15522 W EL CAJON ST 91342

Certificate Information: 15522 W EL CAJON ST 91342

Application / Permit
22014-20000-01077
Plan Check / Job No.
B22VN03609
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
IRREGULAR 15.42' x 37' (442.3 SF) ADDITION AND INTERIOR REMODEL TO THE (E) SINGLE-FAMILY DWELLING TO CONSIST OF ENLARGING THE BEDROOMS, ADDING A BATHROOM, AND ADDING A BEDROOM.
Permit Issued
Issued on 5/12/2022
Issuing Office
Current Status
CofO Issued on 8/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/9/2022 APPLICANT
Assigned to Plan Check Engineer 3/11/2022 LUIS RINCON
Corrections Issued 3/12/2022 LUIS RINCON
Applicant returned to address corrections 4/1/2022 LUIS RINCON
Building Plans Picked Up 4/20/2022 APPLICANT
Plan Check Approved 5/2/2022 JOSHUA WILSON
Issued 5/12/2022 APPLICANT
CofO in Progress 7/29/2024 KEVIN BERBERYAN
Permit Finaled 8/14/2024 DANIEL ORRANTE
CofO Issued 8/14/2024 DANIEL ORRANTE
Permit Finaled 8/14/2024 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/17/2022 BRIAN MILLER
Eng Process Fee Ord 176,300 Cleared 3/21/2022 CARLOS AGUILERA
Sewer availability Cleared 3/21/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 4/5/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Zelada,, Mynor Anibal; Lic. No.: C48666 14545 VICTORY BLVD 405      VAN NUYS, CA 91411

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/23/2023 Conditional Approval MICHAEL SMITH
Footing/Foundation/Slab 1/26/2023 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 2/22/2023 Corrections Issued DAVID MATSON
Sewer 2/22/2023 Not Ready for Inspection DAVID MATSON
BUILDING-Rough-Frame 2/28/2023 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 2/28/2023 Not Ready for Inspection MICHEL ABAJAN
Green Building Rough 2/28/2023 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Rough 2/28/2023 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 5/24/2023 Partial Approval ARAM AVEDISIAN
Deputy Drilled-In Anchors 5/30/2023 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 6/2/2023 Not Ready for Inspection THOMAS FINNILA
Footing/Foundation/Slab 6/2/2023 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 7/20/2023 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 7/20/2023 Partial Approval MICHEL ABAJAN
Green Building Rough 7/20/2023 Approved MICHEL ABAJAN
Rough-Elec/Plmb/HVAC 7/20/2023 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 7/25/2023 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 7/25/2023 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 7/25/2023 Corrections Issued THOMAS FINNILA
Pre-Inspection 8/31/2023 Approved MISAEL ESPARZA
ELECTRICAL-Rough 10/16/2023 Corrections Issued KEVIN BERBERYAN
PLUMBING-Rough 10/16/2023 Conditional Approval KEVIN BERBERYAN
ELECTRICAL-Rough 11/16/2023 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 11/16/2023 Approved KEVIN BERBERYAN
PLUMBING-Rough 11/16/2023 Corrections Issued KEVIN BERBERYAN
BUILDING-Rough-Frame 11/20/2023 Approved KEVIN BERBERYAN
PLUMBING-Final 11/20/2023 Approved KEVIN BERBERYAN
Shower Pan 11/20/2023 Corrections Issued KEVIN BERBERYAN
Insulation 11/27/2023 Approved KEVIN BERBERYAN
Shower Pan 11/27/2023 Approved KEVIN BERBERYAN
Drywall Nailing 12/22/2023 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 12/22/2023 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 4/23/2024 SGSOV Not Ready KEVIN BERBERYAN
Final 5/1/2024 Corrections Issued KEVIN BERBERYAN
Footing/Foundation/Slab 5/1/2024 Approved KEVIN BERBERYAN
Green Building Final 5/1/2024 Not Ready for Inspection KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 5/1/2024 SGSOV Not Ready KEVIN BERBERYAN
Smoke Detectors 5/1/2024 Corrections Issued KEVIN BERBERYAN
Final 5/14/2024 Corrections Issued KEVIN BERBERYAN
Green Building Final 5/14/2024 Not Ready for Inspection KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 5/14/2024 SGSOV Approved KEVIN BERBERYAN
Smoke Detectors 5/14/2024 Approved KEVIN BERBERYAN
Final 7/29/2024 OK to Issue CofO KEVIN BERBERYAN
Green Building Final 7/29/2024 Approved KEVIN BERBERYAN