15808 W RINALDI ST 91344

Certificate Information: 15808 W RINALDI ST 91344

Application / Permit
22014-20000-00955
Plan Check / Job No.
B22VN03199
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
Permit Issued
Issued on 7/26/2022
Issuing Office
Current Status
CofO Issued on 4/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/11/2022 APPLICANT
Assigned to Plan Check Engineer 3/17/2022 JEROME MAGAT PALMA
Corrections Issued 3/19/2022 JEROME MAGAT PALMA
Applicant returned to address corrections 7/15/2022 ALEC MOUSAKHANIAN
Plan Check Approved 7/24/2022 ALEC MOUSAKHANIAN
Issued 7/26/2022 APPLICANT
Building Plans Picked Up 8/1/2022 APPLICANT
CofO in Progress 3/29/2023 JENNIFER RABUCHIN
Permit Finaled 4/4/2023 DANIEL ORRANTE
CofO Issued 4/4/2023 DANIEL ORRANTE
Permit Finaled 4/4/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 6/8/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 6/8/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 6/8/2022 JOSE DUARTE-DIAZ
Construction near power lines Cleared 7/2/2022 WALTER RAMIREZ
Grading Pre-Inspection Cleared 7/15/2022 JEROME MAGAT PALMA

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Test 8/17/2022 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 8/17/2022 Partial Approval JENNIFER RABUCHIN
Underground Mechanical 8/17/2022 Partial Approval JENNIFER RABUCHIN
Deputy Drilled-In Anchors 9/9/2022 Partial Approval ROBERT GOLD
Footing/Foundation/Slab 9/9/2022 Approved JENNIFER RABUCHIN
PLUMBING-Rough 9/14/2022 Partial Approval JENNIFER RABUCHIN
Sewer 9/14/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 11/16/2022 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 11/16/2022 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 11/16/2022 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 11/16/2022 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 11/30/2022 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 11/30/2022 Approved JENNIFER RABUCHIN
Green Building Rough 11/30/2022 Approved JENNIFER RABUCHIN
HVAC-Rough 11/30/2022 Corrections Issued JENNIFER RABUCHIN
Insulation 11/30/2022 Partial Approval JENNIFER RABUCHIN
Interior/Exterior Lathing 11/30/2022 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 11/30/2022 Approved JENNIFER RABUCHIN
Insulation 12/7/2022 Approved JENNIFER RABUCHIN
Drywall Nailing 12/15/2022 Approved JENNIFER RABUCHIN
Shower Pan 12/22/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 1/6/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 2/9/2023 Corrections Issued JENNIFER RABUCHIN
Final 2/9/2023 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Final 2/9/2023 Approved JENNIFER RABUCHIN
HVAC-Final 2/9/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 2/9/2023 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 2/9/2023 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 2/9/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 2/15/2023 Approved JENNIFER RABUCHIN
Final 2/15/2023 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 2/15/2023 Approved JENNIFER RABUCHIN
PLUMBING-Final 2/15/2023 Approved JENNIFER RABUCHIN