13775 W LOUVRE ST 91331

Certificate Information: 13775 W LOUVRE ST 91331

Application / Permit
22014-20000-00917
Plan Check / Job No.
B22VN03098
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
31' X 22' ADDITION TO THE REAR OF EXISTING SINGLE FAMILY DWELLING; EQUIPPED WITH NPFA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 6/16/2022
Issuing Office
Current Status
CofO Issued on 11/12/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2022 APPLICANT
Assigned to Plan Check Engineer 3/10/2022 SELLA BENYAMIN
Corrections Issued 3/15/2022 SELLA BENYAMIN
Quality Review Completed 3/17/2022 STEVEN KIM
Building Plans Picked Up 3/17/2022 APPLICANT
Plan Check Approved 5/19/2022 SELLA BENYAMIN
Issued 6/16/2022 APPLICANT
CofO in Progress 11/3/2022 MICHEL ABAJAN
CofO Issued 11/12/2022 MICHAEL SMITH
Permit Finaled 11/12/2022 MICHAEL SMITH

Permit Application Clearance Information

Sewer availability Cleared 3/25/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 3/30/2022 DAGOVERTO GUERRERO
Low Impact Development Cleared 4/28/2022 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 4/29/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/7/2022 Approved MICHEL ABAJAN
Footing/Foundation/Slab 7/7/2022 Approved MICHEL ABAJAN
METHANE-Barrier 7/7/2022 Approved MICHEL ABAJAN
METHANE-Subgrade 7/7/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 8/5/2022 Partial Approval MICHEL ABAJAN
METHANE-Rough 8/5/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 8/5/2022 Partial Approval MICHEL ABAJAN
Underground Mechanical 8/5/2022 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 8/15/2022 Corrections Issued MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 8/17/2022 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 9/6/2022 Not Ready for Inspection MICHEL ABAJAN
ELECTRICAL-Rough 9/6/2022 Approved MICHEL ABAJAN
Green Building Rough 9/6/2022 Not Ready for Inspection MICHEL ABAJAN
HVAC-Rough 9/6/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 9/6/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 9/13/2022 Approved MICHEL ABAJAN
Green Building Rough 9/13/2022 Approved MICHEL ABAJAN
Insulation 9/15/2022 Approved MICHEL ABAJAN
Interior/Exterior Lathing 9/15/2022 Approved MICHEL ABAJAN
Drywall Nailing 9/20/2022 Approved MICHEL ABAJAN
ELECTRICAL-Final 11/3/2022 Approved MICHEL ABAJAN
Final 11/3/2022 OK to Issue CofO MICHEL ABAJAN
Green Building Final 11/3/2022 Approved MICHEL ABAJAN
HVAC-Final 11/3/2022 Approved MICHEL ABAJAN
PLUMBING-Final 11/3/2022 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 11/3/2022 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 11/3/2022 Approved MICHEL ABAJAN