10842 W CROCKETT ST 91352
Certificate Information: 10842 W CROCKETT ST 91352
- Application / Permit
- 22014-20000-00934
- Plan Check / Job No.
- B22VN03132
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 37'-11" x 29'-3"IRREGULAR SHAPED ADDITION TO THE (E) SINGLE FAMILY DWELLING AND REMODEL TO CONVERT (E) ATTACHED GARAGE TO BEDROOM. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/1/2022
- Issuing Office
- Current Status
- CofO Issued on 7/26/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/30/2022 | LUIS RINCON |
| Corrections Issued | 4/2/2022 | LUIS RINCON |
| Building Plans Picked Up | 4/7/2022 | APPLICANT |
| Plan Check Approved | 9/1/2022 | OMAR GARNICA |
| Issued | 9/1/2022 | APPLICANT |
| CofO in Progress | 6/10/2024 | DAVID ANDERSON |
| Permit Finaled | 7/26/2024 | RUBEN SALAS |
| CofO Issued | 7/26/2024 | RUBEN SALAS |
| Permit Finaled | 7/26/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/11/2022 | LEE GUILBEAUX |
| Sewer availability | Cleared | 4/11/2022 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 8/18/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 8/18/2022 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/16/2023 | Partial Approval | MICHEL ABAJAN |
| Deputy Drilled-In Anchors | 10/23/2023 | Conditional Approval | RUBEN SALAS |
| Footing/Foundation/Slab | 10/23/2023 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2023 | Partial Approval | DAVID ANDERSON |
| Underground Mechanical | 11/22/2023 | Partial Approval | DAVID ANDERSON |
| BUILDING-Rough-Frame | 12/6/2023 | Corrections Issued | DAVID ANDERSON |
| ELECTRICAL-Rough | 12/6/2023 | Approved | DAVID ANDERSON |
| HVAC-Rough | 12/6/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 12/6/2023 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 12/6/2023 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 12/11/2023 | Approved | DAVID ANDERSON |
| Green Building Rough | 12/11/2023 | Approved | DAVID ANDERSON |
| MERV13>=Rough | 12/11/2023 | Approved | DAVID ANDERSON |
| Insulation | 12/14/2023 | Approved | DAVID ANDERSON |
| Drywall Nailing | 12/18/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 12/26/2023 | Approved | DAVID ANDERSON |
| Final | 6/7/2024 | OK to Issue CofO | DAVID ANDERSON |
| Green Building Final | 6/7/2024 | Approved | DAVID ANDERSON |
| MERV13>=Final | 6/7/2024 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 6/7/2024 | SGSOV Approved | DAVID ANDERSON |
| Smoke Detectors | 6/7/2024 | Approved | DAVID ANDERSON |