2023 | Approved | DAVID SCANTLIN |