6461 N ENFIELD AVE 91335
Certificate Information: 6461 N ENFIELD AVE 91335
- Application / Permit
- 22014-20000-01038
- Plan Check / Job No.
- B22VN03453
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION L-SHAPED ( 45'-3" X 21') TO EX. SFD FOR NEW BEDROOM, BATHROOM, LAUNDRY, DINING ROOM AND KITCHEN. REMODEL LIVING ROOM AND EX. BATHROOM. WORK PER ENGINEER. AUTOMATIC FIRE SPRINKLER SYSTEM REQUIRED.
- Permit Issued
- Issued on 7/15/2022
- Issuing Office
- Current Status
- CofO Issued on 2/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/30/2022 | ROSENDO MEDINA |
| Corrections Issued | 3/31/2022 | ROSENDO MEDINA |
| Plan Check Approved | 7/14/2022 | ROSENDO MEDINA |
| Issued | 7/15/2022 | APPLICANT |
| Building Plans Picked Up | 7/20/2022 | APPLICANT |
| CofO in Progress | 5/9/2023 | DAVID SCANTLIN |
| Permit Finaled | 2/24/2025 | JOHN JANSON |
| CofO Issued | 2/24/2025 | JOHN JANSON |
| Permit Finaled | 2/24/2025 | JOHN JANSON |
Permit Application Clearance Information
| Sewer availability | Cleared | 4/6/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/11/2022 | ROMAN GUTIERREZ |
| Low Impact Development | Cleared | 7/7/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 7/7/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Elite Power Remodeling And Design; Lic. No.: 1053184-B | 22919 STYLES STREET WOODLAND HILLS, CA 91367 |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/1/2022 | Conditional Approval | JEFFREY BULL |
| Footing/Foundation/Slab | 9/12/2022 | Corrections Issued | JEFFREY BULL |
| Footing/Foundation/Slab | 9/19/2022 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 9/23/2022 | Partial Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2022 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 10/7/2022 | Partial Approval | SEAN HAUPT |
| BUILDING-Rough-Frame | 11/4/2022 | Approved | JEFFREY BULL |
| ELECTRICAL-Rough | 11/4/2022 | Approved | JEFFREY BULL |
| Green Building Rough | 11/4/2022 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 11/4/2022 | Not Ready for Inspection | JEFFREY BULL |
| Insulation | 11/8/2022 | Conditional Approval | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 11/8/2022 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 11/8/2022 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 11/8/2022 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 11/14/2022 | Approved | MORRIS JACKSON |
| Deputy Wood Construction | 11/21/2022 | Conditional Approval | JUSTIN HAWLEY |
| Drywall Nailing | 11/30/2022 | Approved | MORRIS JACKSON |
| Final | 2/28/2023 | Corrections Issued | JEFFREY PARD |
| Green Building Final | 2/28/2023 | Not Ready for Inspection | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 2/28/2023 | SGSOV Not Ready | JEFFREY PARD |
| Smoke Detectors | 2/28/2023 | Not Ready for Inspection | JEFFREY PARD |
| Final | 5/8/2023 | OK to Issue CofO | DAVID SCANTLIN |
| Green Building Final | 5/8/2023 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 5/8/2023 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 5/8/2023 | Approved | DAVID SCANTLIN |