702 1/4-3/4 E 108TH ST 90059

Certificate Information: 702 1/4-3/4 E 108TH ST 90059

Application / Permit
22014-20000-00853
Plan Check / Job No.
B22VN02922
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18' X 25' 4-CAR GARAGE TO (N) ADU AND CONVERT (E) 22' X 25' GARAGE/REC.ROOM TO (N) ADU. 3' X 18' ADDITION TO ATTACH THE 2 (N) ADUS. WORK DONE PER WFPP.
Permit Issued
Issued on 12/23/2022
Issuing Office
Current Status
CofO Issued on 6/13/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/28/2022 APPLICANT
Assigned to Plan Check Engineer 3/24/2022 SELLA BENYAMIN
Corrections Issued 3/30/2022 SELLA BENYAMIN
Quality Review Completed 4/5/2022 STEVEN KIM
Building Plans Picked Up 4/6/2022 APPLICANT
Plan Check Approved 12/23/2022 MADISON ODELL
Issued 12/23/2022 APPLICANT
CofO in Progress 6/12/2024 BEN MOLSTAD
Permit Finaled 6/13/2024 DONALD CRICHLOW
CofO Issued 6/13/2024 DONALD CRICHLOW
Permit Finaled 6/13/2024 DONALD CRICHLOW

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/9/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 7/29/2022 AMAAN MALIK
Sewer availability Cleared 7/29/2022 AMAAN MALIK
Address approval Cleared 11/29/2022 AMAAN MALIK

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/20/2023 Approved JOHN KLARIN
Footing/Foundation/Slab 11/27/2023 Approved JOHN KLARIN
Sewer 11/27/2023 Partial Inspection JOHN KLARIN
Underground Mechanical 11/27/2023 Partial Inspection JOHN KLARIN
BUILDING-Rough-Frame 12/28/2023 Partial Approval JOHN KLARIN
Green Building Rough 12/28/2023 Not Ready for Inspection JOHN KLARIN
PLUMBING-Rough 1/3/2024 Not Ready for Inspection JOHN KLARIN
PLUMBING-Rough 1/5/2024 Approved JOHN KLARIN
Gas Test 1/12/2024 Partial Approval JOHN KLARIN
Underground Mechanical 1/12/2024 Partial Approval JOHN KLARIN
Interior/Exterior Lathing 1/30/2024 Corrections Issued JOHN KLARIN
ELECTRICAL-Rough 1/31/2024 Approved JOHN KLARIN
Insulation 2/15/2024 Not Ready for Inspection BEN MOLSTAD
Shower Pan 2/15/2024 Not Ready for Inspection BEN MOLSTAD
HVAC-Rough 3/6/2024 Corrections Issued BEN MOLSTAD
Insulation 3/6/2024 Not Ready for Inspection BEN MOLSTAD
Shower Pan 3/6/2024 Not Ready for Inspection BEN MOLSTAD
HVAC-Rough 3/8/2024 Approved BEN MOLSTAD
Insulation 3/8/2024 Corrections Issued BEN MOLSTAD
Shower Pan 3/8/2024 Approved BEN MOLSTAD
Insulation 3/12/2024 Approved BEN MOLSTAD
Interior/Exterior Lathing 3/12/2024 Approved BEN MOLSTAD
Drywall Nailing 3/20/2024 Approved BEN MOLSTAD
Interior/Exterior Lathing 3/29/2024 Partial Approval BEN MOLSTAD
BUILDING-Rough-Frame 5/30/2024 Approved BEN MOLSTAD
ELECTRICAL-Final 5/30/2024 Corrections Issued BEN MOLSTAD
Final 5/30/2024 Corrections Issued BEN MOLSTAD
Green Building Final 5/30/2024 Not Ready for Inspection BEN MOLSTAD
Green Building Rough 5/30/2024 Approved BEN MOLSTAD
HVAC-Final 5/30/2024 Not Ready for Inspection BEN MOLSTAD
PLUMBING-Final 5/30/2024 Corrections Issued BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 5/30/2024 SGSOV Approved BEN MOLSTAD
Smoke Detectors 5/30/2024 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Final 6/6/2024 Not Ready for Inspection BEN MOLSTAD
Final 6/6/2024 Corrections Issued BEN MOLSTAD
Green Building Final 6/6/2024 Corrections Issued BEN MOLSTAD
HVAC-Final 6/6/2024 Not Ready for Inspection BEN MOLSTAD
PLUMBING-Final 6/6/2024 Approved BEN MOLSTAD
Smoke Detectors 6/6/2024 Corrections Issued BEN MOLSTAD
ELECTRICAL-Final 6/11/2024 Approved BEN MOLSTAD
Final 6/11/2024 OK to Issue CofO BEN MOLSTAD
Green Building Final 6/11/2024 Approved BEN MOLSTAD
HVAC-Final 6/11/2024 Approved BEN MOLSTAD
PLUMBING-Final 6/11/2024 Approved BEN MOLSTAD
Smoke Detectors 6/11/2024 Approved BEN MOLSTAD