13337-13339 W DYER ST 91342

Certificate Information: 13337-13339 W DYER ST 91342

Application / Permit
22014-20000-00993
Plan Check / Job No.
B22VN03333
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePLAN. CONVERT (E) ATTACHED GARAGE AND 137 SF OF (E) KITCHEN IN THE SINGLE FAMILY DWELLING INTO AN ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A). KITCHEN REMODEL.
Permit Issued
Issued on 5/9/2022
Issuing Office
Current Status
CofO Issued on 2/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/3/2022 APPLICANT
Corrections Issued 3/4/2022 KEVIN MORALES
Assigned to Plan Check Engineer 3/5/2022 KEVIN MORALES
Corrections Issued 4/27/2022 KEVIN MORALES
Plan Check Approved 5/7/2022 KEVIN MORALES
Issued 5/9/2022 APPLICANT
CofO in Progress 1/25/2023 ARAM AVEDISIAN
CofO Issued 2/8/2023 MICHAEL SMITH
Permit Finaled 2/8/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 3/16/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 3/17/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 3/17/2022 JOSE DUARTE-DIAZ
Grading Pre-Inspection Cleared 4/20/2022 KIRK LINKLATER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/16/2022 Partial Inspection JOHN HAYES
Pre-Inspection 6/13/2022 Approved JOHN HAYES
Deputy Drilled-In Anchors 7/13/2022 Conditional Approval ARAM AVEDISIAN
Footing/Foundation/Slab 7/26/2022 Approved DEANDRE HOFFMAN
PLUMBING-Rough 7/26/2022 Partial Approval DEANDRE HOFFMAN
ELECTRICAL-Rough 9/15/2022 Corrections Issued ARAM AVEDISIAN
HVAC-Rough 9/15/2022 Not Ready for Inspection ARAM AVEDISIAN
PLUMBING-Rough 9/15/2022 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 9/20/2022 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 9/20/2022 Partial Approval ARAM AVEDISIAN
HVAC-Rough 9/20/2022 Partial Approval ARAM AVEDISIAN
Interior/Exterior Lathing 9/20/2022 Partial Approval ARAM AVEDISIAN
Insulation 9/26/2022 Partial Approval ARAM AVEDISIAN
Drywall Nailing 9/28/2022 Partial Approval ARAM AVEDISIAN
Green Building Rough 9/28/2022 Approved ARAM AVEDISIAN
Insulation 11/15/2022 Approved ARAM AVEDISIAN
Special/Order Compliance 11/15/2022 Approved ARAM AVEDISIAN
Drywall Nailing 11/28/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 1/10/2023 Approved ARAM AVEDISIAN
Final 1/10/2023 Corrections Issued ARAM AVEDISIAN
Green Building Final 1/10/2023 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 1/10/2023 SGSOV Not Ready ARAM AVEDISIAN
Smoke Detectors 1/10/2023 Not Ready for Inspection ARAM AVEDISIAN
ELECTRICAL-Final 1/25/2023 Approved ARAM AVEDISIAN
Final 1/25/2023 OK to Issue CofO ARAM AVEDISIAN
HVAC-Final 1/25/2023 Approved ARAM AVEDISIAN
PLUMBING-Final 1/25/2023 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 1/25/2023 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 1/25/2023 Approved ARAM AVEDISIAN