13354 W HARDING ST 91340
Certificate Information: 13354 W HARDING ST 91340
- Application / Permit
- 22014-20000-01017
- Plan Check / Job No.
- B22VN03390
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 17'-2" X 20'-6" 2 STORY ADDITION TO AND CONVERT EXISTING DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 6/9/2022
- Issuing Office
- Current Status
- CofO Issued on 10/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2022 | SELLA BENYAMIN |
| Corrections Issued | 3/22/2022 | SELLA BENYAMIN |
| Quality Review Completed | 3/24/2022 | STEVEN KIM |
| Building Plans Picked Up | 3/25/2022 | APPLICANT |
| Plan Check Approved | 5/19/2022 | SELLA BENYAMIN |
| Issued | 6/9/2022 | APPLICANT |
| CofO in Progress | 9/16/2022 | ARAM AVEDISIAN |
| CofO Issued | 10/29/2022 | MICHAEL SMITH |
| Permit Finaled | 10/29/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 3/25/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 3/30/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 3/30/2022 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 4/22/2022 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 4/26/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/15/2022 | Partial Approval | ARAM AVEDISIAN |
| Deputy Reinf. Concrete | 6/21/2022 | No Result Entered | KENNETH KUROWSKI |
| Footing/Foundation/Slab | 6/21/2022 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/5/2022 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/13/2022 | Corrections Issued | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2022 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 7/26/2022 | Partial Approval | DEANDRE HOFFMAN |
| ELECTRICAL-Rough | 7/26/2022 | Approved | DEANDRE HOFFMAN |
| Green Building Rough | 7/26/2022 | Not Ready for Inspection | DEANDRE HOFFMAN |
| HVAC-Rough | 7/26/2022 | Approved | DEANDRE HOFFMAN |
| PLUMBING-Rough | 7/26/2022 | Approved | DEANDRE HOFFMAN |
| Deputy Wood Construction | 7/27/2022 | No Result Entered | KENNETH KUROWSKI |
| BUILDING-Rough-Frame | 7/29/2022 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 7/29/2022 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 7/29/2022 | Partial Approval | ARAM AVEDISIAN |
| MERV13>=Rough | 7/29/2022 | Approved | ARAM AVEDISIAN |
| Insulation | 8/1/2022 | Approved | ARAM AVEDISIAN |
| Underground Mechanical | 8/1/2022 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 8/4/2022 | Approved | ARAM AVEDISIAN |
| Final | 9/13/2022 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 9/13/2022 | Approved | ARAM AVEDISIAN |
| MERV13>=Final | 9/13/2022 | Not Ready for Inspection | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 9/13/2022 | SGSOV Not Ready | ARAM AVEDISIAN |
| Smoke Detectors | 9/13/2022 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 9/16/2022 | Approved | ARAM AVEDISIAN |
| Final | 9/16/2022 | OK to Issue CofO | ARAM AVEDISIAN |
| HVAC-Final | 9/16/2022 | Approved | ARAM AVEDISIAN |
| MERV13>=Final | 9/16/2022 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 9/16/2022 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 9/16/2022 | SGSOV Approved | ARAM AVEDISIAN |