913 S MULLEN AVE 90019
Certificate Information: 913 S MULLEN AVE 90019
- Application / Permit
- 22014-20000-00902
- Plan Check / Job No.
- B22VN03055
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 11'-9" x 8'-0" ADDITION TO THE (E) SINGLE FAMILY DWELLING FOR A BATHROOM AND INTERIOR REMODEL.
- Permit Issued
- Issued on 7/1/2022
- Issuing Office
- Current Status
- CofO Issued on 12/27/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2022 | SARKIS HARABEDIAN |
| Corrections Issued | 3/5/2022 | SARKIS HARABEDIAN |
| Applicant returned to address corrections | 4/14/2022 | SARKIS HARABEDIAN |
| Plan Check Approved | 6/14/2022 | SARKIS HARABEDIAN |
| Building Plans Picked Up | 6/15/2022 | APPLICANT |
| Issued | 7/1/2022 | APPLICANT |
| CofO in Progress | 11/17/2022 | JEFFREY MEAD |
| Permit Finaled | 12/27/2022 | DEROLD HAUFF |
| CofO Issued | 12/27/2022 | DEROLD HAUFF |
| Permit Finaled | 12/27/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/22/2022 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 3/22/2022 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nirattisai,, Preston; Lic. No.: C85115 | 28411 ASCENT WAY SANTA CLARITA, CA 91350 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/6/2022 | Corrections Issued | JEFFREY MEAD |
| Wood Frame | 7/7/2022 | Corrections Issued | JEFFREY MEAD |
| BUILDING-Rough-Frame | 7/8/2022 | Partial Approval | JEFFREY MEAD |
| ELECTRICAL-Rough | 7/8/2022 | Partial Approval | JEFFREY MEAD |
| Footing/Foundation/Slab | 7/8/2022 | Approved | JEFFREY MEAD |
| Green Building Rough | 7/8/2022 | Partial Approval | JEFFREY MEAD |
| HVAC-Rough | 7/8/2022 | Partial Approval | JEFFREY MEAD |
| METHANE-Barrier | 7/8/2022 | Approved | JEFFREY MEAD |
| METHANE-Rough | 7/8/2022 | Approved | JEFFREY MEAD |
| METHANE-Subgrade | 7/8/2022 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 7/8/2022 | Partial Approval | JEFFREY MEAD |
| Insulation | 7/12/2022 | Partial Approval | JEFFREY MEAD |
| Drywall Nailing | 7/15/2022 | Partial Approval | JEFFREY MEAD |
| ELECTRICAL-Rough | 7/15/2022 | Approved | JEFFREY MEAD |
| HVAC-Rough | 7/15/2022 | Partial Approval | JEFFREY MEAD |
| PLUMBING-Rough | 7/15/2022 | Partial Approval | JEFFREY MEAD |
| Wood Frame | 7/15/2022 | Partial Approval | JEFFREY MEAD |
| Insulation | 7/19/2022 | Approved | JEFFREY MEAD |
| Drywall Nailing | 7/22/2022 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 7/22/2022 | Approved | JEFFREY MEAD |
| Shower Pan | 7/22/2022 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 10/6/2022 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 10/6/2022 | Approved | JEFFREY MEAD |
| Final | 10/6/2022 | Not Ready for Inspection | JEFFREY MEAD |
| Green Building Final | 10/6/2022 | Approved | JEFFREY MEAD |
| Green Building Rough | 10/6/2022 | Approved | JEFFREY MEAD |
| HVAC-Final | 10/6/2022 | Partial Approval | JEFFREY MEAD |
| PLUMBING-Final | 10/6/2022 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 10/6/2022 | SGSOV Not Ready | JEFFREY MEAD |
| Smoke Detectors | 10/6/2022 | Approved | JEFFREY MEAD |
| Final | 10/24/2022 | Conditional Approval | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 10/24/2022 | SGSOV Approved | JEFFREY MEAD |
| Final | 11/17/2022 | OK to Issue CofO | JEFFREY MEAD |