8041 S KENYON AVE 90045

Certificate Information: 8041 S KENYON AVE 90045

Application / Permit
22014-20000-00887
Plan Check / Job No.
B22VN02997
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 11'-0" x 11'-3" ADDITION TO THE (E) SINGLE FAMILY DWELLING FOR A NEW BATHROOM AND INTERIOR REMODEL.
Permit Issued
Issued on 5/6/2022
Issuing Office
Current Status
CofO Issued on 11/15/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/28/2022 APPLICANT
Assigned to Plan Check Engineer 3/4/2022 SARKIS HARABEDIAN
Corrections Issued 3/5/2022 SARKIS HARABEDIAN
Applicant returned to address corrections 4/16/2022 SARKIS HARABEDIAN
Plan Check Approved 5/6/2022 SARKIS HARABEDIAN
Issued 5/6/2022 APPLICANT
Building Plans Picked Up 5/9/2022 APPLICANT
CofO in Progress 11/8/2022 BOBBY KEY
Permit Finaled 11/15/2022 DANIEL ORRANTE
CofO Issued 11/15/2022 DANIEL ORRANTE
Permit Finaled 11/15/2022 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/14/2022 JENSON LEE
Sewer availability Cleared 3/14/2022 JENSON LEE
Specific Plan Cleared 3/14/2022 EDUARDO HERMOSO
Eng Process Fee Ord 176,300 Cleared 3/17/2022 JENSON LEE

Contact Information

Contractor Srt Building And Renovation Inc; Lic. No.: 1018885-B 10773 SAN JOSE AVENUE      LYNWOOD, CA 90262
Engineer Erdelyi,, Peter Tibor; Lic. No.: C26962 2999 OVERLAND AVE STE 103      LOS ANGELES, CA 90064

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/1/2022 Conditional Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 6/8/2022 Approved BOBBY KEY
Footing/Foundation/Slab 6/8/2022 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 6/22/2022 Corrections Issued STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 6/24/2022 Partial Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 7/15/2022 Partial Approval JESUS RODRIGUEZ
BUILDING-Rough-Frame 8/9/2022 Conditional Approval BOBBY KEY
ELECTRICAL-Rough 8/9/2022 Approved BOBBY KEY
Green Building Rough 8/9/2022 Not Ready for Inspection BOBBY KEY
HVAC-Rough 8/9/2022 Approved BOBBY KEY
PLUMBING-Rough 8/9/2022 Approved BOBBY KEY
Insulation 8/11/2022 Approved BOBBY KEY
Drywall Nailing 8/19/2022 Approved CLAYTON GRAHAM
Interior/Exterior Lathing 8/19/2022 Approved CLAYTON GRAHAM
BUILDING-Rough-Frame 10/20/2022 Approved BOBBY KEY
ELECTRICAL-Final 10/20/2022 Approved BOBBY KEY
Final 10/20/2022 Corrections Issued BOBBY KEY
Green Building Final 10/20/2022 Approved BOBBY KEY
Green Building Rough 10/20/2022 Approved BOBBY KEY
HVAC-Final 10/20/2022 Approved BOBBY KEY
PLUMBING-Final 10/20/2022 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 10/20/2022 SGSOV Approved BOBBY KEY
Smoke Detectors 10/20/2022 Approved BOBBY KEY
Final 11/8/2022 OK to Issue CofO BOBBY KEY