10115-10115 1/2 N MONOGRAM AVE 91343
Certificate Information: 10115-10115 1/2 N MONOGRAM AVE 91343
- Application / Permit
- 22014-20000-01029
- Plan Check / Job No.
- B22VN03439
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Conversion of the Attached Garage into ADU PER ATTACHED ADU ORDINANCE , ALL WORK per WFPP
- Permit Issued
- Issued on 3/17/2022
- Issuing Office
- Current Status
- Issued on 3/17/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/8/2022 | CARLOS MONTES |
| Corrections Issued | 3/8/2022 | CARLOS MONTES |
| Plan Check Approved | 3/16/2022 | CARLOS MONTES |
| Issued | 3/17/2022 | APPLICANT |
| CofO in Progress | 5/26/2023 | JAVIER RAMOS JR |
| Permit Finaled-Status Void | 5/26/2023 | MICHAEL SMITH |
| CofO Issued-Status Void | 5/26/2023 | MICHAEL SMITH |
| Re-Activate Permit | 6/26/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 3/10/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 3/10/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 3/15/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/11/2022 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Rough | 5/12/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| PLUMBING-Rough | 5/12/2022 | Partial Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 5/20/2022 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 6/6/2022 | Partial Approval | JAVIER RAMOS JR |
| Sewer | 6/6/2022 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 6/10/2022 | Partial Approval | JAVIER RAMOS JR |
| Sewer | 6/10/2022 | Approved | JAVIER RAMOS JR |
| Pre-Inspection | 7/1/2022 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 7/8/2022 | Corrections Issued | DEANDRE HOFFMAN |
| PLUMBING-Rough | 7/15/2022 | Corrections Issued | DEANDRE HOFFMAN |
| ELECTRICAL-Rough | 7/20/2022 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 7/20/2022 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 7/29/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Insulation | 8/16/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 8/24/2022 | Corrections Issued | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 8/24/2022 | Approved | JAVIER RAMOS JR |
| Insulation | 8/24/2022 | Corrections Issued | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 9/6/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Green Building Rough | 9/6/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 9/12/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Pre-Inspection | 9/12/2022 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 9/21/2022 | No Access for Inspection | JAVIER RAMOS JR |
| Green Building Rough | 9/21/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Green Building Rough | 9/30/2022 | Approved | JAVIER RAMOS JR |
| Insulation | 9/30/2022 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 9/30/2022 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 10/13/2022 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 10/13/2022 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 11/2/2022 | Approved | JAVIER RAMOS JR |
| Shower Pan | 11/2/2022 | Approved | JAVIER RAMOS JR |
| Pre-Inspection | 2/23/2023 | Corrections Issued | JAVIER RAMOS JR |
| ELECTRICAL-Final | 3/31/2023 | Approved | JAVIER RAMOS JR |
| Final | 3/31/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Green Building Final | 3/31/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 3/31/2023 | SGSOV Not Ready | JAVIER RAMOS JR |
| Smoke Detectors | 3/31/2023 | Approved | JAVIER RAMOS JR |
| Final | 5/10/2023 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 5/10/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 5/10/2023 | SGSOV Not Ready | JAVIER RAMOS JR |
| Final | 5/17/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Gas Test | 5/17/2023 | Approved | JAVIER RAMOS JR |
| Green Building Final | 5/17/2023 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 5/17/2023 | SGSOV Approved | JAVIER RAMOS JR |
| Final | 5/26/2023 | OK to Issue CofO | JAVIER RAMOS JR |
| Service/Power Release | 5/26/2023 | Approved | JAVIER RAMOS JR |