411 E 92ND ST 90003

Certificate Information: 411 E 92ND ST 90003

Application / Permit
22014-20000-01031
Plan Check / Job No.
B22VN03441
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*EPLAN* CONVERT (E) DETACHED 1-CAR GARAGE (225 SF) TO ADU AND ADD (391 SF) PER LAMC 12.22A.33(c)-(d).
Permit Issued
Issued on 5/4/2022
Issuing Office
Current Status
CofO Issued on 4/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/7/2022 APPLICANT
Assigned to Plan Check Engineer 3/8/2022 VIVIAN LAO
Corrections Issued 3/9/2022 VIVIAN LAO
Plan Check Approved 4/18/2022 VIVIAN LAO
Issued 5/4/2022 APPLICANT
CofO in Progress 4/18/2023 LILIANA PORTILLO
No Progress 4/18/2023 LILIANA PORTILLO
CofO in Progress 4/18/2023 LILIANA PORTILLO
Permit Finaled 4/24/2023 DEROLD HAUFF
CofO Issued 4/24/2023 DEROLD HAUFF
Permit Finaled 4/24/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/18/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 3/18/2022 JEANIE LAM
Roof/Waste drainage to street Cleared 3/18/2022 JEANIE LAM
Sewer availability Cleared 3/18/2022 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Francisco Javier; Lic. No.: C76510 2705 S FREMONT AVE APT D      ALHAMBRA, CA 91803

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/11/2022 Partial Inspection LILIANA PORTILLO
Pre-Inspection 6/8/2022 Partial Inspection LILIANA PORTILLO
PLUMBING-Rough 6/23/2022 Partial Approval LILIANA PORTILLO
Sewer 6/23/2022 Approved LILIANA PORTILLO
Underground Mechanical 6/23/2022 Partial Approval LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 6/30/2022 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 6/30/2022 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 8/25/2022 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 8/25/2022 Approved LILIANA PORTILLO
Deputy Wood Construction 10/19/2022 Conditional Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 10/25/2022 Approved LILIANA PORTILLO
PLUMBING-Rough 10/25/2022 Corrections Issued LILIANA PORTILLO
Pre-Inspection 10/27/2022 Partial Inspection LILIANA PORTILLO
BUILDING-Rough-Frame 11/14/2022 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 11/14/2022 Corrections Issued LILIANA PORTILLO
HVAC-Rough 11/14/2022 Approved LILIANA PORTILLO
PLUMBING-Rough 11/14/2022 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 12/22/2022 Approved LILIANA PORTILLO
ELECTRICAL-Rough 12/22/2022 Approved LILIANA PORTILLO
Green Building Rough 12/22/2022 Approved LILIANA PORTILLO
Insulation 12/22/2022 Corrections Issued LILIANA PORTILLO
Interior/Exterior Lathing 12/22/2022 Approved LILIANA PORTILLO
Drywall Nailing 1/3/2023 Partial Approval LILIANA PORTILLO
Drywall Nailing 1/13/2023 Approved LILIANA PORTILLO
Insulation 1/13/2023 Approved LILIANA PORTILLO
ELECTRICAL-Final 2/1/2023 Not Ready for Inspection LILIANA PORTILLO
Green Building Final 2/1/2023 Not Ready for Inspection LILIANA PORTILLO
Pre-Inspection 2/1/2023 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 2/1/2023 SGSOV Not Ready LILIANA PORTILLO
Smoke Detectors 2/1/2023 Approved LILIANA PORTILLO
Final 3/3/2023 Corrections Issued LILIANA PORTILLO
Green Building Final 3/3/2023 Corrections Issued LILIANA PORTILLO
HVAC-Final 3/3/2023 Approved LILIANA PORTILLO
PLUMBING-Final 3/3/2023 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 3/3/2023 SGSOV Not Ready LILIANA PORTILLO
Service/Power Release 3/3/2023 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Final 3/23/2023 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Final 3/29/2023 Not Ready for Inspection LILIANA PORTILLO
Final 3/29/2023 Not Ready for Inspection LILIANA PORTILLO
Gas Test 3/29/2023 Approved LILIANA PORTILLO
Green Building Final 3/29/2023 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 3/29/2023 SGSOV Approved LILIANA PORTILLO
ELECTRICAL-Final 4/17/2023 Approved LILIANA PORTILLO
Final 4/17/2023 OK to Issue CofO LILIANA PORTILLO
PLUMBING-Final 4/17/2023 Approved LILIANA PORTILLO
Service/Power Release 4/18/2023 Approved LILIANA PORTILLO