15522 W EL CAJON ST 91342
Certificate Information: 15522 W EL CAJON ST 91342
- Application / Permit
- 22014-20000-01077
- Plan Check / Job No.
- B22VN03609
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- IRREGULAR 15.42' x 37' (442.3 SF) ADDITION AND INTERIOR REMODEL TO THE (E) SINGLE-FAMILY DWELLING TO CONSIST OF ENLARGING THE BEDROOMS, ADDING A BATHROOM, AND ADDING A BEDROOM.
- Permit Issued
- Issued on 5/12/2022
- Issuing Office
- Current Status
- CofO Issued on 8/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2022 | LUIS RINCON |
| Corrections Issued | 3/12/2022 | LUIS RINCON |
| Applicant returned to address corrections | 4/1/2022 | LUIS RINCON |
| Building Plans Picked Up | 4/20/2022 | APPLICANT |
| Plan Check Approved | 5/2/2022 | JOSHUA WILSON |
| Issued | 5/12/2022 | APPLICANT |
| CofO in Progress | 7/29/2024 | KEVIN BERBERYAN |
| Permit Finaled | 8/14/2024 | DANIEL ORRANTE |
| CofO Issued | 8/14/2024 | DANIEL ORRANTE |
| Permit Finaled | 8/14/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/17/2022 | BRIAN MILLER |
| Eng Process Fee Ord 176,300 | Cleared | 3/21/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 3/21/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 4/5/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zelada,, Mynor Anibal; Lic. No.: C48666 | 14545 VICTORY BLVD 405 VAN NUYS, CA 91411 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/23/2023 | Conditional Approval | MICHAEL SMITH |
| Footing/Foundation/Slab | 1/26/2023 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 2/22/2023 | Corrections Issued | DAVID MATSON |
| Sewer | 2/22/2023 | Not Ready for Inspection | DAVID MATSON |
| BUILDING-Rough-Frame | 2/28/2023 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Rough | 2/28/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Green Building Rough | 2/28/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 2/28/2023 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2023 | Partial Approval | ARAM AVEDISIAN |
| Deputy Drilled-In Anchors | 5/30/2023 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 6/2/2023 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 7/20/2023 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2023 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 7/20/2023 | Approved | MICHEL ABAJAN |
| Rough-Elec/Plmb/HVAC | 7/20/2023 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 7/25/2023 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 7/25/2023 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Rough | 7/25/2023 | Corrections Issued | THOMAS FINNILA |
| Pre-Inspection | 8/31/2023 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 10/16/2023 | Corrections Issued | KEVIN BERBERYAN |
| PLUMBING-Rough | 10/16/2023 | Conditional Approval | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 11/16/2023 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 11/16/2023 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 11/16/2023 | Corrections Issued | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 11/20/2023 | Approved | KEVIN BERBERYAN |
| PLUMBING-Final | 11/20/2023 | Approved | KEVIN BERBERYAN |
| Shower Pan | 11/20/2023 | Corrections Issued | KEVIN BERBERYAN |
| Insulation | 11/27/2023 | Approved | KEVIN BERBERYAN |
| Shower Pan | 11/27/2023 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 12/22/2023 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 12/22/2023 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 4/23/2024 | SGSOV Not Ready | KEVIN BERBERYAN |
| Final | 5/1/2024 | Corrections Issued | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 5/1/2024 | Approved | KEVIN BERBERYAN |
| Green Building Final | 5/1/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 5/1/2024 | SGSOV Not Ready | KEVIN BERBERYAN |
| Smoke Detectors | 5/1/2024 | Corrections Issued | KEVIN BERBERYAN |
| Final | 5/14/2024 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 5/14/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 5/14/2024 | SGSOV Approved | KEVIN BERBERYAN |
| Smoke Detectors | 5/14/2024 | Approved | KEVIN BERBERYAN |
| Final | 7/29/2024 | OK to Issue CofO | KEVIN BERBERYAN |
| Green Building Final | 7/29/2024 | Approved | KEVIN BERBERYAN |