13759 W RAYWOOD DR 90049

Certificate Information: 13759 W RAYWOOD DR 90049

Application / Permit
22014-20000-01126
Plan Check / Job No.
B22VN03726
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR AND EXTERIOR REMODEL OF (E) 2-STORY SFD WITH 32 SQ. FT. 1ST FLOOR & 192 SQ. FT. 2ND FLOOR ADDITION (224 SQ. FT TOTAL.).
Permit Issued
Issued on 7/6/2022
Issuing Office
Current Status
CofO Issued on 11/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/25/2022 APPLICANT
Assigned to Plan Check Engineer 4/7/2022 COLIN LOREDO
Corrections Issued 4/11/2022 COLIN LOREDO
Quality Review Completed 4/15/2022 OMID HEDAYAT
Building Plans Picked Up 4/19/2022 APPLICANT
Plan Check Approved 6/1/2022 COLIN LOREDO
Issued 7/6/2022 APPLICANT
CofO in Progress 10/26/2023 KEVIN SARGSYAN
Permit Finaled 11/14/2023 DANIEL ORRANTE
CofO Issued 11/14/2023 DANIEL ORRANTE
Permit Finaled 11/14/2023 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 4/22/2022 ROBERT HUGHES
Eng Process Fee Ord 176,300 Cleared 4/26/2022 JENSON LEE
Roof/Waste drainage to street Cleared 4/26/2022 JENSON LEE
Sewer availability Cleared 4/26/2022 JENSON LEE
Watercourse Cleared 5/2/2022 HISASHI KOBAYAKAWA
GPI Written Notices Cleared 5/4/2022 COLIN LOREDO
Hydrant and Access approval Cleared 5/12/2022 LAURINDA MEADE

Contact Information

Architect Calabia,, Carlito Serrano; Lic. No.: C25200 6922 KATHERINE AVENUE      VAN NUYS, CA 91405
Contractor D K R Construction Inc; Lic. No.: 1070450-B 7110 FOREST HILLS RD      WEST HILLS, CA 91307

Inspector Information

KEVIN SARGSYAN, (310) 914-3889 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 9/22/2022 Approved JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 10/11/2022 Approved JUAN VALENZUELA
Footing/Foundation/Slab 10/11/2022 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 11/29/2022 Not Ready for Inspection JUAN VALENZUELA
FLOOD-Proofing Certificate 11/29/2022 Approved JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 11/29/2022 Partial Approval JUAN VALENZUELA
Green Building Rough 11/29/2022 Not Ready for Inspection JUAN VALENZUELA
PLUMBING-Rough 11/29/2022 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Rough 1/17/2023 Approved KEVIN SARGSYAN
HVAC-Rough 1/17/2023 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 1/17/2023 Corrections Issued KEVIN SARGSYAN
Special/Order Compliance 1/17/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Wood Frame 1/17/2023 Corrections Issued KEVIN SARGSYAN
HVAC-Rough 1/26/2023 Approved KEVIN SARGSYAN
PLUMBING-Rough 1/26/2023 Not Ready for Inspection KEVIN SARGSYAN
Wood Frame 1/26/2023 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 1/31/2023 Corrections Issued KEVIN SARGSYAN
Shower Pan 1/31/2023 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 2/8/2023 Partial Approval KEVIN SARGSYAN
BUILDING-Rough-Frame 2/15/2023 Approved KEVIN SARGSYAN
Green Building Rough 2/15/2023 Approved KEVIN SARGSYAN
Insulation 2/15/2023 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 2/15/2023 Approved KEVIN SARGSYAN
PLUMBING-Rough 2/15/2023 Approved KEVIN SARGSYAN
Drywall Nailing 2/22/2023 Approved KEVIN SARGSYAN
Final 8/4/2023 Corrections Issued KEVIN SARGSYAN
Green Building Final 8/4/2023 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 8/4/2023 SGSOV Approved KEVIN SARGSYAN
Smoke Detectors 8/4/2023 Approved KEVIN SARGSYAN
Final 10/4/2023 Corrections Issued KEVIN SARGSYAN
Final 10/26/2023 OK to Issue CofO KEVIN SARGSYAN