8121 N NOBLE AVE 91402
Certificate Information: 8121 N NOBLE AVE 91402
- Application / Permit
- 22014-20000-01079
- Plan Check / Job No.
- B22VN03616
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION OF 29'-10" X 11'-0" AND CONVERT EXISTING DETACHED RECREACTIONAL ROOM AND STORAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). - ALL WORK TO BE DONE PER WFPP. ***“The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.
- Permit Issued
- Issued on 6/24/2022
- Issuing Office
- Current Status
- CofO Issued on 6/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2022 | DANIEL ABRAMYAN |
| Corrections Issued | 3/12/2022 | DANIEL ABRAMYAN |
| Building Plans Picked Up | 3/18/2022 | APPLICANT |
| Applicant returned to address corrections | 5/12/2022 | DANIEL ABRAMYAN |
| Plan Check Approved | 5/13/2022 | DANIEL ABRAMYAN |
| Issued | 6/24/2022 | APPLICANT |
| CofO in Progress | 5/28/2025 | VINCENT HANLEY |
| Permit Finaled | 6/24/2025 | RUBEN SALAS |
| CofO Issued | 6/24/2025 | RUBEN SALAS |
| Permit Finaled | 6/24/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/16/2022 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 3/16/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/31/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 3/31/2022 | JOSE DUARTE-DIAZ |
| Construction near power lines | Cleared | 4/27/2022 | RIDWAN HARDY |
| Construction within easement | Cleared | 4/27/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/12/2022 | Corrections Issued | WILLIAM WREN |
| PLUMBING-Rough | 9/16/2022 | Corrections Issued | WILLIAM WREN |
| PLUMBING-Rough | 9/22/2022 | Corrections Issued | GREGG CUMMINGS |
| Sewer | 9/22/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 9/29/2022 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 10/12/2022 | Partial Approval | GREGG CUMMINGS |
| Footing/Foundation/Slab | 10/20/2022 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2022 | No Access for Inspection | WILLIAM WREN |
| ELECTRICAL-Rough | 1/17/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 1/17/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 1/23/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 1/23/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 1/23/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 2/1/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 2/1/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Wood Frame | 2/1/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 2/7/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 2/7/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 2/7/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 2/7/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 7/26/2023 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 7/26/2023 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Rough | 7/26/2023 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 8/15/2023 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 8/15/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 8/15/2023 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 9/6/2023 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 9/6/2023 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 9/6/2023 | Partial Approval | GREGG CUMMINGS |
| HVAC-Rough | 9/6/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Underground Mechanical | 9/6/2023 | Partial Approval | GREGG CUMMINGS |
| Interior/Exterior Lathing | 10/5/2023 | Partial Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 10/12/2023 | Partial Approval | ROBERT GOLD |
| Pre-Inspection | 11/13/2023 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 11/27/2023 | Conditional Approval | GREGG CUMMINGS |
| ELECTRICAL-Rough | 11/27/2023 | Approved | GREGG CUMMINGS |
| Green Building Rough | 11/27/2023 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 11/27/2023 | Approved | GREGG CUMMINGS |
| Insulation | 11/30/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Insulation | 12/4/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Shower Pan | 12/4/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Insulation | 12/6/2023 | Approved | CHRISTOPHER ROJAS |
| Shower Pan | 12/6/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Drywall Nailing | 12/11/2023 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 12/11/2023 | Approved | CHRISTOPHER ROJAS |
| Shower Pan | 12/11/2023 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 1/29/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 3/28/2024 | Approved | KIRK SANDERS |
| Final | 3/28/2024 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 3/28/2024 | Not Ready for Inspection | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 3/28/2024 | SGSOV Approved | KIRK SANDERS |
| Smoke Detectors | 3/28/2024 | Corrections Issued | KIRK SANDERS |
| Final | 12/10/2024 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 12/10/2024 | No Access for Inspection | VINCENT HANLEY |
| Smoke Detectors | 12/10/2024 | No Access for Inspection | VINCENT HANLEY |
| ELECTRICAL-Final | 1/29/2025 | Approved | VINCENT HANLEY |
| Final | 1/29/2025 | Corrections Issued | VINCENT HANLEY |
| HVAC-Final | 1/29/2025 | Approved | VINCENT HANLEY |
| MERV13>=Final | 1/29/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 1/29/2025 | Approved | VINCENT HANLEY |
| Final | 5/28/2025 | OK to Issue CofO | VINCENT HANLEY |
| Green Building Final | 5/28/2025 | Approved | VINCENT HANLEY |
| Smoke Detectors | 5/28/2025 | Approved | VINCENT HANLEY |