4038 N SAN REMO WAY 91356

Certificate Information: 4038 N SAN REMO WAY 91356

Application / Permit
22014-20000-00963
Plan Check / Job No.
B22VN03222
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
19'-6 x 20'-3" ADDITION OF A NEW BEDROOM AND BATHROOM TO THE FIRST FLOOR.
Permit Issued
Issued on 4/18/2022
Issuing Office
Current Status
CofO Issued on 2/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/2/2022 APPLICANT
Assigned to Plan Check Engineer 3/8/2022 JESSE ARELLANO
Corrections Issued 3/8/2022 JESSE ARELLANO
Applicant returned to address corrections 3/25/2022 JESSE ARELLANO
Applicant returned to address corrections 4/12/2022 JESSE ARELLANO
Issued 4/18/2022 APPLICANT
Building Plans Picked Up 4/19/2022 APPLICANT
CofO in Progress 10/7/2022 DAVID SANDOVAL
Permit Finaled 2/18/2023 DANIEL ORRANTE
CofO Issued 2/18/2023 DANIEL ORRANTE
Permit Finaled 2/18/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/15/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 3/15/2022 CARLOS AGUILERA
Sewer availability Cleared 3/15/2022 CARLOS AGUILERA
Grading Pre-Inspection Cleared 3/25/2022 JESSE ARELLANO
Green Code Cleared 3/25/2022 JESSE ARELLANO

Contact Information

Contractor Sharp Builders & Son; Lic. No.: 1058253-B 18320 RINALDI PLACE      PORTER RANCH, CA 91356
Engineer Koma,, Shahram Javadi; Lic. No.: C69497 23241 VENTURA BLVD 300      WOODLAND HILLS, CA 91364

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/25/2022 Conditional Approval MORRIS JACKSON
Excavation/Setback/Form/Re-Bar 5/25/2022 Approved DAVID SANDOVAL
Footing/Foundation/Slab 5/25/2022 Approved DAVID SANDOVAL
Sewer 5/25/2022 Approved DAVID SANDOVAL
Underground Mechanical 5/25/2022 Partial Approval DAVID SANDOVAL
BUILDING-Rough-Frame 7/27/2022 Not Ready for Inspection DAVID SANDOVAL
Green Building Rough 7/27/2022 Not Ready for Inspection DAVID SANDOVAL
Rough-Elec/Plmb/HVAC 7/27/2022 Corrections Issued DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 8/1/2022 Approved DAVID SANDOVAL
Rough-Elec/Plmb/HVAC 8/1/2022 Corrections Issued DAVID SANDOVAL
BUILDING-Rough-Frame 8/3/2022 Approved DAVID SANDOVAL
Green Building Rough 8/3/2022 Approved DAVID SANDOVAL
Rough-Elec/Plmb/HVAC 8/3/2022 Approved DAVID SANDOVAL
Insulation 8/5/2022 Approved SEAN WIRCH
Interior/Exterior Lathing 8/5/2022 Approved SEAN WIRCH
Drywall Nailing 8/9/2022 Approved DAVID SANDOVAL
Interior/Exterior Lathing 8/9/2022 Approved DAVID SANDOVAL
Final 9/9/2022 Corrections Issued DAVID SANDOVAL
Green Building Final 9/9/2022 Not Ready for Inspection DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 9/9/2022 SGSOV Not Ready DAVID SANDOVAL
Smoke Detectors 9/9/2022 Not Ready for Inspection DAVID SANDOVAL
Final 9/21/2022 Not Ready for Inspection DAVID SANDOVAL
Green Building Final 9/21/2022 Approved DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 9/21/2022 SGSOV Not Ready DAVID SANDOVAL
Smoke Detectors 9/21/2022 Approved DAVID SANDOVAL
Final 9/26/2022 Corrections Issued DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 9/26/2022 SGSOV Not Ready DAVID SANDOVAL
Final 10/6/2022 OK to Issue CofO DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 10/6/2022 SGSOV Approved DAVID SANDOVAL