15949 W LEMARSH ST 91343
Certificate Information: 15949 W LEMARSH ST 91343
- Application / Permit
- 22014-20000-01011
- Plan Check / Job No.
- B22VN03373
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 12'-6" X 27'-6" ADDITION TO THE (E) SFD PER ENGINEERING.
- Permit Issued
- Issued on 4/18/2022
- Issuing Office
- Current Status
- CofO Issued on 11/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2022 | ARTIN ZARUKIAN |
| Corrections Issued | 3/13/2022 | ARTIN ZARUKIAN |
| Applicant returned to address corrections | 3/25/2022 | ARTIN ZARUKIAN |
| Plan Check Approved | 4/8/2022 | ARTIN ZARUKIAN |
| Issued | 4/18/2022 | APPLICANT |
| Building Plans Picked Up | 5/3/2022 | APPLICANT |
| CofO in Progress | 11/4/2025 | CHRISTOPHER ROJAS |
| Permit Finaled | 11/18/2025 | RUBEN SALAS |
| CofO Issued | 11/18/2025 | RUBEN SALAS |
| Permit Finaled | 11/18/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/21/2022 | VASIL MIHALEV |
| Eng Process Fee Ord 176,300 | Cleared | 3/22/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 3/22/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 3/22/2022 | CARLOS AGUILERA |
| Hold | Cleared | 7/15/2022 | JASON SHEETS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barzegar,, Leon None; Lic. No.: C41760 | 2748 HOLLISTER TER GLENDALE, CA 91206 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/24/2025 | Conditional Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 1/30/2025 | Corrections Issued | ROBERT GOLD |
| Footing/Foundation/Slab | 1/31/2025 | Approved | ROBERT GOLD |
| BUILDING-Rough-Frame | 2/13/2025 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2025 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 2/13/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2025 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 3/18/2025 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 4/10/2025 | Partial Approval | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 5/1/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 5/1/2025 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 5/13/2025 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 5/13/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 5/20/2025 | Approved | CHRISTOPHER ROJAS |
| Insulation | 5/20/2025 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 5/20/2025 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 5/29/2025 | Conditional Approval | MICHAEL CORTEZ |
| Shower Pan | 8/12/2025 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 8/15/2025 | Partial Approval | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 8/18/2025 | Partial Approval | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 10/23/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| HVAC-Final | 10/23/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 10/24/2025 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 11/3/2025 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 11/3/2025 | Approved | CHRISTOPHER ROJAS |
| Final | 11/3/2025 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Green Building Final | 11/3/2025 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 11/3/2025 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 11/3/2025 | SGSOV Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 11/3/2025 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Final | 11/17/2025 | Approved | CHRISTOPHER ROJAS |