12650 N BROMONT AVE 91340

Certificate Information: 12650 N BROMONT AVE 91340

Application / Permit
22014-20000-01018
Plan Check / Job No.
B22VN03390
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
15'-5" x 36' ADDITION TO EXISTING SINGLE FAMILY DWELLING
Permit Issued
Issued on 6/5/2022
Issuing Office
Current Status
CofO Issued on 10/15/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/4/2022 APPLICANT
Assigned to Plan Check Engineer 3/17/2022 SELLA BENYAMIN
Corrections Issued 3/22/2022 SELLA BENYAMIN
Quality Review Completed 3/24/2022 STEVEN KIM
Building Plans Picked Up 3/25/2022 APPLICANT
Plan Check Approved 5/19/2022 SELLA BENYAMIN
Issued 6/5/2022 APPLICANT
CofO in Progress 9/16/2022 ARAM AVEDISIAN
Permit Finaled 10/15/2022 MICHAEL SMITH
CofO Issued 10/15/2022 MICHAEL SMITH
Permit Finaled 10/15/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/30/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 3/30/2022 DAGOVERTO GUERRERO
Low Impact Development Cleared 4/22/2022 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 4/26/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Ramirez, Cid, Jose Carlos; Lic. No.: C91046 5164 N RATON CIR      LONG BEACH, CA 90807

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 6/21/2022 No Result Entered KENNETH KUROWSKI
Footing/Foundation/Slab 6/22/2022 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 6/30/2022 Partial Approval ARAM AVEDISIAN
Insulation 6/30/2022 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 7/13/2022 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Rough 7/26/2022 Corrections Issued CHRISTOPHER DELLEFIELD
HVAC-Rough 7/26/2022 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 7/29/2022 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 7/29/2022 Approved ARAM AVEDISIAN
Green Building Rough 7/29/2022 Conditional Approval ARAM AVEDISIAN
MERV13>=Rough 7/29/2022 Approved ARAM AVEDISIAN
Insulation 8/1/2022 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 8/1/2022 Partial Approval ARAM AVEDISIAN
Drywall Nailing 8/30/2022 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 9/13/2022 Approved ARAM AVEDISIAN
Final 9/13/2022 Corrections Issued ARAM AVEDISIAN
Green Building Final 9/13/2022 Approved ARAM AVEDISIAN
Green Building Rough 9/13/2022 Approved ARAM AVEDISIAN
MERV13>=Final 9/13/2022 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 9/13/2022 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 9/13/2022 Approved ARAM AVEDISIAN
ELECTRICAL-Final 9/16/2022 Approved ARAM AVEDISIAN
Final 9/16/2022 OK to Issue CofO ARAM AVEDISIAN
HVAC-Final 9/16/2022 Approved ARAM AVEDISIAN
PLUMBING-Final 9/16/2022 Approved ARAM AVEDISIAN