133 N LA JOLLA AVE 90048
Certificate Information: 133 N LA JOLLA AVE 90048
- Application / Permit
- 22014-20000-00924
- Plan Check / Job No.
- B22VN03108
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (2) 5' X 2'-6" & 10' X 14' ADDITION AND INTERIOR REMODEL. ENCLOSE 15' X 19'-7 PATIO COVER AND CONVERT TO HABITABLE SPACE. (N) 7'-8" X 17'-2" PATIO COVER.
- Permit Issued
- Issued on 4/14/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2022 | JEFFREY TANGONAN |
| Corrections Issued | 3/5/2022 | JEFFREY TANGONAN |
| Building Plans Picked Up | 3/14/2022 | APPLICANT |
| Plan Check Approved | 9/20/2022 | SERGIO MUNIZ |
| Issued | 4/14/2023 | APPLICANT |
| CofO in Progress | 1/17/2025 | MEL KHACHATOURIAN |
| Permit Finaled | 1/27/2025 | RICHARD STEINBACH |
| CofO Issued | 1/27/2025 | RICHARD STEINBACH |
| Permit Finaled | 1/27/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/3/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 6/7/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 6/8/2022 | STEVE MELGAR |
Contact Information
| Architect | Santiago-Dieppa,, Rafael Angel; Lic. No.: C10361 | 17116 RAYMER STREET NORTHRIDGE, CA 91325 |
| Contractor | Barhoum Construction; Lic. No.: 677879-B | 1109 N MICHIGAN AVENUE PASADENA, CA 91104 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/13/2023 | Partial Approval | JEREMY TODD |
| METHANE-Barrier | 6/13/2023 | Approved | JEREMY TODD |
| METHANE-Subgrade | 6/13/2023 | Approved | JEREMY TODD |
| BUILDING-Rough-Frame | 8/29/2023 | Partial Approval | MEL KHACHATOURIAN |
| Green Building Rough | 8/29/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| METHANE-Rough | 8/29/2023 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Rough | 8/29/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Insulation | 9/1/2023 | Partial Approval | MEL KHACHATOURIAN |
| PLUMBING-Rough | 9/1/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 10/25/2023 | Partial Approval | CARLOS MATAMOROS |
| Green Building Rough | 10/25/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 11/30/2023 | Corrections Issued | MEL KHACHATOURIAN |
| Green Building Rough | 11/30/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 1/10/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 1/19/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 1/19/2024 | Partial Approval | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 1/19/2024 | Approved | MEL KHACHATOURIAN |
| Green Building Rough | 1/19/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| HVAC-Rough | 1/19/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 1/19/2024 | Approved | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 1/30/2024 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 1/30/2024 | Partial Approval | MEL KHACHATOURIAN |
| Green Building Rough | 1/30/2024 | Approved | MEL KHACHATOURIAN |
| HVAC-Rough | 1/30/2024 | Approved | MEL KHACHATOURIAN |
| Insulation | 2/14/2024 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 2/14/2024 | Partial Approval | MEL KHACHATOURIAN |
| Drywall Nailing | 2/22/2024 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Rough | 2/22/2024 | Approved | MEL KHACHATOURIAN |
| Shower Pan | 2/22/2024 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 3/19/2024 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Final | 11/21/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Final | 11/21/2024 | Corrections Issued | MEL KHACHATOURIAN |
| Green Building Final | 11/21/2024 | Corrections Issued | MEL KHACHATOURIAN |
| HVAC-Final | 11/21/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Final | 11/21/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 11/21/2024 | SGSOV Not Ready | MEL KHACHATOURIAN |
| Smoke Detectors | 11/21/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Gas Test | 12/3/2024 | Approved | ARAM AVEDISIAN |
| Final | 12/26/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Green Building Final | 12/26/2024 | Approved | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 12/26/2024 | SGSOV Not Ready | MEL KHACHATOURIAN |
| Smoke Detectors | 12/26/2024 | Approved | MEL KHACHATOURIAN |
| Final | 1/9/2025 | Corrections Issued | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 1/9/2025 | SGSOV Not Ready | KEVIN SARGSYAN |
| Final | 1/14/2025 | OK to Issue CofO | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 1/14/2025 | SGSOV Approved | MEL KHACHATOURIAN |
| Service/Power Release | 1/18/2025 | Approved | MEL KHACHATOURIAN |