10600-10602 N ETON AVE 91311

Certificate Information: 10600-10602 N ETON AVE 91311

Application / Permit
22014-20000-00999
Plan Check / Job No.
B22VN03338
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Proposed garage conversion to ADU & interior model with engineering.
Permit Issued
Issued on 6/16/2022
Issuing Office
Current Status
CofO Issued on 1/29/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/14/2022 APPLICANT
Assigned to Plan Check Engineer 3/16/2022 JOE VO
Corrections Issued 3/17/2022 JOE VO
Plan Check Approved 5/2/2022 JOE VO
Issued 6/16/2022 APPLICANT
CofO in Progress 1/28/2026 DAVID SCANTLIN
Permit Finaled 1/29/2026 JOHN JANSON
CofO Issued 1/29/2026 JOHN JANSON
Permit Finaled 1/29/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/31/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 3/31/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 4/12/2022 DAGOVERTO GUERRERO

Contact Information

Contractor B H Remodeling; Lic. No.: 1036402-B 38 EAGLECREEK      IRVINE, CA 92618
Engineer Rivera,, Bobby Zulueta; Lic. No.: C77218 14703 HELWIG AVE      NORWALK, CA 90650

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/23/2022 Approved JEFFREY PARD
PLUMBING-Rough 6/23/2022 Corrections Issued JEFFREY PARD
BUILDING-Rough-Frame 6/29/2022 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Rough 6/29/2022 Not Ready for Inspection JEFFREY PARD
Green Building Rough 6/29/2022 Not Ready for Inspection JEFFREY PARD
Insulation 6/29/2022 Not Ready for Inspection JEFFREY PARD
PLUMBING-Rough 6/29/2022 Not Ready for Inspection JEFFREY PARD
Wood Frame 6/29/2022 Not Ready for Inspection JEFFREY PARD
BUILDING-Rough-Frame 7/21/2022 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Rough 7/21/2022 Not Ready for Inspection JEFFREY PARD
Green Building Rough 7/21/2022 Not Ready for Inspection JEFFREY PARD
PLUMBING-Rough 7/21/2022 Not Ready for Inspection JEFFREY PARD
Wood Frame 7/21/2022 Not Ready for Inspection JEFFREY PARD
BUILDING-Rough-Frame 7/27/2022 No Access for Inspection JEFFREY PARD
Green Building Rough 7/27/2022 No Access for Inspection JEFFREY PARD
PLUMBING-Rough 7/27/2022 No Access for Inspection JEFFREY PARD
Wood Frame 7/27/2022 No Access for Inspection JEFFREY PARD
PLUMBING-Rough 8/16/2022 Not Ready for Inspection JEFFREY PARD
Wood Frame 8/16/2022 Not Ready for Inspection JEFFREY PARD
Insulation 8/23/2022 Approved JEFFREY PARD
Interior/Exterior Lathing 8/23/2022 Approved JEFFREY PARD
Wood Frame 8/23/2022 Partial Approval JEFFREY PARD
ELECTRICAL-Rough 9/8/2022 Not Ready for Inspection JEFFREY PARD
Wood Frame 9/8/2022 Not Ready for Inspection JEFFREY PARD
BUILDING-Rough-Frame 9/16/2022 Corrections Issued DAVID SANDOVAL
ELECTRICAL-Rough 9/16/2022 Not Ready for Inspection DAVID SANDOVAL
Wood Frame 9/22/2022 No Access for Inspection JEFFREY BULL
Wood Frame 11/7/2022 Corrections Issued DAVID SCANTLIN
Pre-Inspection 9/25/2024 Partial Inspection KRISTEN CAUSEY
Pre-Inspection 9/30/2024 Not Ready for Inspection DAVID SCANTLIN
BUILDING-Rough-Frame 11/7/2024 Corrections Issued DAVID SCANTLIN
PLUMBING-Rough 12/20/2024 Approved DAVID SCANTLIN
ELECTRICAL-Rough 2/14/2025 Approved KRISTEN CAUSEY
HVAC-Rough 3/3/2025 Approved DAVID SCANTLIN
Service/Power Release 3/3/2025 Not Ready for Inspection DAVID SCANTLIN
Service/Power Release 3/20/2025 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 6/11/2025 Approved DAVID SCANTLIN
Drywall Nailing 6/11/2025 Approved DAVID SCANTLIN
Green Building Rough 6/11/2025 Approved DAVID SCANTLIN
Insulation 6/11/2025 Approved DAVID SCANTLIN
Interior/Exterior Lathing 7/14/2025 Approved DAVID SCANTLIN
Shower Pan 7/14/2025 Approved DAVID SCANTLIN
Final 1/20/2026 Corrections Issued DAVID SCANTLIN
Green Building Final 1/20/2026 Not Ready for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 1/20/2026 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 1/20/2026 Approved DAVID SCANTLIN
Final 1/27/2026 OK to Issue CofO DAVID SCANTLIN
Green Building Final 1/27/2026 Approved DAVID SCANTLIN
Service/Power Release 1/27/2026 Approved DAVID SCANTLIN