13015 W GREENLEAF ST 91604
Certificate Information: 13015 W GREENLEAF ST 91604
- Application / Permit
- 22014-20000-00973
- Plan Check / Job No.
- B22VN03260
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND MAJOR REMODEL TO (E) 2-STORY SFD WITH ROOF TOP AND GARAGE
- Permit Issued
- Issued on 2/10/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/14/2022 | SUNMIN LEE |
| Corrections Issued | 4/21/2022 | SUNMIN LEE |
| Building Plans Picked Up | 5/12/2022 | APPLICANT |
| Quality Review Completed | 5/17/2022 | MICHAEL PEREZ |
| Applicant returned to address corrections | 12/14/2022 | SUNMIN LEE |
| Applicant returned to address corrections | 12/23/2022 | SUNMIN LEE |
| Plan Check Approved | 1/20/2023 | SUNMIN LEE |
| Issued | 2/10/2023 | APPLICANT |
| CofO in Progress | 12/12/2024 | CHRISTOPHE COCHRAN |
| CofO in Progress | 2/12/2025 | JACK KARGODORIAN |
| CofO Issued | 6/4/2025 | RUBEN SALAS |
| Permit Finaled | 6/4/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Permit | Cleared | 7/15/2022 | LEE GUILBEAUX |
| Street Frontage | Cleared | 7/15/2022 | LEE GUILBEAUX |
| Sewer availability | Cleared | 7/18/2022 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 8/8/2022 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 11/3/2022 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 11/3/2022 | DAGOVERTO GUERRERO |
| Trees in Parkway | Cleared | 11/4/2022 | ADALBERTO VERA |
| ZI | Cleared | 11/8/2022 | NELSON RODRIGUEZ |
| Excavation more than 5-ft deep | Cleared | 12/23/2022 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 12/23/2022 | SUNMIN LEE |
| Grading Pre-Inspection | Cleared | 12/23/2022 | SUNMIN LEE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
| Engineer | Koester,, Ronald Norman; Lic. No.: L5930 | 1815 SHADOW CANYON RD ACTON, CA 93510 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/21/2023 | Approved | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 5/17/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 5/19/2023 | Partial Approval | JUAN VALENZUELA |
| Underground Mechanical | 5/19/2023 | Partial Approval | JUAN VALENZUELA |
| Deputy Reinf. Concrete | 5/22/2023 | Conditional Approval | MICHAEL SMITH |
| Excavation/Setback/Form/Re-Bar | 5/31/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 5/31/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Underground Mechanical | 5/31/2023 | Approved | CHRISTOPHE COCHRAN |
| Deputy Shotcrete | 6/6/2023 | Conditional Approval | MICHAEL SMITH |
| Deputy Shotcrete | 6/8/2023 | Conditional Approval | JUAN VALENZUELA |
| Grading Pre-Inspection | 6/23/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 7/3/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 7/17/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Deputy Reinf. Concrete | 7/31/2023 | Conditional Approval | RUBEN SALAS |
| Footing/Foundation/Slab | 8/3/2023 | Approved | CHRISTOPHE COCHRAN |
| Deputy Steel/Welding | 8/25/2023 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 8/31/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| Structural Steel Frame | 8/31/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Structural Steel Frame | 9/5/2023 | Approved | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/6/2023 | Approved | CHRISTOPHE COCHRAN |
| Light Gage Steel Frame | 9/6/2023 | Approved | CHRISTOPHE COCHRAN |
| Structural Steel Frame | 9/6/2023 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 9/7/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Deputy Wood Construction | 10/10/2023 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| HVAC-Final | 10/31/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 11/29/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Deputy Wood Construction | 11/29/2023 | Conditional Approval | JUAN VALENZUELA |
| Green Building Rough | 11/29/2023 | Approved | CHRISTOPHE COCHRAN |
| Wood Frame | 11/29/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 12/20/2023 | Not Ready for Inspection | JOHN COLEMAN |
| ELECTRICAL-Rough | 12/20/2023 | Approved | JOHN COLEMAN |
| HVAC-Rough | 12/20/2023 | Approved | JOHN COLEMAN |
| PLUMBING-Rough | 12/20/2023 | Approved | JOHN COLEMAN |
| Sewer | 12/20/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Wood Frame | 12/20/2023 | Not Ready for Inspection | JOHN COLEMAN |
| ELECTRICAL-Rough | 12/22/2023 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 12/22/2023 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 12/22/2023 | Approved | CHRISTOPHE COCHRAN |
| Sewer | 12/22/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Wood Frame | 12/22/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 12/28/2023 | Approved | CHRISTOPHE COCHRAN |
| Sewer | 12/28/2023 | Approved | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2024 | Corrections Issued | JOHN COLEMAN |
| Interior/Exterior Lathing | 2/22/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 2/27/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Insulation | 2/29/2024 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 2/29/2024 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 3/6/2024 | Approved | MATTHEW NELSON |
| Drywall Nailing | 3/14/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Pre-Inspection | 4/25/2024 | Approved | JOHN COLEMAN |
| Pre-Inspection | 5/31/2024 | Partial Inspection | CHRISTOPHE COCHRAN |
| Underground Mechanical | 6/17/2024 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 6/27/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Drywall Nailing | 8/28/2024 | Approved | CHRISTOPHE COCHRAN |
| Final | 8/28/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 8/28/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 8/28/2024 | SGSOV Not Ready | CHRISTOPHE COCHRAN |
| Smoke Detectors | 8/28/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Final | 9/6/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 9/6/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 9/6/2024 | SGSOV Not Ready | CHRISTOPHE COCHRAN |
| Smoke Detectors | 9/6/2024 | Approved | CHRISTOPHE COCHRAN |
| Final | 11/18/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 11/18/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 11/18/2024 | SGSOV Not Ready | CHRISTOPHE COCHRAN |
| Final | 12/12/2024 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| Green Building Final | 12/12/2024 | Approved | CHRISTOPHE COCHRAN |
| Pre-Inspection | 12/12/2024 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 12/12/2024 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 2/6/2025 | Approved | CHRISTOPHE COCHRAN |
| Final | 2/11/2025 | OK to Issue CofO | JACK KARGODORIAN |