13759 W RAYWOOD DR 90049
Certificate Information: 13759 W RAYWOOD DR 90049
- Application / Permit
- 22014-20000-01126
- Plan Check / Job No.
- B22VN03726
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR AND EXTERIOR REMODEL OF (E) 2-STORY SFD WITH 32 SQ. FT. 1ST FLOOR & 192 SQ. FT. 2ND FLOOR ADDITION (224 SQ. FT TOTAL.).
- Permit Issued
- Issued on 7/6/2022
- Issuing Office
- Current Status
- CofO Issued on 11/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2022 | COLIN LOREDO |
| Corrections Issued | 4/11/2022 | COLIN LOREDO |
| Quality Review Completed | 4/15/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 4/19/2022 | APPLICANT |
| Plan Check Approved | 6/1/2022 | COLIN LOREDO |
| Issued | 7/6/2022 | APPLICANT |
| CofO in Progress | 10/26/2023 | KEVIN SARGSYAN |
| Permit Finaled | 11/14/2023 | DANIEL ORRANTE |
| CofO Issued | 11/14/2023 | DANIEL ORRANTE |
| Permit Finaled | 11/14/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/22/2022 | ROBERT HUGHES |
| Eng Process Fee Ord 176,300 | Cleared | 4/26/2022 | JENSON LEE |
| Roof/Waste drainage to street | Cleared | 4/26/2022 | JENSON LEE |
| Sewer availability | Cleared | 4/26/2022 | JENSON LEE |
| Watercourse | Cleared | 5/2/2022 | HISASHI KOBAYAKAWA |
| GPI Written Notices | Cleared | 5/4/2022 | COLIN LOREDO |
| Hydrant and Access approval | Cleared | 5/12/2022 | LAURINDA MEADE |
Contact Information
| Architect | Calabia,, Carlito Serrano; Lic. No.: C25200 | 6922 KATHERINE AVENUE VAN NUYS, CA 91405 |
| Contractor | D K R Construction Inc; Lic. No.: 1070450-B | 7110 FOREST HILLS RD WEST HILLS, CA 91307 |
Inspector Information
| KEVIN SARGSYAN, (310) 914-3889 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/22/2022 | Approved | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 10/11/2022 | Approved | JUAN VALENZUELA |
| Footing/Foundation/Slab | 10/11/2022 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 11/29/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| FLOOD-Proofing Certificate | 11/29/2022 | Approved | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2022 | Partial Approval | JUAN VALENZUELA |
| Green Building Rough | 11/29/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| PLUMBING-Rough | 11/29/2022 | Corrections Issued | JUAN VALENZUELA |
| ELECTRICAL-Rough | 1/17/2023 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 1/17/2023 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 1/17/2023 | Corrections Issued | KEVIN SARGSYAN |
| Special/Order Compliance | 1/17/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Wood Frame | 1/17/2023 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Rough | 1/26/2023 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 1/26/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| Wood Frame | 1/26/2023 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 1/31/2023 | Corrections Issued | KEVIN SARGSYAN |
| Shower Pan | 1/31/2023 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 2/8/2023 | Partial Approval | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 2/15/2023 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 2/15/2023 | Approved | KEVIN SARGSYAN |
| Insulation | 2/15/2023 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 2/15/2023 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 2/15/2023 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 2/22/2023 | Approved | KEVIN SARGSYAN |
| Final | 8/4/2023 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Final | 8/4/2023 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 8/4/2023 | SGSOV Approved | KEVIN SARGSYAN |
| Smoke Detectors | 8/4/2023 | Approved | KEVIN SARGSYAN |
| Final | 10/4/2023 | Corrections Issued | KEVIN SARGSYAN |
| Final | 10/26/2023 | OK to Issue CofO | KEVIN SARGSYAN |