12019 W ARCHWOOD ST 91606
Certificate Information: 12019 W ARCHWOOD ST 91606
- Application / Permit
- 22014-20000-00919
- Plan Check / Job No.
- B22VN03101
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DET. GARAGE WITH IRR SHAPED ADDITION TO NEW 42'-1" x 29'-10" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 4/26/2022
- Issuing Office
- Current Status
- CofO Issued on 3/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2022 | SEAN SHAHMIRI |
| Corrections Issued | 3/21/2022 | SEAN SHAHMIRI |
| Quality Review Completed | 3/21/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 3/22/2022 | APPLICANT |
| Applicant returned to address corrections | 4/26/2022 | SEAN SHAHMIRI |
| Plan Check Approved | 4/26/2022 | SEAN SHAHMIRI |
| Issued | 4/26/2022 | APPLICANT |
| CofO in Progress | 2/22/2023 | JOHN HAYES |
| Permit Finaled | 3/13/2023 | DANIEL ORRANTE |
| CofO Issued | 3/13/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/13/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 3/30/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 4/1/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 4/1/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 4/20/2022 | KHAING AYE |
| Roof/Waste drainage to street | Cleared | 4/20/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 11 CEDARWOOD DR POMONA, CA 91766 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/16/2022 | No Access for Inspection | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 6/27/2022 | Partial Approval | JOHN HAYES |
| PLUMBING-Rough | 6/27/2022 | Partial Approval | JOHN HAYES |
| Footing/Foundation/Slab | 6/28/2022 | Not Ready for Inspection | JOHN HAYES |
| Underground Mechanical | 6/28/2022 | Not Ready for Inspection | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 7/6/2022 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2022 | Corrections Issued | WILLIAM WREN |
| BUILDING-Rough-Frame | 8/12/2022 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 8/12/2022 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 8/12/2022 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 8/12/2022 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 8/12/2022 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 8/22/2022 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 8/22/2022 | Not Ready for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2022 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 8/22/2022 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 8/22/2022 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 8/22/2022 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 8/30/2022 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 8/30/2022 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 8/30/2022 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 8/30/2022 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 8/30/2022 | Approved | JOHN HAYES |
| Wood Frame | 8/30/2022 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 9/20/2022 | Approved | JOHN HAYES |
| Green Building Rough | 9/20/2022 | Approved | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 9/20/2022 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 10/4/2022 | Partial Approval | JOHN HAYES |
| Insulation | 10/13/2022 | Corrections Issued | CALEB MEISTER |
| Shower Pan | 10/13/2022 | Approved | CALEB MEISTER |
| HVAC-Rough | 10/20/2022 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 10/20/2022 | Approved | MORRIS JACKSON |
| Insulation | 10/26/2022 | Approved | JOHN HAYES |
| Sewer | 10/26/2022 | Not Ready for Inspection | JOHN HAYES |
| Underground Mechanical | 10/26/2022 | Not Ready for Inspection | JOHN HAYES |
| Drywall Nailing | 11/3/2022 | Approved | JOHN HAYES |
| Gas Test | 11/3/2022 | Approved | JOHN HAYES |
| Sewer | 11/3/2022 | Approved | JOHN HAYES |
| Underground Mechanical | 11/3/2022 | Approved | JOHN HAYES |
| Final | 2/14/2023 | Corrections Issued | DAVID MATSON |
| Footing/Foundation/Slab | 2/14/2023 | Approved | DAVID MATSON |
| Green Building Final | 2/14/2023 | Approved | DAVID MATSON |
| SGSOV-Seismic Gas S/O Valve | 2/14/2023 | SGSOV Not Ready | DAVID MATSON |
| Smoke Detectors | 2/14/2023 | Approved | DAVID MATSON |
| Final | 2/21/2023 | OK to Issue CofO | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 2/21/2023 | SGSOV Approved | JOHN HAYES |