4038 N SAN REMO WAY 91356
Certificate Information: 4038 N SAN REMO WAY 91356
- Application / Permit
- 22014-20000-00963
- Plan Check / Job No.
- B22VN03222
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 19'-6 x 20'-3" ADDITION OF A NEW BEDROOM AND BATHROOM TO THE FIRST FLOOR.
- Permit Issued
- Issued on 4/18/2022
- Issuing Office
- Current Status
- CofO Issued on 2/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/8/2022 | JESSE ARELLANO |
| Corrections Issued | 3/8/2022 | JESSE ARELLANO |
| Applicant returned to address corrections | 3/25/2022 | JESSE ARELLANO |
| Applicant returned to address corrections | 4/12/2022 | JESSE ARELLANO |
| Issued | 4/18/2022 | APPLICANT |
| Building Plans Picked Up | 4/19/2022 | APPLICANT |
| CofO in Progress | 10/7/2022 | DAVID SANDOVAL |
| Permit Finaled | 2/18/2023 | DANIEL ORRANTE |
| CofO Issued | 2/18/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/18/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/15/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 3/15/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 3/15/2022 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 3/25/2022 | JESSE ARELLANO |
| Green Code | Cleared | 3/25/2022 | JESSE ARELLANO |
Contact Information
| Contractor | Sharp Builders & Son; Lic. No.: 1058253-B | 18320 RINALDI PLACE PORTER RANCH, CA 91356 |
| Engineer | Koma,, Shahram Javadi; Lic. No.: C69497 | 23241 VENTURA BLVD 300 WOODLAND HILLS, CA 91364 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/25/2022 | Conditional Approval | MORRIS JACKSON |
| Excavation/Setback/Form/Re-Bar | 5/25/2022 | Approved | DAVID SANDOVAL |
| Footing/Foundation/Slab | 5/25/2022 | Approved | DAVID SANDOVAL |
| Sewer | 5/25/2022 | Approved | DAVID SANDOVAL |
| Underground Mechanical | 5/25/2022 | Partial Approval | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 7/27/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Green Building Rough | 7/27/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Rough-Elec/Plmb/HVAC | 7/27/2022 | Corrections Issued | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2022 | Approved | DAVID SANDOVAL |
| Rough-Elec/Plmb/HVAC | 8/1/2022 | Corrections Issued | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 8/3/2022 | Approved | DAVID SANDOVAL |
| Green Building Rough | 8/3/2022 | Approved | DAVID SANDOVAL |
| Rough-Elec/Plmb/HVAC | 8/3/2022 | Approved | DAVID SANDOVAL |
| Insulation | 8/5/2022 | Approved | SEAN WIRCH |
| Interior/Exterior Lathing | 8/5/2022 | Approved | SEAN WIRCH |
| Drywall Nailing | 8/9/2022 | Approved | DAVID SANDOVAL |
| Interior/Exterior Lathing | 8/9/2022 | Approved | DAVID SANDOVAL |
| Final | 9/9/2022 | Corrections Issued | DAVID SANDOVAL |
| Green Building Final | 9/9/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 9/9/2022 | SGSOV Not Ready | DAVID SANDOVAL |
| Smoke Detectors | 9/9/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Final | 9/21/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Green Building Final | 9/21/2022 | Approved | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 9/21/2022 | SGSOV Not Ready | DAVID SANDOVAL |
| Smoke Detectors | 9/21/2022 | Approved | DAVID SANDOVAL |
| Final | 9/26/2022 | Corrections Issued | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 9/26/2022 | SGSOV Not Ready | DAVID SANDOVAL |
| Final | 10/6/2022 | OK to Issue CofO | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 10/6/2022 | SGSOV Approved | DAVID SANDOVAL |