13623 W SYLVAN ST 91401
Certificate Information: 13623 W SYLVAN ST 91401
- Application / Permit
- 22014-20000-01057
- Plan Check / Job No.
- B22VN03533
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-STORY ADDITION ABOVE THE (E) SINGLE FAMILY DWELLING WITH ATTACHED TRELLIS. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 5/19/2022
- Issuing Office
- Current Status
- CofO Issued on 6/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2022 | COLIN LOREDO |
| Corrections Issued | 4/11/2022 | COLIN LOREDO |
| Quality Review Completed | 4/15/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 4/18/2022 | APPLICANT |
| Plan Check Approved | 5/12/2022 | COLIN LOREDO |
| Issued | 5/19/2022 | APPLICANT |
| CofO in Progress | 6/6/2023 | JUAN VALENZUELA |
| Permit Finaled | 6/8/2023 | MICHAEL SMITH |
| CofO Issued | 6/8/2023 | MICHAEL SMITH |
| Permit Finaled | 6/8/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/18/2022 | CHRIS CHAHBAZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/19/2022 | CHRIS CHAHBAZ |
| Sewer availability | Cleared | 4/19/2022 | CHRIS CHAHBAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/30/2022 | Partial Approval | MATT KELLERMAN |
| Footing/Foundation/Slab | 6/30/2022 | Approved | RAFAEL CORTES |
| Underground Mechanical | 7/8/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2022 | Partial Approval | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 8/17/2022 | Partial Approval | RAFAEL CORTES |
| BUILDING-Rough-Frame | 9/15/2022 | Not Ready for Inspection | RAFAEL CORTES |
| ELECTRICAL-Rough | 9/15/2022 | Approved | RAFAEL CORTES |
| Green Building Rough | 9/15/2022 | Not Ready for Inspection | RAFAEL CORTES |
| PLUMBING-Rough | 9/15/2022 | Corrections Issued | RAFAEL CORTES |
| Shower Pan | 9/22/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Interior/Exterior Lathing | 9/28/2022 | Approved | RAFAEL CORTES |
| Shower Pan | 9/28/2022 | Approved | RAFAEL CORTES |
| BUILDING-Rough-Frame | 10/4/2022 | Approved | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2022 | Approved | RAFAEL CORTES |
| Green Building Rough | 10/4/2022 | Approved | RAFAEL CORTES |
| Interior/Exterior Lathing | 10/4/2022 | Partial Approval | RAFAEL CORTES |
| Insulation | 10/11/2022 | Approved | ALAN MORELOS |
| Drywall Nailing | 10/20/2022 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 10/20/2022 | Approved | WILLIAM WREN |
| Final | 2/16/2023 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 2/16/2023 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 2/16/2023 | SGSOV Approved | KIRK SANDERS |
| Smoke Detectors | 2/16/2023 | Approved | KIRK SANDERS |
| Final | 3/13/2023 | Partial Approval | KIRK SANDERS |
| Final | 4/19/2023 | Conditional Approval | KIRK SANDERS |
| Final | 5/1/2023 | Not Ready for Inspection | KIRK SANDERS |
| Final | 5/9/2023 | Corrections Issued | KIRK SANDERS |
| Final | 6/6/2023 | OK to Issue CofO | JUAN VALENZUELA |