7523 W ALPINE WAY 91042
Certificate Information: 7523 W ALPINE WAY 91042
- Application / Permit
- 22014-20000-01122
- Plan Check / Job No.
- B22VN03719
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD (9'-8"x 2'-3") ENTRY PORCH & CONVERT (15'-8"x 9'-11") ATTIC SPACE TO BATHROOM/CLOSET @ 2ND FLOOR OF (E) 2-STORY SINGLE FAMILY DWELLING. WORK PER ENGINEER. "COMPLY WITH DEPARTMENT ORDER effective date 03/25/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 5/25/2022
- Issuing Office
- Current Status
- CofO Issued on 5/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2022 | TROY DEGUZMAN |
| Corrections Issued | 4/13/2022 | TROY DEGUZMAN |
| Quality Review Completed | 4/13/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 4/14/2022 | APPLICANT |
| Applicant returned to address corrections | 5/6/2022 | TROY DEGUZMAN |
| Plan Check Approved | 5/25/2022 | TROY DEGUZMAN |
| Issued | 5/25/2022 | APPLICANT |
| CofO in Progress | 2/22/2023 | EMIL ALEXANDRIAN |
| CofO Issued | 5/5/2023 | DAVID JAMES |
| Permit Finaled | 5/5/2023 | DAVID JAMES |
Permit Application Clearance Information
| Specific Plan | Cleared | 4/29/2022 | PEGGY MALONE-BROWN |
| ZI | Cleared | 4/29/2022 | PEGGY MALONE-BROWN |
| Miscellaneous | Cleared | 5/1/2022 | STEVEN WECHSLER |
| Miscellaneous | Cleared | 5/1/2022 | STEVEN WECHSLER |
| Roof/Waste drainage to street | Cleared | 5/6/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 5/6/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/9/2022 | ROMAN GUTIERREZ |
| Grading Pre-Inspection | Cleared | 5/10/2022 | KIRK LINKLATER |
| Green Code | Cleared | 5/25/2022 | TROY DEGUZMAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Baraty,, Patrick; Lic. No.: S5900 | 1819 SUNSHINE COURT GLENDALE, CA 91208 |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIO CUEVAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/27/2022 | Not Ready for Inspection | EMIL ALEXANDRIAN |
| Pre-Inspection | 5/27/2022 | Approved | EMIL ALEXANDRIAN |
| Wood Frame | 5/27/2022 | Not Ready for Inspection | EMIL ALEXANDRIAN |
| Deputy Drilled-In Anchors | 6/8/2022 | Approved | JASON BRANNON |
| Footing/Foundation/Slab | 6/9/2022 | Approved | EMIL ALEXANDRIAN |
| BUILDING-Rough-Frame | 8/3/2022 | Not Ready for Inspection | EMIL ALEXANDRIAN |
| ELECTRICAL-Rough | 8/3/2022 | Not Ready for Inspection | EMIL ALEXANDRIAN |
| Green Building Rough | 8/3/2022 | Not Ready for Inspection | EMIL ALEXANDRIAN |
| HVAC-Rough | 8/3/2022 | Not Ready for Inspection | EMIL ALEXANDRIAN |
| PLUMBING-Rough | 8/3/2022 | Not Ready for Inspection | EMIL ALEXANDRIAN |
| Sewer | 8/3/2022 | Approved | EMIL ALEXANDRIAN |
| Underground Mechanical | 8/3/2022 | Approved | EMIL ALEXANDRIAN |
| BUILDING-Rough-Frame | 8/18/2022 | Not Ready for Inspection | EMIL ALEXANDRIAN |
| ELECTRICAL-Rough | 8/18/2022 | Approved | EMIL ALEXANDRIAN |
| Green Building Rough | 8/18/2022 | Approved | EMIL ALEXANDRIAN |
| PLUMBING-Rough | 8/18/2022 | Approved | EMIL ALEXANDRIAN |
| BUILDING-Rough-Frame | 8/29/2022 | Approved | EMIL ALEXANDRIAN |
| Interior/Exterior Lathing | 8/29/2022 | Approved | EMIL ALEXANDRIAN |
| Insulation | 9/1/2022 | Approved | EMIL ALEXANDRIAN |
| Drywall Nailing | 9/6/2022 | Approved | EMIL ALEXANDRIAN |
| Final | 2/21/2023 | Conditional Approval | EMIL ALEXANDRIAN |
| Green Building Final | 2/21/2023 | Approved | EMIL ALEXANDRIAN |
| SGSOV-Seismic Gas S/O Valve | 2/21/2023 | SGSOV Approved | EMIL ALEXANDRIAN |
| Smoke Detectors | 2/21/2023 | Approved | EMIL ALEXANDRIAN |