723 E 85TH ST 90001

Certificate Information: 723 E 85TH ST 90001

Application / Permit
22014-20000-00968
Plan Check / Job No.
B22VN03237
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
12' X 24'-5" IRR.-SHAPE 2-STORY ADDITION TO REAR OF (E) SFD. ALL WORK DONE PER ENGINEERING.
Permit Issued
Issued on 1/31/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 1/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/2/2022 APPLICANT
Assigned to Plan Check Engineer 3/10/2022 GURUNATH NESARAJAH
Corrections Issued 3/13/2022 GURUNATH NESARAJAH
Building Plans Picked Up 3/31/2022 APPLICANT
Plan Check Approved 10/27/2022 ALEC MOUSAKHANIAN
Issued 1/31/2023 APPLICANT
CofO in Progress 1/6/2026 JOHN QUINTANILLA
Permit Finaled 1/9/2026 DEROLD HAUFF
CofO Issued 1/9/2026 DEROLD HAUFF
Permit Finaled 1/9/2026 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 6/7/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 6/17/2022 AMAAN MALIK
Low Impact Development Cleared 10/14/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 10/27/2022 AMAAN MALIK

Contact Information

Contractor Owner-Builder       ,
Engineer Fernandez,, Samuel; Lic. No.: C70886 8225 BRIMFIELD AVE      PANORAMA CITY, CA 91402

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Service/Power Release 3/10/2023 Not Ready for Inspection LILIANA PORTILLO
Deputy Drilled-In Anchors 3/29/2023 Conditional Approval LILIANA PORTILLO
Footing/Foundation/Slab 3/31/2023 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 4/10/2023 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 4/10/2023 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 4/13/2023 Partial Approval RUBEN SALAS
Floor/Roof Diaphrgm/Shear Wall 4/21/2023 Partial Approval LILIANA PORTILLO
BUILDING-Rough-Frame 6/6/2023 Partial Approval STUART CHAPMAN
ELECTRICAL-Rough 6/6/2023 Approved STUART CHAPMAN
Green Building Rough 6/6/2023 Not Ready for Inspection STUART CHAPMAN
HVAC-Rough 6/6/2023 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Rough 6/6/2023 Approved STUART CHAPMAN
Insulation 6/9/2023 Approved STUART CHAPMAN
Interior/Exterior Lathing 6/9/2023 Partial Approval STUART CHAPMAN
Drywall Nailing 6/13/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 6/13/2023 Not Ready for Inspection MICHAEL LEWIS
Shower Pan 6/13/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 9/26/2025 Approved JOHN QUINTANILLA
Final 9/26/2025 Conditional Approval JOHN QUINTANILLA
Green Building Final 9/26/2025 Approved JOHN QUINTANILLA
Green Building Rough 9/26/2025 Approved JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 9/26/2025 SGSOV Approved JOHN QUINTANILLA
Smoke Detectors 9/26/2025 Approved JOHN QUINTANILLA
Final 1/5/2026 OK to Issue CofO JOHN QUINTANILLA