10030-10032 N LEMONA AVE 91345
Certificate Information: 10030-10032 N LEMONA AVE 91345
- Application / Permit
- 22014-20000-00906
- Plan Check / Job No.
- B22VN03087
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN CONVERT EXISTING ATTACHED 2-CAR GARAGE INTO AN ACCESSORY DWELLING UNIT PER ORDINANCE.
- Permit Issued
- Issued on 3/14/2022
- Issuing Office
- Current Status
- CofO Issued on 6/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/1/2022 | MICHAEL LOPEZ |
| Corrections Issued | 3/1/2022 | MICHAEL LOPEZ |
| Plan Check Approved | 3/11/2022 | MICHAEL LOPEZ |
| Issued | 3/14/2022 | APPLICANT |
| CofO in Progress | 5/20/2025 | JENNIFER RABUCHIN |
| No Progress | 5/21/2025 | RAUL OLAGI |
| CofO in Progress | 5/21/2025 | RAUL OLAGI |
| Permit Finaled | 6/6/2025 | RUBEN SALAS |
| CofO Issued | 6/6/2025 | RUBEN SALAS |
| Permit Finaled | 6/6/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/4/2022 | CINDY QI |
| Sewer availability | Cleared | 3/4/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 3/7/2022 | CINDY QI |
Contact Information
| Contractor | Construction For Less; Lic. No.: 965043-B | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/21/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 11/21/2022 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 12/23/2022 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 12/23/2022 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 12/23/2022 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 1/6/2023 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 1/6/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 1/6/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 1/6/2023 | Approved | JENNIFER RABUCHIN |
| Insulation | 1/20/2023 | Approved | JOHN COLEMAN |
| BUILDING-Rough-Frame | 1/24/2023 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 1/27/2023 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 2/9/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 5/16/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 5/16/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 5/16/2023 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 5/16/2023 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 5/16/2023 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 5/16/2023 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 5/16/2023 | Approved | JENNIFER RABUCHIN |
| Final | 6/8/2023 | Corrections Issued | ROBERT GOLD |
| Green Building Final | 6/8/2023 | Not Ready for Inspection | ROBERT GOLD |
| Final | 7/13/2023 | Partial Inspection | ROBERT GOLD |
| Green Building Final | 7/13/2023 | Approved | ROBERT GOLD |
| Final | 5/6/2025 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 5/19/2025 | Approved | JENNIFER RABUCHIN |
| Final | 5/19/2025 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 5/19/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 5/19/2025 | Approved | JENNIFER RABUCHIN |
| Special/Order Compliance | 5/22/2025 | Corrections Issued | JENNIFER RABUCHIN |