12250 W MORRISON ST 91607
Certificate Information: 12250 W MORRISON ST 91607
- Application / Permit
- 22014-20000-01060
- Plan Check / Job No.
- B22VN03547
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR INTERIOR/EXTERIOR REMODEL AND (1412 SQFT ADDITION AND NEW (336 SQFT) ATTACHED 2 CAR GARAGE W/NEW FRONT PORCH (50 SQFT) AND REAR PATIO (125 SQFT) TO (E) 1-STORY SFD W/NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 6/24/2022
- Issuing Office
- Current Status
- CofO Issued on 3/20/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/24/2022 | PETER MOSESIAN |
| Corrections Issued | 3/26/2022 | PETER MOSESIAN |
| Quality Review Completed | 3/30/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 4/6/2022 | APPLICANT |
| Plan Check Approved | 6/13/2022 | PETER MOSESIAN |
| Issued | 6/24/2022 | APPLICANT |
| CofO in Progress | 2/15/2024 | JOSE AVILA |
| Permit Finaled | 3/20/2024 | RUBEN SALAS |
| CofO Issued | 3/20/2024 | RUBEN SALAS |
| Permit Finaled | 3/20/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/19/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 4/19/2022 | DAGOVERTO GUERRERO |
| Specific Plan | Cleared | 4/26/2022 | CORREY KITCHENS |
| ZI | Cleared | 4/26/2022 | CORREY KITCHENS |
| Low Impact Development | Cleared | 5/19/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 6/1/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wang,, Hongyu; Lic. No.: C72679 | 8887 W FALMINGO RD STE 101 LAS VEGAS, NV 89147 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/16/2022 | Partial Inspection | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 1/25/2023 | Conditional Approval | MICHAEL SMITH |
| Footing/Foundation/Slab | 2/1/2023 | Corrections Issued | KIRK SANDERS |
| Footing/Foundation/Slab | 2/16/2023 | Approved | KIRK SANDERS |
| Sewer | 3/16/2023 | Corrections Issued | KIRK SANDERS |
| Sewer | 3/20/2023 | Approved | KIRK SANDERS |
| Footing/Foundation/Slab | 4/6/2023 | Partial Approval | KIRK SANDERS |
| Underground Mechanical | 4/6/2023 | Approved | KIRK SANDERS |
| Wood Frame | 5/24/2023 | Partial Approval | ROBERT GOLD |
| PLUMBING-Rough | 6/5/2023 | Partial Approval | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2023 | Partial Approval | KIRK SANDERS |
| Gas Test | 6/28/2023 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Rough | 6/28/2023 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Rough | 6/28/2023 | Approved | KIRK SANDERS |
| Shower Pan | 6/28/2023 | Approved | KIRK SANDERS |
| Deputy Wood Construction | 6/29/2023 | Conditional Approval | KIRK SANDERS |
| ELECTRICAL-Rough | 7/11/2023 | Corrections Issued | KIRK SANDERS |
| HVAC-Rough | 7/11/2023 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 7/11/2023 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 7/17/2023 | Partial Approval | KIRK SANDERS |
| Interior/Exterior Lathing | 7/17/2023 | Partial Approval | KIRK SANDERS |
| BUILDING-Rough-Frame | 7/21/2023 | Approved | KIRK SANDERS |
| ELECTRICAL-Rough | 7/21/2023 | Conditional Approval | KIRK SANDERS |
| Green Building Rough | 7/21/2023 | Approved | KIRK SANDERS |
| Insulation | 7/28/2023 | Partial Approval | KIRK SANDERS |
| Interior/Exterior Lathing | 7/28/2023 | Approved | KIRK SANDERS |
| Insulation | 8/3/2023 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 8/3/2023 | Approved | KIRK SANDERS |
| Drywall Nailing | 8/15/2023 | Approved | JUAN VALENZUELA |
| Deputy Drilled-In Anchors | 8/28/2023 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 8/30/2023 | Partial Approval | CHRISTOPHER ROJAS |
| Rough-Elec/Plmb/HVAC | 8/30/2023 | Partial Approval | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 11/6/2023 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 11/6/2023 | Approved | KIRK SANDERS |
| ELECTRICAL-Final | 11/14/2023 | Approved | KIRK SANDERS |
| Gas Test | 11/14/2023 | Approved | KIRK SANDERS |
| Service/Power Release | 11/14/2023 | Approved | KIRK SANDERS |
| HVAC-Final | 12/7/2023 | Approved | KIRK SANDERS |
| PLUMBING-Final | 12/7/2023 | Partial Approval | KIRK SANDERS |
| PLUMBING-Final | 12/14/2023 | Approved | KIRK SANDERS |
| Final | 12/19/2023 | Corrections Issued | KIRK SANDERS |
| Footing/Foundation/Slab | 12/19/2023 | Approved | KIRK SANDERS |
| Green Building Final | 12/19/2023 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 12/19/2023 | SGSOV Not Ready | KIRK SANDERS |
| Smoke Detectors | 12/19/2023 | Approved | KIRK SANDERS |
| Final | 2/7/2024 | Corrections Issued | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 2/7/2024 | SGSOV Approved | JOSE AVILA |
| Final | 2/14/2024 | OK to Issue CofO | JOSE AVILA |