12811-12813 N COMETA AVE 91340
Certificate Information: 12811-12813 N COMETA AVE 91340
- Application / Permit
- 22014-20000-00900
- Plan Check / Job No.
- B22VN03051
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 24' X 21'-6" SECOND FLOOR ADDITION TO AND CONVERT THE (E) ATTACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e) IN SFD.
- Permit Issued
- Issued on 6/6/2022
- Issuing Office
- Current Status
- CofO Issued on 9/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2022 | SERGIO MUNIZ |
| Corrections Issued | 3/6/2022 | SERGIO MUNIZ |
| Applicant returned to address corrections | 5/21/2022 | SERGIO MUNIZ |
| Plan Check Approved | 5/24/2022 | SERGIO MUNIZ |
| Building Plans Picked Up | 5/25/2022 | APPLICANT |
| Issued | 6/6/2022 | APPLICANT |
| CofO in Progress | 9/15/2022 | ARAM AVEDISIAN |
| CofO Issued | 9/22/2022 | MICHAEL SMITH |
| Permit Finaled | 9/22/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 3/18/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/18/2022 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 3/18/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 3/18/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Vicsinc.Com; Lic. No.: 1002544-B | P O BOX 950931 MISSION HILLS, CA 91395 |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/7/2022 | Conditional Approval | JOHN HAYES |
| Footing/Foundation/Slab | 6/9/2022 | Conditional Approval | MATT KELLERMAN |
| Underground Mechanical | 6/9/2022 | Partial Inspection | MATT KELLERMAN |
| Wood Frame | 6/15/2022 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 6/21/2022 | Corrections Issued | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 6/27/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 6/27/2022 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 6/27/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 6/27/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 6/30/2022 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 6/30/2022 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 7/7/2022 | Approved | ARAM AVEDISIAN |
| Final | 8/30/2022 | Corrections Issued | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 9/15/2022 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 9/15/2022 | Approved | ARAM AVEDISIAN |
| Final | 9/15/2022 | OK to Issue CofO | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 9/15/2022 | Approved | ARAM AVEDISIAN |
| Green Building Final | 9/15/2022 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 9/15/2022 | Approved | ARAM AVEDISIAN |
| HVAC-Final | 9/15/2022 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 9/15/2022 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 9/15/2022 | SGSOV Approved | ARAM AVEDISIAN |
| Service/Power Release | 9/15/2022 | Approved | ARAM AVEDISIAN |
| Smoke Detectors | 9/15/2022 | Approved | ARAM AVEDISIAN |