8121 N NOBLE AVE 91402

Certificate Information: 8121 N NOBLE AVE 91402

Application / Permit
22014-20000-01079
Plan Check / Job No.
B22VN03616
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION OF 29'-10" X 11'-0" AND CONVERT EXISTING DETACHED RECREACTIONAL ROOM AND STORAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). - ALL WORK TO BE DONE PER WFPP. ***“The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.
Permit Issued
Issued on 6/24/2022
Issuing Office
Current Status
CofO Issued on 6/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/9/2022 APPLICANT
Assigned to Plan Check Engineer 3/11/2022 DANIEL ABRAMYAN
Corrections Issued 3/12/2022 DANIEL ABRAMYAN
Building Plans Picked Up 3/18/2022 APPLICANT
Applicant returned to address corrections 5/12/2022 DANIEL ABRAMYAN
Plan Check Approved 5/13/2022 DANIEL ABRAMYAN
Issued 6/24/2022 APPLICANT
CofO in Progress 5/28/2025 VINCENT HANLEY
Permit Finaled 6/24/2025 RUBEN SALAS
CofO Issued 6/24/2025 RUBEN SALAS
Permit Finaled 6/24/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/16/2022 JOSE DUARTE-DIAZ
Roof/Waste drainage to street Cleared 3/16/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 3/31/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 3/31/2022 JOSE DUARTE-DIAZ
Construction near power lines Cleared 4/27/2022 RIDWAN HARDY
Construction within easement Cleared 4/27/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/12/2022 Corrections Issued WILLIAM WREN
PLUMBING-Rough 9/16/2022 Corrections Issued WILLIAM WREN
PLUMBING-Rough 9/22/2022 Corrections Issued GREGG CUMMINGS
Sewer 9/22/2022 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 9/29/2022 Corrections Issued GREGG CUMMINGS
PLUMBING-Rough 10/12/2022 Partial Approval GREGG CUMMINGS
Footing/Foundation/Slab 10/20/2022 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 11/14/2022 No Access for Inspection WILLIAM WREN
ELECTRICAL-Rough 1/17/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 1/17/2023 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Rough 1/17/2023 Corrections Issued CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 1/23/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 1/23/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Green Building Rough 1/23/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
PLUMBING-Rough 1/23/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 2/1/2023 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Rough 2/1/2023 Approved CHRISTOPHER DELLEFIELD
Wood Frame 2/1/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 2/7/2023 Corrections Issued CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 2/7/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Green Building Rough 2/7/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
HVAC-Rough 2/7/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 7/26/2023 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Rough 7/26/2023 Corrections Issued GREGG CUMMINGS
HVAC-Rough 7/26/2023 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Rough 8/15/2023 Approved GREGG CUMMINGS
HVAC-Rough 8/15/2023 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 8/15/2023 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 9/6/2023 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Rough 9/6/2023 Approved GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 9/6/2023 Partial Approval GREGG CUMMINGS
HVAC-Rough 9/6/2023 Not Ready for Inspection GREGG CUMMINGS
Underground Mechanical 9/6/2023 Partial Approval GREGG CUMMINGS
Interior/Exterior Lathing 10/5/2023 Partial Inspection MISAEL ESPARZA
Interior/Exterior Lathing 10/12/2023 Partial Approval ROBERT GOLD
Pre-Inspection 11/13/2023 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 11/27/2023 Conditional Approval GREGG CUMMINGS
ELECTRICAL-Rough 11/27/2023 Approved GREGG CUMMINGS
Green Building Rough 11/27/2023 Approved GREGG CUMMINGS
HVAC-Rough 11/27/2023 Approved GREGG CUMMINGS
Insulation 11/30/2023 Not Ready for Inspection GREGG CUMMINGS
Insulation 12/4/2023 Corrections Issued CHRISTOPHER ROJAS
Shower Pan 12/4/2023 Not Ready for Inspection CHRISTOPHER ROJAS
Insulation 12/6/2023 Approved CHRISTOPHER ROJAS
Shower Pan 12/6/2023 Not Ready for Inspection CHRISTOPHER ROJAS
Drywall Nailing 12/11/2023 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 12/11/2023 Approved CHRISTOPHER ROJAS
Shower Pan 12/11/2023 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 1/29/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 3/28/2024 Approved KIRK SANDERS
Final 3/28/2024 Corrections Issued KIRK SANDERS
Green Building Final 3/28/2024 Not Ready for Inspection KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 3/28/2024 SGSOV Approved KIRK SANDERS
Smoke Detectors 3/28/2024 Corrections Issued KIRK SANDERS
Final 12/10/2024 Corrections Issued VINCENT HANLEY
Green Building Final 12/10/2024 No Access for Inspection VINCENT HANLEY
Smoke Detectors 12/10/2024 No Access for Inspection VINCENT HANLEY
ELECTRICAL-Final 1/29/2025 Approved VINCENT HANLEY
Final 1/29/2025 Corrections Issued VINCENT HANLEY
HVAC-Final 1/29/2025 Approved VINCENT HANLEY
MERV13>=Final 1/29/2025 Approved VINCENT HANLEY
PLUMBING-Final 1/29/2025 Approved VINCENT HANLEY
Final 5/28/2025 OK to Issue CofO VINCENT HANLEY
Green Building Final 5/28/2025 Approved VINCENT HANLEY
Smoke Detectors 5/28/2025 Approved VINCENT HANLEY