11743 W HATTERAS ST 91607

Certificate Information: 11743 W HATTERAS ST 91607

Application / Permit
22014-20000-01041
Plan Check / Job No.
B22VN03471
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 23'-7" X 39'-2" IRREGLAR SHAPED 2ND STORY ADDITION TO (E) 1-STORY SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 9/15/2022
Issuing Office
Valley
Current Status
CofO in Progress on 9/10/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/9/2022 APPLICANT
Assigned to Plan Check Engineer 4/7/2022 RAPHAEL ROSAS
Corrections Issued 4/18/2022 RAPHAEL ROSAS
Quality Review Completed 4/21/2022 STEVEN KIM
Building Plans Picked Up 4/22/2022 APPLICANT
Applicant returned to address corrections 7/8/2022 RAPHAEL ROSAS
Applicant returned to address corrections 8/1/2022 RAPHAEL ROSAS
Plan Check Approved 9/9/2022 RAPHAEL ROSAS
Issued 9/15/2022 APPLICANT
CofO in Progress 9/10/2025 ROBERTO PALACIOS-LOPEZ
CofO in Progress 9/12/2025 JUAN VALENZUELA

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/25/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 4/25/2022 CARLOS AGUILERA
Sewer availability Cleared 4/26/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Booth,, Drummond Ricardo E; Lic. No.: C41805 PO BOX 2045      VENICE, CA 90294

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/21/2022 Partial Approval ROBERT GOLD
Deputy Drilled-In Anchors 10/24/2022 Conditional Approval MICHAEL SMITH
Footing/Foundation/Slab 10/24/2022 Corrections Issued JOHN HAYES
Excavation/Setback/Form/Re-Bar 10/25/2022 Approved JOHN HAYES
Deputy Steel/Welding 11/10/2022 Conditional Approval JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 11/17/2022 Corrections Issued JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 12/3/2022 Not Ready for Inspection COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 12/9/2022 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 12/22/2022 Not Ready for Inspection JOHN HAYES
Insulation 12/22/2022 Not Ready for Inspection JOHN HAYES
Interior/Exterior Lathing 12/22/2022 Not Ready for Inspection JOHN HAYES
Service/Power Release 12/22/2022 Not Ready for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 12/23/2022 Partial Approval JOHN HAYES
BUILDING-Rough-Frame 1/9/2023 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Rough 1/9/2023 Not Ready for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 1/9/2023 Not Ready for Inspection JOHN HAYES
Green Building Rough 1/9/2023 Not Ready for Inspection JOHN HAYES
HVAC-Rough 1/9/2023 Not Ready for Inspection JOHN HAYES
MERV13>=Rough 1/9/2023 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 1/9/2023 Not Ready for Inspection JOHN HAYES
Wood Frame 1/9/2023 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Rough 1/18/2023 Approved JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 1/18/2023 Partial Approval JOHN HAYES
HVAC-Rough 1/18/2023 Approved JOHN HAYES
PLUMBING-Rough 1/18/2023 Approved JOHN HAYES
Wood Frame 1/18/2023 Corrections Issued JOHN HAYES
BUILDING-Rough-Frame 1/20/2023 Approved THOMAS FINNILA
Green Building Rough 1/20/2023 Approved THOMAS FINNILA
MERV13>=Rough 1/20/2023 Approved THOMAS FINNILA
Deputy Wood Construction 1/23/2023 Conditional Approval DAVID MATSON
Insulation 1/30/2023 Approved JOHN HAYES
Shower Pan 1/30/2023 Approved JOHN HAYES
Drywall Nailing 2/6/2023 Approved JOHN COLEMAN
Interior/Exterior Lathing 2/6/2023 Partial Approval JOHN COLEMAN
Interior/Exterior Lathing 3/6/2023 Approved CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 4/10/2023 SGSOV Not Ready JOHN HAYES
ELECTRICAL-Final 5/3/2023 Approved JOHN HAYES
Final 5/3/2023 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 5/3/2023 Approved JOHN HAYES
Green Building Final 5/3/2023 Approved JOHN HAYES
HVAC-Final 5/3/2023 Approved JOHN HAYES
MERV13>=Final 5/3/2023 Approved JOHN HAYES
PLUMBING-Final 5/3/2023 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 5/3/2023 SGSOV Approved JOHN HAYES
Smoke Detectors 5/3/2023 Approved JOHN HAYES
Final 2/5/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 2/10/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Service/Power Release 2/10/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 9/5/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 9/9/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Service/Power Release 9/9/2025 Approved ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 9/15/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 12/15/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 5/27/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ