913 S MULLEN AVE 90019

Certificate Information: 913 S MULLEN AVE 90019

Application / Permit
22014-20000-00902
Plan Check / Job No.
B22VN03055
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 11'-9" x 8'-0" ADDITION TO THE (E) SINGLE FAMILY DWELLING FOR A BATHROOM AND INTERIOR REMODEL.
Permit Issued
Issued on 7/1/2022
Issuing Office
Current Status
CofO Issued on 12/27/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/28/2022 APPLICANT
Assigned to Plan Check Engineer 3/4/2022 SARKIS HARABEDIAN
Corrections Issued 3/5/2022 SARKIS HARABEDIAN
Applicant returned to address corrections 4/14/2022 SARKIS HARABEDIAN
Plan Check Approved 6/14/2022 SARKIS HARABEDIAN
Building Plans Picked Up 6/15/2022 APPLICANT
Issued 7/1/2022 APPLICANT
CofO in Progress 11/17/2022 JEFFREY MEAD
Permit Finaled 12/27/2022 DEROLD HAUFF
CofO Issued 12/27/2022 DEROLD HAUFF
Permit Finaled 12/27/2022 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/22/2022 JEANIE LAM
Roof/Waste drainage to street Cleared 3/22/2022 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Nirattisai,, Preston; Lic. No.: C85115 28411 ASCENT WAY      SANTA CLARITA, CA 91350

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/6/2022 Corrections Issued JEFFREY MEAD
Wood Frame 7/7/2022 Corrections Issued JEFFREY MEAD
BUILDING-Rough-Frame 7/8/2022 Partial Approval JEFFREY MEAD
ELECTRICAL-Rough 7/8/2022 Partial Approval JEFFREY MEAD
Footing/Foundation/Slab 7/8/2022 Approved JEFFREY MEAD
Green Building Rough 7/8/2022 Partial Approval JEFFREY MEAD
HVAC-Rough 7/8/2022 Partial Approval JEFFREY MEAD
METHANE-Barrier 7/8/2022 Approved JEFFREY MEAD
METHANE-Rough 7/8/2022 Approved JEFFREY MEAD
METHANE-Subgrade 7/8/2022 Approved JEFFREY MEAD
PLUMBING-Rough 7/8/2022 Partial Approval JEFFREY MEAD
Insulation 7/12/2022 Partial Approval JEFFREY MEAD
Drywall Nailing 7/15/2022 Partial Approval JEFFREY MEAD
ELECTRICAL-Rough 7/15/2022 Approved JEFFREY MEAD
HVAC-Rough 7/15/2022 Partial Approval JEFFREY MEAD
PLUMBING-Rough 7/15/2022 Partial Approval JEFFREY MEAD
Wood Frame 7/15/2022 Partial Approval JEFFREY MEAD
Insulation 7/19/2022 Approved JEFFREY MEAD
Drywall Nailing 7/22/2022 Approved JEFFREY MEAD
Interior/Exterior Lathing 7/22/2022 Approved JEFFREY MEAD
Shower Pan 7/22/2022 Approved JEFFREY MEAD
BUILDING-Rough-Frame 10/6/2022 Approved JEFFREY MEAD
ELECTRICAL-Final 10/6/2022 Approved JEFFREY MEAD
Final 10/6/2022 Not Ready for Inspection JEFFREY MEAD
Green Building Final 10/6/2022 Approved JEFFREY MEAD
Green Building Rough 10/6/2022 Approved JEFFREY MEAD
HVAC-Final 10/6/2022 Partial Approval JEFFREY MEAD
PLUMBING-Final 10/6/2022 Approved JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 10/6/2022 SGSOV Not Ready JEFFREY MEAD
Smoke Detectors 10/6/2022 Approved JEFFREY MEAD
Final 10/24/2022 Conditional Approval JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 10/24/2022 SGSOV Approved JEFFREY MEAD
Final 11/17/2022 OK to Issue CofO JEFFREY MEAD