8123 N HINDS AVE 91605
Certificate Information: 8123 N HINDS AVE 91605
- Application / Permit
- 22014-20000-00961
- Plan Check / Job No.
- B22VN03221
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 33' 4" X 25' 5" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) & (d), ADD 18' 7" X 19' 2" DETACHED GARAGE, ADD 13' 11" X 14' 7" OPEN TRELLIS AND REMOVE 19' 7" X 19' 2" PORTION OF (E) GARAGE. ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 7/20/2022
- Issuing Office
- Current Status
- CofO Issued on 5/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/10/2022 | GURUNATH NESARAJAH |
| Corrections Issued | 3/13/2022 | GURUNATH NESARAJAH |
| Plan Check Approved | 6/30/2022 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 7/1/2022 | APPLICANT |
| Issued | 7/20/2022 | APPLICANT |
| CofO in Progress | 2/28/2024 | MATTHEW NELSON |
| Permit Finaled | 5/2/2024 | RUBEN SALAS |
| CofO Issued | 5/2/2024 | RUBEN SALAS |
| Permit Finaled | 5/2/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/18/2022 | CHRIS CHAHBAZ |
| Clean Up Green Up | Cleared | 3/18/2022 | MIGUEL GAMBOA |
| Eng Process Fee Ord 176,300 | Cleared | 3/21/2022 | CHRIS CHAHBAZ |
| Sewer availability | Cleared | 3/22/2022 | CHRIS CHAHBAZ |
| Construction near power lines | Cleared | 4/25/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 6/15/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 6/21/2022 | CHRIS CHAHBAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grigoryan,, Souren Krist; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/10/2023 | Partial Approval | MATTHEW NELSON |
| Pre-Inspection | 7/10/2023 | Approved | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 7/12/2023 | Approved | MATTHEW NELSON |
| Footing/Foundation/Slab | 7/14/2023 | Not Ready for Inspection | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/3/2023 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 8/3/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Deputy Wood Construction | 8/7/2023 | Conditional Approval | DAVID MATSON |
| HVAC-Rough | 8/7/2023 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Rough | 8/7/2023 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 8/18/2023 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 8/18/2023 | Approved | MATTHEW NELSON |
| Green Building Rough | 8/18/2023 | Approved | MATTHEW NELSON |
| HVAC-Rough | 8/18/2023 | Corrections Issued | MATTHEW NELSON |
| Interior/Exterior Lathing | 8/18/2023 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 8/18/2023 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 9/13/2023 | Conditional Approval | THOMAS FINNILA |
| Insulation | 9/18/2023 | Corrections Issued | DAVID ANDERSON |
| Insulation | 9/25/2023 | Approved | WILLIAM WREN |
| Drywall Nailing | 9/28/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 10/19/2023 | Approved | CHRISTOPHER ROJAS |
| Shower Pan | 10/19/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Shower Pan | 10/26/2023 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 2/15/2024 | Approved | DAVID ANDERSON |
| Final | 2/15/2024 | Corrections Issued | DAVID ANDERSON |
| Footing/Foundation/Slab | 2/15/2024 | Approved | DAVID ANDERSON |
| Green Building Final | 2/15/2024 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 2/15/2024 | SGSOV Not Ready | DAVID ANDERSON |
| Smoke Detectors | 2/15/2024 | Approved | DAVID ANDERSON |
| Final | 2/28/2024 | OK to Issue CofO | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 2/28/2024 | SGSOV Approved | MATTHEW NELSON |
| Service/Power Release | 2/28/2024 | Approved | MATTHEW NELSON |