1041 N AVENUE 63 90042

Certificate Information: 1041 N AVENUE 63 90042

Application / Permit
22014-20000-00931
Plan Check / Job No.
B22VN03119
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION ( 20' X 15' ) TO EX. SFD FOR NEW BATHROOM/ STUDY. ADDITION (13'-1" X 6'-5") FOR LIVING ROOM CONVERSION. REMODEL KITCHEN, LIVING ROOM AND DEN. RE-FRAME EX. DETACHED GARAGE AND CONNECT TO SFD. WORK PER DESIGN.
Permit Issued
Issued on 9/1/2022
Issuing Office
Valley
Current Status
CofO Issued on 8/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/7/2022 APPLICANT
Assigned to Plan Check Engineer 3/11/2022 ROSENDO MEDINA
Corrections Issued 3/12/2022 ROSENDO MEDINA
Applicant returned to address corrections 5/18/2022 ROSENDO MEDINA
Plan Check Approved 6/8/2022 ROSENDO MEDINA
Building Plans Picked Up 6/14/2022 APPLICANT
Issued 9/1/2022 APPLICANT
CofO in Progress 8/4/2023 AMY COLIN
CofO Issued 8/7/2023 DEROLD HAUFF
Permit Finaled 8/7/2023 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/25/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 4/8/2022 AMAAN MALIK
Grading Pre-Inspection Cleared 4/11/2022 KIRK LINKLATER
Hydrant and Access approval Cleared 4/29/2022 MICHAEL GILLISSIE

Contact Information

Architect Grist,, John Kenneth; Lic. No.: C4295 470 STANFORD DRIVE      CLAREMONT, CA 91711
Contractor K&K Construction; Lic. No.: 1079161-B 39312 DUNBAR STREET      PALMDALE, CA 93551

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/2/2022 Conditional Approval AMY COLIN
Footing/Foundation/Slab 9/8/2022 Partial Approval AMY COLIN
PLUMBING-Rough 9/8/2022 Partial Approval AMY COLIN
Footing/Foundation/Slab 9/13/2022 Corrections Issued AMY COLIN
Footing/Foundation/Slab 9/20/2022 Approved AMY COLIN
ELECTRICAL-Rough 11/3/2022 Not Ready for Inspection AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 11/3/2022 Corrections Issued AMY COLIN
HVAC-Rough 11/3/2022 Not Ready for Inspection AMY COLIN
PLUMBING-Rough 11/3/2022 Not Ready for Inspection AMY COLIN
Sewer 11/3/2022 Not Ready for Inspection AMY COLIN
Wood Frame 11/3/2022 Not Ready for Inspection AMY COLIN
Deputy Wood Construction 11/4/2022 Conditional Approval AMY COLIN
BUILDING-Rough-Frame 11/22/2022 Approved AMY COLIN
ELECTRICAL-Rough 11/22/2022 Approved AMY COLIN
Green Building Rough 11/22/2022 Approved AMY COLIN
HVAC-Rough 11/22/2022 Approved AMY COLIN
PLUMBING-Rough 11/22/2022 Approved AMY COLIN
Insulation 12/1/2022 Approved AMY COLIN
Drywall Nailing 12/12/2022 Approved OSVALDO PARAMO
Shower Pan 12/27/2022 Approved AMY COLIN
Final 6/15/2023 Corrections Issued AMY COLIN
Green Building Final 6/15/2023 Approved AMY COLIN
SGSOV-Seismic Gas S/O Valve 6/15/2023 SGSOV Approved AMY COLIN
Smoke Detectors 6/15/2023 Corrections Issued AMY COLIN
Final 6/29/2023 Partial Inspection AMY COLIN
Smoke Detectors 6/29/2023 Approved AMY COLIN
Final 8/4/2023 OK to Issue CofO AMY COLIN