12250 W MORRISON ST 91607

Certificate Information: 12250 W MORRISON ST 91607

Application / Permit
22014-20000-01060
Plan Check / Job No.
B22VN03547
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR INTERIOR/EXTERIOR REMODEL AND (1412 SQFT ADDITION AND NEW (336 SQFT) ATTACHED 2 CAR GARAGE W/NEW FRONT PORCH (50 SQFT) AND REAR PATIO (125 SQFT) TO (E) 1-STORY SFD W/NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 6/24/2022
Issuing Office
Current Status
CofO Issued on 3/20/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/11/2022 APPLICANT
Assigned to Plan Check Engineer 3/24/2022 PETER MOSESIAN
Corrections Issued 3/26/2022 PETER MOSESIAN
Quality Review Completed 3/30/2022 OMID HEDAYAT
Building Plans Picked Up 4/6/2022 APPLICANT
Plan Check Approved 6/13/2022 PETER MOSESIAN
Issued 6/24/2022 APPLICANT
CofO in Progress 2/15/2024 JOSE AVILA
Permit Finaled 3/20/2024 RUBEN SALAS
CofO Issued 3/20/2024 RUBEN SALAS
Permit Finaled 3/20/2024 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/19/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 4/19/2022 DAGOVERTO GUERRERO
Specific Plan Cleared 4/26/2022 CORREY KITCHENS
ZI Cleared 4/26/2022 CORREY KITCHENS
Low Impact Development Cleared 5/19/2022 TA ANH
Roof/Waste drainage to street Cleared 6/1/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Wang,, Hongyu; Lic. No.: C72679 8887 W FALMINGO RD STE 101      LAS VEGAS, NV 89147

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/16/2022 Partial Inspection JENNIFER RABUCHIN
Deputy Drilled-In Anchors 1/25/2023 Conditional Approval MICHAEL SMITH
Footing/Foundation/Slab 2/1/2023 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 2/16/2023 Approved KIRK SANDERS
Sewer 3/16/2023 Corrections Issued KIRK SANDERS
Sewer 3/20/2023 Approved KIRK SANDERS
Footing/Foundation/Slab 4/6/2023 Partial Approval KIRK SANDERS
Underground Mechanical 4/6/2023 Approved KIRK SANDERS
Wood Frame 5/24/2023 Partial Approval ROBERT GOLD
PLUMBING-Rough 6/5/2023 Partial Approval KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 6/28/2023 Partial Approval KIRK SANDERS
Gas Test 6/28/2023 Not Ready for Inspection KIRK SANDERS
HVAC-Rough 6/28/2023 Corrections Issued KIRK SANDERS
PLUMBING-Rough 6/28/2023 Approved KIRK SANDERS
Shower Pan 6/28/2023 Approved KIRK SANDERS
Deputy Wood Construction 6/29/2023 Conditional Approval KIRK SANDERS
ELECTRICAL-Rough 7/11/2023 Corrections Issued KIRK SANDERS
HVAC-Rough 7/11/2023 Approved KIRK SANDERS
Interior/Exterior Lathing 7/11/2023 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 7/17/2023 Partial Approval KIRK SANDERS
Interior/Exterior Lathing 7/17/2023 Partial Approval KIRK SANDERS
BUILDING-Rough-Frame 7/21/2023 Approved KIRK SANDERS
ELECTRICAL-Rough 7/21/2023 Conditional Approval KIRK SANDERS
Green Building Rough 7/21/2023 Approved KIRK SANDERS
Insulation 7/28/2023 Partial Approval KIRK SANDERS
Interior/Exterior Lathing 7/28/2023 Approved KIRK SANDERS
Insulation 8/3/2023 Approved KIRK SANDERS
Interior/Exterior Lathing 8/3/2023 Approved KIRK SANDERS
Drywall Nailing 8/15/2023 Approved JUAN VALENZUELA
Deputy Drilled-In Anchors 8/28/2023 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 8/30/2023 Partial Approval CHRISTOPHER ROJAS
Rough-Elec/Plmb/HVAC 8/30/2023 Partial Approval CHRISTOPHER ROJAS
ELECTRICAL-Final 11/6/2023 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 11/6/2023 Approved KIRK SANDERS
ELECTRICAL-Final 11/14/2023 Approved KIRK SANDERS
Gas Test 11/14/2023 Approved KIRK SANDERS
Service/Power Release 11/14/2023 Approved KIRK SANDERS
HVAC-Final 12/7/2023 Approved KIRK SANDERS
PLUMBING-Final 12/7/2023 Partial Approval KIRK SANDERS
PLUMBING-Final 12/14/2023 Approved KIRK SANDERS
Final 12/19/2023 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 12/19/2023 Approved KIRK SANDERS
Green Building Final 12/19/2023 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 12/19/2023 SGSOV Not Ready KIRK SANDERS
Smoke Detectors 12/19/2023 Approved KIRK SANDERS
Final 2/7/2024 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 2/7/2024 SGSOV Approved JOSE AVILA
Final 2/14/2024 OK to Issue CofO JOSE AVILA