6326 N ETHEL AVE 91401
Certificate Information: 6326 N ETHEL AVE 91401
- Application / Permit
- 22014-20000-00870
- Plan Check / Job No.
- B22VN02962
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 30'-10" X 14' ATTACHED PATION COVER TO (E) SFD, ENCLOSER PORCH AND INTERIOR REMODEL.
- Permit Issued
- Issued on 5/27/2022
- Issuing Office
- Current Status
- CofO Issued on 7/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2022 | SERGIO MUNIZ |
| Corrections Issued | 3/4/2022 | SERGIO MUNIZ |
| Plan Check Approved | 5/4/2022 | SERGIO MUNIZ |
| Building Plans Picked Up | 5/5/2022 | APPLICANT |
| Issued | 5/27/2022 | APPLICANT |
| Re-Activate Permit | 6/5/2024 | OGANES TARAKHCHYAN |
| Permit Expired-Status Void | 6/5/2024 | OGANES TARAKHCHYAN |
| CofO in Progress | 6/14/2024 | OGANES TARAKHCHYAN |
| Permit Finaled | 7/17/2024 | RUBEN SALAS |
| CofO Issued | 7/17/2024 | RUBEN SALAS |
| Permit Finaled | 7/17/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/4/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 4/7/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Aronianpour,, Eilan; Lic. No.: C88101 | 7242 JELLICO AVE LAKE BALBOA, CA 91406 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/2/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2022 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 12/8/2022 | Conditional Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 12/19/2022 | Corrections Issued | MISAEL ESPARZA |
| Underground Mechanical | 12/19/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Deputy Drilled-In Anchors | 12/20/2022 | Conditional Approval | MICHAEL SMITH |
| Footing/Foundation/Slab | 12/21/2022 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 1/4/2023 | Partial Approval | KIRK SANDERS |
| ELECTRICAL-Rough | 1/4/2023 | Partial Approval | KIRK SANDERS |
| PLUMBING-Rough | 1/4/2023 | Partial Approval | KIRK SANDERS |
| Wood Frame | 1/4/2023 | Partial Approval | KIRK SANDERS |
| Deputy Wood Construction | 1/5/2023 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 1/6/2023 | Partial Approval | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2023 | Approved | KIRK SANDERS |
| Gas Test | 1/6/2023 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Rough | 1/6/2023 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 1/6/2023 | Partial Approval | KIRK SANDERS |
| Rough-Elec/Plmb/HVAC | 1/6/2023 | Partial Approval | KIRK SANDERS |
| ELECTRICAL-Rough | 2/7/2023 | Approved | KIRK SANDERS |
| Gas Test | 2/7/2023 | Not Ready for Inspection | KIRK SANDERS |
| PLUMBING-Rough | 2/7/2023 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 3/20/2023 | Approved | KIRK SANDERS |
| Insulation | 3/24/2023 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 3/24/2023 | Partial Approval | KIRK SANDERS |
| Interior/Exterior Lathing | 3/30/2023 | No Access for Inspection | KIRK SANDERS |
| Shower Pan | 3/30/2023 | No Access for Inspection | KIRK SANDERS |
| Drywall Nailing | 4/5/2023 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 4/5/2023 | Partial Approval | KIRK SANDERS |
| Shower Pan | 4/5/2023 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 6/29/2023 | Approved | KIRK SANDERS |
| Final | 5/6/2024 | Corrections Issued | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 5/6/2024 | SGSOV Approved | SALVADOR MARTINEZ |
| Smoke Detectors | 5/6/2024 | Approved | SALVADOR MARTINEZ |
| Final | 5/9/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Gas Test | 5/23/2024 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 5/23/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Final | 6/4/2024 | OK to Issue CofO | OGANES TARAKHCHYAN |
| PLUMBING-Final | 6/4/2024 | Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 6/6/2024 | No Access for Inspection | SALVADOR MARTINEZ |
| Service/Power Release | 6/11/2024 | Approved | OGANES TARAKHCHYAN |