4634 N LA SUBIDA PL 91356

Certificate Information: 4634 N LA SUBIDA PL 91356

Application / Permit
22014-20000-00937
Plan Check / Job No.
B22VN03149
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 19'-1" X 27'-2" FOR TWO NEW BEDROOMS AND ONE FULL BATHROOM TO (E) SFD PER ENGINEERING
Permit Issued
Issued on 3/22/2022
Issuing Office
Current Status
CofO Issued on 4/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2022 APPLICANT
Assigned to Plan Check Engineer 3/2/2022 JENNIFER LEE
Corrections Issued 3/2/2022 JENNIFER LEE
Plan Check Approved 3/21/2022 JENNIFER LEE
Issued 3/22/2022 APPLICANT
Building Plans Picked Up 3/22/2022 APPLICANT
CofO in Progress 4/27/2023 SEAN HAUPT
Permit Finaled 4/16/2024 DANIEL ORRANTE
CofO Issued 4/16/2024 DANIEL ORRANTE
Permit Finaled 4/16/2024 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/18/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/21/2022 CARLOS AGUILERA
Grading Pre-Inspection Cleared 3/21/2022 JENNIFER LEE
Sewer availability Cleared 3/21/2022 CARLOS AGUILERA

Contact Information

Contractor Structa Ii; Lic. No.: 999353-B 16030 VENTURA BLVD SUITE 430      ENCINO, CA 91436
Engineer Judd,, Shane Dennis; Lic. No.: C70991 17 E HIGH ST STE A      MOORPARK, CA 93021

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/25/2022 Approved DAVID SANDOVAL
Excavation/Setback/Form/Re-Bar 4/25/2022 Not Ready for Inspection DAVID SANDOVAL
Footing/Foundation/Slab 4/25/2022 Corrections Issued DAVID SANDOVAL
Special/Order Compliance 4/27/2022 Partial Inspection ROBERT GOLD
Excavation/Setback/Form/Re-Bar 5/2/2022 Corrections Issued DAVID SANDOVAL
Deputy Drilled-In Anchors 5/9/2022 Approved ROBERT GOLD
Excavation/Setback/Form/Re-Bar 5/11/2022 Approved ROBERT GOLD
Footing/Foundation/Slab 5/11/2022 Approved ROBERT GOLD
BUILDING-Rough-Frame 5/19/2022 Partial Approval ROBERT GOLD
Green Building Rough 5/19/2022 Not Ready for Inspection ROBERT GOLD
PLUMBING-Rough 5/19/2022 Not Ready for Inspection ROBERT GOLD
BUILDING-Rough-Frame 6/7/2022 Corrections Issued ROBERT GOLD
ELECTRICAL-Rough 6/7/2022 Approved ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 6/7/2022 Partial Approval ROBERT GOLD
Green Building Rough 6/7/2022 Not Ready for Inspection ROBERT GOLD
HVAC-Rough 6/7/2022 Corrections Issued ROBERT GOLD
PLUMBING-Rough 6/7/2022 Approved ROBERT GOLD
Rough-Elec/Plmb/HVAC 6/7/2022 Not Ready for Inspection ROBERT GOLD
Insulation 6/13/2022 Partial Approval ROBERT GOLD
Interior/Exterior Lathing 6/13/2022 Not Ready for Inspection ROBERT GOLD
Shower Pan 6/13/2022 Approved ROBERT GOLD
Special/Order Compliance 6/13/2022 Approved JEFFREY BULL
Drywall Nailing 6/17/2022 Approved ROBERT GOLD
Green Building Rough 6/17/2022 Approved ROBERT GOLD
Interior/Exterior Lathing 6/17/2022 Approved ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 6/23/2022 Approved ROBERT GOLD
BUILDING-Rough-Frame 9/6/2022 Approved SEAN WIRCH
Final 9/6/2022 Corrections Issued SEAN WIRCH
Green Building Final 9/6/2022 Approved SEAN WIRCH
SGSOV-Seismic Gas S/O Valve 9/6/2022 SGSOV Approved SEAN WIRCH
Smoke Detectors 9/6/2022 Approved SEAN WIRCH
Final 4/26/2023 OK to Issue CofO SEAN HAUPT