3801 S GRAYBURN AVE 90008
Certificate Information: 3801 S GRAYBURN AVE 90008
- Application / Permit
- 22014-20000-01088
- Plan Check / Job No.
- B22VN03638
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT THE (E) 320 SF FAMILY ROOM INTO A (N) BEDROOM AND (N) MUD ROOM AND AN ADDITION OF 72 SQ. FT. TO REAR OF SFD. WORK TO INLCUDE REFRAMING A PORTION OF THE (e) ROOF.
- Permit Issued
- Issued on 4/14/2022
- Issuing Office
- Current Status
- CofO Issued on 5/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/10/2022 | LUISANGEL VALENZUELA |
| Corrections Issued | 3/10/2022 | LUISANGEL VALENZUELA |
| Plan Check Approved | 4/14/2022 | LUISANGEL VALENZUELA |
| Issued | 4/14/2022 | APPLICANT |
| Building Plans Picked Up | 4/15/2022 | APPLICANT |
| CofO in Progress | 4/30/2024 | ANTHONY EGSON |
| Permit Finaled | 5/7/2024 | DEROLD HAUFF |
| CofO Issued | 5/7/2024 | DEROLD HAUFF |
| Permit Finaled | 5/7/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/15/2022 | WALLIE JONG |
| Sewer availability | Cleared | 3/15/2022 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 4/6/2022 | WALLIE JONG |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: C30383 | 5739 KANAN ROAD # 133 AGOURA HILLS, CA 91301 |
| Contractor | Supreme Remodeling Inc; Lic. No.: 939981-B | 14545 VICTORY BLVD UNIT 401 VAN NUYS, CA 91411 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/26/2022 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 5/26/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 6/24/2022 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2022 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 6/24/2022 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 7/1/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Rough | 7/1/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Wood Frame | 7/1/2022 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2022 | Approved | ANTHONY EGSON |
| Wood Frame | 7/14/2022 | Corrections Issued | ANTHONY EGSON |
| Wood Frame | 7/19/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 7/25/2022 | Approved | ANTHONY EGSON |
| Insulation | 7/28/2022 | Approved | ANTHONY EGSON |
| Drywall Nailing | 8/4/2022 | Approved | ANTHONY EGSON |
| Green Building Rough | 8/4/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 9/23/2022 | Approved | ANTHONY EGSON |
| Final | 9/23/2022 | Conditional Approval | ANTHONY EGSON |
| Green Building Final | 9/23/2022 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 9/23/2022 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 9/23/2022 | Approved | ANTHONY EGSON |
| Final | 4/30/2024 | OK to Issue CofO | ANTHONY EGSON |