19457 W COLLIER ST 91356

Certificate Information: 19457 W COLLIER ST 91356

Application / Permit
22014-20000-01138
Plan Check / Job No.
B22VN03753
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
**ePlan** Addition and Remodel of (E) Single Family Dwelling
Permit Issued
Issued on 5/23/2023
Issuing Office
Current Status
CofO Issued on 7/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/11/2022 APPLICANT
Assigned to Plan Check Engineer 3/14/2022 JOE VO
Corrections Issued 3/14/2022 ARSALAN SHABESTARI
Applicant returned to address corrections 5/19/2022 ARSALAN SHABESTARI
Applicant returned to address corrections 5/26/2022 ARSALAN SHABESTARI
Applicant returned to address corrections 6/23/2022 ARSALAN SHABESTARI
Plan Check Approved 5/22/2023 EDWIN ESPIN
Issued 5/23/2023 APPLICANT
CofO in Progress 5/29/2024 JOHN KIDWELL
CofO in Progress 6/11/2024 SEAN WIRCH
Permit Finaled 7/17/2024 JOHN JANSON
CofO Issued 7/17/2024 JOHN JANSON
Permit Finaled 7/17/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/23/2022 LEE GUILBEAUX
Permit Cleared 3/23/2022 LEE GUILBEAUX
Sewer availability Cleared 3/23/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 3/24/2022 LEE GUILBEAUX
Low Impact Development Cleared 5/4/2022 LONDY ALVARADO
Roof/Waste drainage to street Cleared 5/5/2022 CARLOS AGUILERA
Permit Cleared 6/8/2022 DAGOVERTO GUERRERO
Grading Pre-Inspection Cleared 6/16/2022 KIRK LINKLATER
GPI Written Notices Cleared 10/14/2022 ARSALAN SHABESTARI

Contact Information

Contractor Adu Concepts; Lic. No.: 1018294-B       ,
Contractor Green Source Energy Inc; Lic. No.: 1018294-B       ,
Engineer Yiu,, Siu; Lic. No.: S5801 PO BOX 5143      EL MONTE, CA 91734

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 10/11/2023 Not Ready for Inspection SEAN HAUPT
Deputy Drilled-In Anchors 10/11/2023 Approved SEAN HAUPT
Footing/Foundation/Slab 10/11/2023 Approved SEAN HAUPT
Green Building Rough 10/11/2023 Not Ready for Inspection SEAN HAUPT
Underground Mechanical 10/11/2023 Not Ready for Inspection SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 11/15/2023 Approved SEAN HAUPT
Special/Order Compliance 11/15/2023 Corrections Issued SEAN HAUPT
BUILDING-Rough-Frame 12/15/2023 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 12/15/2023 Approved JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 12/15/2023 Approved JOHN KIDWELL
Green Building Rough 12/15/2023 Approved JOHN KIDWELL
HVAC-Rough 12/15/2023 Approved JOHN KIDWELL
PLUMBING-Rough 12/15/2023 Approved JOHN KIDWELL
Interior/Exterior Lathing 12/18/2023 Partial Approval SEAN HAUPT
Special/Order Compliance 12/18/2023 Approved SEAN HAUPT
BUILDING-Rough-Frame 12/21/2023 Approved SEAN HAUPT
Green Building Rough 12/21/2023 Approved SEAN HAUPT
Insulation 12/27/2023 Corrections Issued JEFFREY BULL
Special/Order Compliance 12/27/2023 Approved JEFFREY BULL
Insulation 12/29/2023 Approved SEAN HAUPT
Shower Pan 12/29/2023 Approved SEAN HAUPT
Interior/Exterior Lathing 1/4/2024 Approved SEAN HAUPT
Drywall Nailing 1/8/2024 Approved SEAN HAUPT
Green Building Final 4/1/2024 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 4/1/2024 SGSOV Not Ready VINCENT HANLEY
Service/Power Release 4/1/2024 Approved VINCENT HANLEY
Smoke Detectors 4/1/2024 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Final 4/15/2024 Approved JOHN KIDWELL
Gas Test 4/19/2024 Approved JOHN KIDWELL
PLUMBING-Final 4/19/2024 Approved JOHN KIDWELL
Pre-Inspection 5/1/2024 Partial Inspection JOHN KIDWELL
Final 5/14/2024 Corrections Issued JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 5/14/2024 SGSOV Approved JOHN KIDWELL
Smoke Detectors 5/14/2024 Approved JOHN KIDWELL
Final 5/28/2024 OK to Issue CofO JOHN KIDWELL
Special/Order Compliance 6/12/2024 Corrections Issued JOHN KIDWELL