8258 W JAYSEEL ST 91040
Certificate Information: 8258 W JAYSEEL ST 91040
- Application / Permit
- 22014-20000-00869
- Plan Check / Job No.
- B22VN02957
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 10'-5" X 42'-2" IRREGULAR SHAPED, 10'-5" X 14'-1", AND 9'-7" X 28'-1" ADDITIONS TO ENLARGE (E) SFD, NEW ATTACHED STORAGE AND TRELLIS PATIO COVER AND REMODEL BATHROOM. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 5/26/2022
- Issuing Office
- Current Status
- CofO Issued on 1/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2022 | RAPHAEL ROSAS |
| Corrections Issued | 3/6/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 5/5/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 5/18/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 5/24/2022 | APPLICANT |
| Issued | 5/26/2022 | APPLICANT |
| CofO in Progress | 1/13/2023 | WILLIAM WREN |
| Permit Finaled | 1/21/2023 | MICHAEL SMITH |
| CofO Issued | 1/21/2023 | MICHAEL SMITH |
| Permit Finaled | 1/21/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/9/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 3/9/2022 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 3/10/2022 | KIRK LINKLATER |
| Construction near power lines | Cleared | 4/13/2022 | WALTER RAMIREZ |
| Low Impact Development | Cleared | 4/20/2022 | KHAING AYE |
| Roof/Waste drainage to street | Cleared | 4/21/2022 | CARLOS AGUILERA |
| GPI Written Notices | Cleared | 5/4/2022 | RAPHAEL ROSAS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/23/2022 | Conditional Approval | MATTHEW NELSON |
| Footing/Foundation/Slab | 8/24/2022 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2022 | Approved | MATTHEW NELSON |
| Wood Frame | 8/30/2022 | Partial Approval | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2022 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 9/27/2022 | Approved | MATTHEW NELSON |
| Green Building Rough | 9/27/2022 | Approved | MATTHEW NELSON |
| Rough-Elec/Plmb/HVAC | 9/27/2022 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 10/3/2022 | Approved | MATTHEW NELSON |
| Shower Pan | 10/3/2022 | Approved | MATTHEW NELSON |
| Insulation | 10/7/2022 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 10/7/2022 | Approved | CALEB MEISTER |
| Drywall Nailing | 10/14/2022 | Approved | MATTHEW NELSON |
| Final | 1/9/2023 | Corrections Issued | WILLIAM WREN |
| Green Building Final | 1/9/2023 | Approved | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 1/9/2023 | SGSOV Approved | WILLIAM WREN |
| Smoke Detectors | 1/9/2023 | Approved | WILLIAM WREN |
| Final | 1/12/2023 | OK to Issue CofO | WILLIAM WREN |