10018-10020 N CABANAS AVE 91042

Certificate Information: 10018-10020 N CABANAS AVE 91042

Application / Permit
22014-20000-00915
Plan Check / Job No.
B22VN03097
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL AND ADDITION TO DWELLING, INCLUDING CONVERSION OF GARAGE TO JADU
Permit Issued
Issued on 3/7/2023
Issuing Office
Valley
Current Status
CofO Issued on 2/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2022 APPLICANT
Assigned to Plan Check Engineer 3/31/2022 HERNAN ARREOLA
Corrections Issued 4/6/2022 HERNAN ARREOLA
Quality Review Completed 4/12/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 2/22/2023 HERNAN ARREOLA
Plan Check Approved 3/6/2023 HERNAN ARREOLA
Issued 3/7/2023 APPLICANT
CofO in Progress 2/10/2025 WILLIAM WREN
Permit Finaled 2/18/2025 RUBEN SALAS
CofO Issued 2/18/2025 RUBEN SALAS
Permit Finaled 2/18/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/15/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 4/18/2022 CARLOS AGUILERA
Sewer availability Cleared 4/18/2022 CARLOS AGUILERA
Grading Pre-Inspection Cleared 4/22/2022 VASIL MIHALEV
Miscellaneous Cleared 5/11/2022 DANIEL SCHNEIDEREIT
Construction within easement Cleared 6/4/2022 RIDWAN HARDY
Hydrant and Access approval Cleared 8/16/2022 GILBERT URREA
Low Impact Development Cleared 10/2/2022 TA ANH
Roof/Waste drainage to street Cleared 10/5/2022 MEGAN GODINEZ
GPI Written Notices Cleared 2/22/2023 HERNAN ARREOLA
Miscellaneous Cleared 2/27/2023 HERNAN ARREOLA

Contact Information

Contractor Owner-Builder       ,
Engineer Moradian,, Helbert; Lic. No.: C76618 6854 FOOTHILL BLVD      TUJUNGA, CA 91042

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/12/2023 Conditional Approval MICHAEL SMITH
Footing/Foundation/Slab 5/15/2023 Corrections Issued WILLIAM WREN
Footing/Foundation/Slab 5/31/2023 Corrections Issued WILLIAM WREN
Green Building Rough 5/31/2023 Not Ready for Inspection WILLIAM WREN
PLUMBING-Rough 5/31/2023 Corrections Issued WILLIAM WREN
Excavation/Setback/Form/Re-Bar 6/5/2023 Approved WILLIAM WREN
PLUMBING-Rough 6/5/2023 Partial Approval WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 8/23/2023 Partial Approval WILLIAM WREN
Deputy Wood Construction 9/1/2023 Conditional Approval DAVID MATSON
HVAC-Rough 9/14/2023 Corrections Issued WILLIAM WREN
PLUMBING-Rough 9/14/2023 Approved WILLIAM WREN
BUILDING-Rough-Frame 10/2/2023 Corrections Issued WILLIAM WREN
Green Building Rough 10/2/2023 Not Ready for Inspection WILLIAM WREN
BUILDING-Rough-Frame 10/17/2023 Not Ready for Inspection WILLIAM WREN
ELECTRICAL-Rough 10/17/2023 Not Ready for Inspection WILLIAM WREN
Green Building Rough 10/17/2023 Not Ready for Inspection WILLIAM WREN
Rough-Elec/Plmb/HVAC 10/17/2023 Not Ready for Inspection WILLIAM WREN
BUILDING-Rough-Frame 10/24/2023 Corrections Issued WILLIAM WREN
ELECTRICAL-Rough 10/24/2023 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 10/24/2023 Approved WILLIAM WREN
Green Building Rough 10/24/2023 Approved WILLIAM WREN
Rough-Elec/Plmb/HVAC 10/24/2023 Approved WILLIAM WREN
BUILDING-Rough-Frame 10/26/2023 Approved WILLIAM WREN
Insulation 10/26/2023 Partial Approval WILLIAM WREN
Insulation 11/1/2023 Approved WILLIAM WREN
Drywall Nailing 11/8/2023 Approved WILLIAM WREN
Interior/Exterior Lathing 11/8/2023 Approved WILLIAM WREN
Interior/Exterior Lathing 11/15/2023 Approved MICHEL ABAJAN
Shower Pan 3/14/2024 Approved WILLIAM WREN
ELECTRICAL-Rough 5/22/2024 Not Ready for Inspection WILLIAM WREN
Service/Power Release 8/21/2024 Not Ready for Inspection WILLIAM WREN
Smoke Detectors 8/21/2024 Not Ready for Inspection WILLIAM WREN
Final 11/26/2024 Not Ready for Inspection WILLIAM WREN
Footing/Foundation/Slab 11/26/2024 Approved WILLIAM WREN
Green Building Final 11/26/2024 Not Ready for Inspection WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 11/26/2024 SGSOV Approved WILLIAM WREN
Service/Power Release 11/26/2024 Approved WILLIAM WREN
Smoke Detectors 11/26/2024 Not Ready for Inspection WILLIAM WREN
Final 1/24/2025 Corrections Issued WILLIAM WREN
Green Building Final 1/24/2025 Not Ready for Inspection WILLIAM WREN
Smoke Detectors 1/24/2025 Corrections Issued WILLIAM WREN
Final 1/30/2025 OK to Issue CofO WILLIAM WREN
Green Building Final 1/30/2025 Approved WILLIAM WREN
Smoke Detectors 1/30/2025 Approved WILLIAM WREN