13015 W GREENLEAF ST 91604

Certificate Information: 13015 W GREENLEAF ST 91604

Application / Permit
22014-20000-00973
Plan Check / Job No.
B22VN03260
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND MAJOR REMODEL TO (E) 2-STORY SFD WITH ROOF TOP AND GARAGE
Permit Issued
Issued on 2/10/2023
Issuing Office
Metro
Current Status
CofO Issued on 6/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/21/2022 APPLICANT
Assigned to Plan Check Engineer 4/14/2022 SUNMIN LEE
Corrections Issued 4/21/2022 SUNMIN LEE
Building Plans Picked Up 5/12/2022 APPLICANT
Quality Review Completed 5/17/2022 MICHAEL PEREZ
Applicant returned to address corrections 12/14/2022 SUNMIN LEE
Applicant returned to address corrections 12/23/2022 SUNMIN LEE
Plan Check Approved 1/20/2023 SUNMIN LEE
Issued 2/10/2023 APPLICANT
CofO in Progress 12/12/2024 CHRISTOPHE COCHRAN
CofO in Progress 2/12/2025 JACK KARGODORIAN
CofO Issued 6/4/2025 RUBEN SALAS
Permit Finaled 6/4/2025 RUBEN SALAS

Permit Application Clearance Information

Permit Cleared 7/15/2022 LEE GUILBEAUX
Street Frontage Cleared 7/15/2022 LEE GUILBEAUX
Sewer availability Cleared 7/18/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 8/8/2022 LEE GUILBEAUX
Low Impact Development Cleared 11/3/2022 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 11/3/2022 DAGOVERTO GUERRERO
Trees in Parkway Cleared 11/4/2022 ADALBERTO VERA
ZI Cleared 11/8/2022 NELSON RODRIGUEZ
Excavation more than 5-ft deep Cleared 12/23/2022 CALOSHA APPROVED
GPI Written Notices Cleared 12/23/2022 SUNMIN LEE
Grading Pre-Inspection Cleared 12/23/2022 SUNMIN LEE

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367
Engineer Koester,, Ronald Norman; Lic. No.: L5930 1815 SHADOW CANYON RD      ACTON, CA 93510
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/21/2023 Approved CHRISTOPHE COCHRAN
Footing/Foundation/Slab 5/17/2023 Corrections Issued CHRISTOPHE COCHRAN
Footing/Foundation/Slab 5/19/2023 Partial Approval JUAN VALENZUELA
Underground Mechanical 5/19/2023 Partial Approval JUAN VALENZUELA
Deputy Reinf. Concrete 5/22/2023 Conditional Approval MICHAEL SMITH
Excavation/Setback/Form/Re-Bar 5/31/2023 Corrections Issued CHRISTOPHE COCHRAN
Footing/Foundation/Slab 5/31/2023 Partial Approval CHRISTOPHE COCHRAN
Underground Mechanical 5/31/2023 Approved CHRISTOPHE COCHRAN
Deputy Shotcrete 6/6/2023 Conditional Approval MICHAEL SMITH
Deputy Shotcrete 6/8/2023 Conditional Approval JUAN VALENZUELA
Grading Pre-Inspection 6/23/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Footing/Foundation/Slab 7/3/2023 Partial Approval CHRISTOPHE COCHRAN
Footing/Foundation/Slab 7/17/2023 Corrections Issued CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 7/20/2023 Partial Approval CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 7/31/2023 Conditional Approval RUBEN SALAS
Footing/Foundation/Slab 8/3/2023 Approved CHRISTOPHE COCHRAN
Deputy Steel/Welding 8/25/2023 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 8/31/2023 Corrections Issued CHRISTOPHE COCHRAN
Structural Steel Frame 8/31/2023 Corrections Issued CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 9/5/2023 Partial Approval CHRISTOPHE COCHRAN
Structural Steel Frame 9/5/2023 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 9/6/2023 Approved CHRISTOPHE COCHRAN
Light Gage Steel Frame 9/6/2023 Approved CHRISTOPHE COCHRAN
Structural Steel Frame 9/6/2023 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 9/7/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Deputy Wood Construction 10/10/2023 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 10/31/2023 Partial Approval CHRISTOPHE COCHRAN
HVAC-Final 10/31/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 11/29/2023 Partial Approval CHRISTOPHE COCHRAN
Deputy Wood Construction 11/29/2023 Conditional Approval JUAN VALENZUELA
Green Building Rough 11/29/2023 Approved CHRISTOPHE COCHRAN
Wood Frame 11/29/2023 Partial Approval CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 12/20/2023 Not Ready for Inspection JOHN COLEMAN
ELECTRICAL-Rough 12/20/2023 Approved JOHN COLEMAN
HVAC-Rough 12/20/2023 Approved JOHN COLEMAN
PLUMBING-Rough 12/20/2023 Approved JOHN COLEMAN
Sewer 12/20/2023 Not Ready for Inspection JOHN COLEMAN
Wood Frame 12/20/2023 Not Ready for Inspection JOHN COLEMAN
ELECTRICAL-Rough 12/22/2023 Approved CHRISTOPHE COCHRAN
HVAC-Rough 12/22/2023 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 12/22/2023 Approved CHRISTOPHE COCHRAN
Sewer 12/22/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Wood Frame 12/22/2023 Partial Approval CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 12/28/2023 Approved CHRISTOPHE COCHRAN
Sewer 12/28/2023 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 2/13/2024 Corrections Issued JOHN COLEMAN
Interior/Exterior Lathing 2/22/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Interior/Exterior Lathing 2/27/2024 Partial Approval CHRISTOPHE COCHRAN
Insulation 2/29/2024 Approved CHRISTOPHE COCHRAN
Shower Pan 2/29/2024 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 3/6/2024 Approved MATTHEW NELSON
Drywall Nailing 3/14/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Pre-Inspection 4/25/2024 Approved JOHN COLEMAN
Pre-Inspection 5/31/2024 Partial Inspection CHRISTOPHE COCHRAN
Underground Mechanical 6/17/2024 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 6/27/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Drywall Nailing 8/28/2024 Approved CHRISTOPHE COCHRAN
Final 8/28/2024 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 8/28/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 8/28/2024 SGSOV Not Ready CHRISTOPHE COCHRAN
Smoke Detectors 8/28/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Final 9/6/2024 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 9/6/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 9/6/2024 SGSOV Not Ready CHRISTOPHE COCHRAN
Smoke Detectors 9/6/2024 Approved CHRISTOPHE COCHRAN
Final 11/18/2024 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 11/18/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 11/18/2024 SGSOV Not Ready CHRISTOPHE COCHRAN
Final 12/12/2024 OK to Issue CofO CHRISTOPHE COCHRAN
Green Building Final 12/12/2024 Approved CHRISTOPHE COCHRAN
Pre-Inspection 12/12/2024 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 12/12/2024 SGSOV Approved CHRISTOPHE COCHRAN
Service/Power Release 2/6/2025 Approved CHRISTOPHE COCHRAN
Final 2/11/2025 OK to Issue CofO JACK KARGODORIAN