9712 N LEV AVE 91331

Certificate Information: 9712 N LEV AVE 91331

Application / Permit
22014-20000-01064
Plan Check / Job No.
B22VN03576
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
DEMOLITION OF EXISTING ATTACHED CARPORT AND ADDITION 19'-9" X 13'-6" FAMILY ROOM TO EXISTING SINGLE FAMILY DWELLING PER ENGINEERING
Permit Issued
Issued on 5/17/2022
Issuing Office
Valley
Current Status
CofO Issued on 10/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/9/2022 APPLICANT
Assigned to Plan Check Engineer 3/11/2022 DANIEL ABRAMYAN
Corrections Issued 3/12/2022 DANIEL ABRAMYAN
Plan Check Approved 5/3/2022 DANIEL ABRAMYAN
Building Plans Picked Up 5/5/2022 APPLICANT
Issued 5/17/2022 APPLICANT
CofO in Progress 9/5/2023 MICHEL ABAJAN
Permit Finaled 10/13/2023 RUBEN SALAS
CofO Issued 10/13/2023 RUBEN SALAS
Permit Finaled 10/13/2023 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/19/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/23/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/12/2023 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 7/17/2023 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 7/27/2023 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 8/9/2023 Partial Approval MISAEL ESPARZA
ELECTRICAL-Rough 8/9/2023 Approved MISAEL ESPARZA
Green Building Rough 8/9/2023 Approved MISAEL ESPARZA
MERV13>=Rough 8/9/2023 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 8/15/2023 Approved WILLIAM WREN
Insulation 8/15/2023 Approved WILLIAM WREN
Drywall Nailing 8/21/2023 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 9/5/2023 Approved MICHEL ABAJAN
ELECTRICAL-Final 9/5/2023 Approved MICHEL ABAJAN
Final 9/5/2023 OK to Issue CofO MICHEL ABAJAN
Green Building Final 9/5/2023 Approved MICHEL ABAJAN
HVAC-Final 9/5/2023 Approved MICHEL ABAJAN
MERV13>=Final 9/5/2023 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 9/5/2023 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 9/5/2023 Approved MICHEL ABAJAN